CE 3026 Project Management - Exam 2 Review

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/38

flashcard set

Earn XP

Description and Tags

Vocabulary flashcards reviewing core concepts for CE 3026 Project Management Exam 2, covering contract law, delivery methods, surety bonds, cost estimating, retirement planning, and project manuals.

39 Terms

1
New cards

Contract

A legally enforceable agreement created when two or more competent parties agree to perform, or to avoid performing, certain acts that they have a legal right to do and that meet certain legal requirements.

2
New cards

General Contract Method

The most common contracting procedure, wherein the owner enters into a single contract with a general contractor who subsequently coordinates, hires, and oversees subcontractors and workers.

3
New cards

Separate Contracts Method

A contracting method in which the project owner enters into multiple separate, direct contracts with specialty contractors rather than contracting with a single general contractor.

4
New cards

Design-Construct Method (Design-Build / Turnkey)

A project delivery method where the owner awards a single contract for both the design and construction of a project, frequently used in industrial projects and enabling construction to begin before design is complete.

5
New cards

Construction Management Method (CM)

A delivery approach where a construction manager is hired on a fee basis to review the design for cost and time savings, assist the owner in achieving an economical project, and award separate contracts or a general contract.

6
New cards

Construction Management at Risk (CM at Risk)

A project delivery method where the construction manager serves as an independent contractor rather than an agent of the owner and assumes financial risk by providing a guaranteed maximum price.

7
New cards

Independent Contractor

A contractor who is neither an employee nor an agent of the owner; they are obligated only to meet the owner's final specifications, meaning their means and methods cannot be directed by the owner or engineer.

8
New cards

Agent–Principal Relationship

A fiduciary legal relationship (such as engineer to owner) in which the agent must display utmost loyalty and good faith, obey instructions, act with reasonable care and skill, communicate all project information, and turn over all profits to the principal.

9
New cards

Engineers Joint Contract Documents Committee (EJCDC)

A joint committee of ACEC, NSPE, and ASCE that creates standardized contract documents and templates for engineering and construction projects.

10
New cards

General Conditions

Contract documents consisting of 1717 articles that establish the ground rules for construction, outline administrative and bond/insurance procedures, and define the roles and duties of the contractor, owner, and engineer.

11
New cards

Supplementary Conditions

Contract provisions that expand, modify, or add specific project-by-project details to the standard General Conditions.

12
New cards

Addenda

Formal additions, deletions, or revisions made to the bidding requirements, drawings, specifications, or contract documents during the bidding period prior to contract execution.

13
New cards

Change Order

A written contract modification issued after the contract agreement has been signed that alters the work scope, contract price, or contract completion time.

14
New cards

Surety Bond

A three-party agreement in which a surety underwriter assumes responsibility for a contractor's capability, financial standing, and trustworthiness, guaranteeing contract performance to the owner.

15
New cards

Bid Bond

A bond guaranteeing that if a contractor submitting the lowest bid is awarded the contract and refuses to execute it, the surety will pay the owner the cost difference between that bid and the next lowest bid.

16
New cards

Performance Bond

A surety bond guaranteeing that the contractor will complete the project work in accordance with the plans and specifications for the agreed price and duration, typically written for 100%100\% of the contract price.

17
New cards

Payment Bond

A surety bond guaranteeing that the contractor will pay all laborers, suppliers, and subcontractors, thereby protecting the owner's property from mechanic's liens.

18
New cards

Mechanic's Lien

A statutory legal claim placed against real property by unpaid laborers, material suppliers, or subcontractors, which must be filed in court within 120120 days to recover owed costs.

19
New cards

Cost Estimating

The forward-looking process of forecasting and predicting future project costs and required resources to form the basis of a bid submittal.

20
New cards

Rough Estimate

A gut-level, early-stage estimate with an expected accuracy range of −30%-30\% to +60%+60\%.

21
New cards

Semi-Detailed Estimate

A reasonably sophisticated estimate based on historical records, exhibiting an accuracy range of −15%-15\% to +20%+20\%.

22
New cards

Detailed Estimate

A highly accurate estimate based on comprehensive specifications and structured cost models, typically having an accuracy range of −3%-3\% to +5%+5\%.

23
New cards

Parametric Estimating Method

A unit-based estimating technique that derives total costs by multiplying a comprehensive physical measurement unit (such as square footage or volume) by a cost per unit.

24
New cards

Segmenting Method

A bottom-up, divide-and-conquer estimating procedure that compiles detailed cost estimates for each individual work breakdown task and combines them with other necessary items to form the overall cost.

25
New cards

Quantity Takeoff

The process of measuring and compiling quantities of physical work items into standardized units of measurement (e.g., square feet, cubic yards) directly from project drawings.

26
New cards

Cost Index

A numerical value that tracks historical cost changes over time, applied via ratios to update historical costs from past dates to current or future time periods.

27
New cards

Learning Curve

The industrial concept establishing that as cumulative production output doubles, unit production time decreases by a predictable, fixed percentage.

28
New cards

Engineer's Estimate

A cost estimate prepared once design is complete that achieves approximately ±3%\pm 3\% accuracy to verify that the project is within the owner's budget and to serve as a benchmark for evaluating bids.

29
New cards

Bid Estimate

A contractor-prepared cost projection based on final confirmed drawings that incorporates markups for overhead and anticipated profit.

30
New cards

401(k) Plan

A defined contribution retirement plan where employees contribute pre-tax earnings from payroll into market investments, frequently matched by employers at rates between 2%2\% and 15%15\%.

31
New cards

Pension

A defined benefit retirement plan that guarantees a fixed monthly dollar distribution for the remainder of a retiree's life.

32
New cards

Required Minimum Distribution (RMD)

The mandatory annual withdrawal amount that an individual must begin taking from their tax-deferred retirement accounts upon reaching age 7474.

33
New cards

Dollar-Cost Averaging

An investment strategy of allocating fixed dollar amounts on a consistent schedule, which buys more fund shares when market prices decline and fewer shares when prices rise.

34
New cards

Project Manual

The comprehensive bound document containing all the written non-drawing components of an engineering project, including bidding instructions, contract conditions, and technical specifications.

35
New cards

Construction Drawings

Graphic representations showing the form, dimensions, physical relationships, and quantities of construction materials, products, and assemblies.

36
New cards

Technical Specifications

Written construction documents establishing the qualitative standards, material types, and workmanship performance required under the construction contract.

37
New cards

CSI Section Format

The standard organizational structure for each individual specification section, consisting of three mandatory, fixed-order parts: Part 1 - General, Part 2 - Products, and Part 3 - Execution.

38
New cards

CSI MasterFormat Division 00

The MasterFormat category dedicated to Procurement and Contracting Requirements, containing advertisements, bid instructions, bid forms, bonds, and general/supplementary conditions.

39
New cards

CSI MasterFormat Division 01

The MasterFormat category designated for General Requirements, specifying procedural, operational, and administrative criteria including work summaries, measurement, and payment.