BUS2 190 Exam 2: Ch 6-9 (Sensitivity Analysis + Supply Chain Models)

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/71

flashcard set

Earn XP

Description and Tags

Built from the Exam 2 study guide, lecture slides, Quiz 3 and 4, and sensitivity practice problems. Ch 6 & 7 sensitivity analysis, Ch 8 & 9 transportation and transshipment.

72 Terms

1
New cards

Sensitivity analysis

Used to determine how the optimal solution is affected by changes in (1) the objective function coefficients and (2) the right-hand side (RHS) values.

2
New cards

Why is sensitivity analysis also called postoptimality analysis?

Because it begins only after the optimal solution to the original linear programming problem has been found.

3
New cards

Sensitivity analysis is concerned with how certain changes affect the ______ solution.

Optimal solution

4
New cards

Range of optimality

The range of an objective function coefficient over which the current solution stays optimal. It's the amount a coefficient can change before a different set of decision variable values becomes optimal.

5
New cards

Rule: when does the optimal solution stay the same after an objective coefficient changes?

When the slope of the new objective function line is still between the slopes of the binding constraints. If it falls outside that range, you have to find a new optimal solution.

6
New cards

How do you find the slope of a constraint or objective function?

Rewrite it in y = ax + b form (solve for the y variable). The slope is a. Shortcut: for aX + bY = c, slope = -a/b.

7
New cards

Slope of the constraint X + Y = 10

Y = -X + 10, so slope = -1

8
New cards

Slope of the constraint 8X + 2Y = 10

2Y = -8X + 10, so Y = -4X + 5, slope = -4

9
New cards

Slope of the objective function Z = 2X + Y

Y = -2X + Z, so slope = -2

10
New cards

Max 2X + Y s.t. X + Y ≤ 10, 8X + 2Y ≤ 10. Does the objective lead to the same optimal solution?

Constraint slopes are -1 and -4, objective slope is -2. Since -4 ≤ -2 ≤ -1, the slope is between the two binding constraints, so the optimal solution stays the same.

11
New cards

Par, Inc.: when does extreme point 3 (S = 540, D = 252) stay optimal?

When -3/2 ≤ slope of the objective function ≤ -7/10. Line B (finishing): D = -3/2 S + 1062. Line A (cutting and dyeing): D = -7/10 S + 630.

12
New cards

Practice: Max 3A + 2B s.t. A + B ≤ 10, 3A + B ≤ 24. What are the constraint slopes and the optimality range?

Constraint 1: B = -A + 10 (slope -1). Constraint 2: B = -3A + 24 (slope -3). Optimal solution stays the same as long as -3 ≤ objective slope ≤ -1. Optimal solution: A = 7, B = 3.

13
New cards

Practice: Max 3A + 2B s.t. A + B ≤ 10, 3A + B ≤ 24. Coefficient of A changes from 3 to 5. Does the optimal solution change?

New objective 5A + 2B gives B = -2.5A + 0.5P, slope -2.5. Since -3 ≤ -2.5 ≤ -1, it does NOT change. Still A = 7, B = 3.

14
New cards

Practice: Max 3A + 2B s.t. A + B ≤ 10, 3A + B ≤ 24. Coefficient of B changes from 2 to 4. Does the optimal solution change?

New objective 3A + 4B gives B = -0.75A + 0.25P, slope -0.75. That is NOT between -3 and -1, so YES it changes. New optimal solution: A = 0, B = 10.

15
New cards

Practice Problem 1: Max Z = 3A + 2B s.t. A + B ≤ 6, 2A + B ≤ 8. Constraint slopes and optimal solution?

Constraint 1: B = -A + 6 (slope -1). Constraint 2: B = -2A + 8 (slope -2). Objective slope is -3/2, which is between -2 and -1, so the optimal solution is the intersection: A = 2, B = 4 (Z = 14).

16
New cards

Practice Problem 1 (Max 3A + 2B, A + B ≤ 6, 2A + B ≤ 8): coefficient of A changes from 3 to 4. Does the optimal solution change?

New Z = 4A + 2B, so B = -2A + 1/2 Z, slope -2. Still within -2 ≤ slope ≤ -1 (right on the edge), so A = 2, B = 4 is still optimal.

17
New cards

Practice Problem 1 (Max 3A + 2B, A + B ≤ 6, 2A + B ≤ 8): coefficient of B changes from 2 to 5. Does the optimal solution change?

New Z = 3A + 5B, so B = -3/5 A + 1/5 Z, slope -3/5. Not between -2 and -1, so YES it changes. New optimal: A = 0, B = 6 (Z = 30).

18
New cards

Practice Problem 2: Max Z = 5A + 2B s.t. A + B ≤ 8, A + 2B ≤ 10. Constraint slopes and optimal solution?

Constraint 1: B = -A + 8 (slope -1). Constraint 2: B = -1/2 A + 5 (slope -1/2). Objective slope is -5/2, steeper than both, so the optimal is the extreme point A = 8, B = 0 (Z = 40).

19
New cards

Practice Problem 2 (Max 5A + 2B, A + B ≤ 8, A + 2B ≤ 10): coefficient of A changes from 5 to 1. Does the optimal solution change?

New Z = A + 2B, so B = -1/2 A + 1/2 Z, slope -1/2. The slope is no longer steeper than -1, so YES it changes. It now matches constraint 2's slope, so (6, 2) and (0, 5) both give Z = 10 (alternative optimal solutions).

20
New cards

Practice Problem 2 (Max 5A + 2B, A + B ≤ 8, A + 2B ≤ 10): coefficient of B changes from 2 to 3. Does the optimal solution change?

New Z = 5A + 3B, so B = -5/3 A + 1/3 Z, slope -5/3. Still steeper than -1, so NO change. Optimal stays A = 8, B = 0.

21
New cards

Changes in the right-hand side (RHS)

Changing a constraint's RHS shifts that constraint line, which changes the feasible region and can change the optimal solution and the objective function value.

22
New cards

Par, Inc.: what happens with 10 more hours of cutting and dyeing time (630 to 640)?

The feasible region expands. New optimal solution: S = 527.5, D = 270.75. Profit goes from $7,668.00 to $7,711.75, an increase of $43.75.

23
New cards

Reduced cost (decision variables)

The amount by which the objective function coefficient of a decision variable must improve before that variable becomes part of the optimal solution (if it is currently not in the solution).

24
New cards

What does a reduced cost of zero mean?

The decision variable is already part of the optimal solution.

25
New cards

Reduced cost in a MAXIMIZATION problem

Negative reduced cost: increasing the objective coefficient (profit) makes it more attractive to include. Zero: already in the solution. Positive reduced cost is NOT possible.

26
New cards

Reduced cost in a MINIMIZATION problem

Positive reduced cost: decreasing the objective coefficient (cost) makes it more attractive to include. Zero: already in the solution. Negative reduced cost is NOT possible.

27
New cards

Dual value (shadow price)

How much the objective function value changes per one-unit increase or decrease in the RHS of a constraint, with everything else held constant.

28
New cards

What does a shadow price of zero mean?

The constraint is non-binding (slack or surplus > 0). Changing its RHS has no impact on the optimal objective function value.

29
New cards

Binding constraint

Slack or surplus = 0 and shadow price > 0. The resource is fully used, so increasing its availability would improve the objective (profit).

30
New cards

Non-binding constraint

Slack or surplus > 0 and shadow price = 0. There is unused capacity, so increasing the RHS will not improve the objective function.

31
New cards

Par, Inc. shadow prices from the sensitivity report

Cutting and dyeing = 4.375, Finishing = 6.9375, Sewing = 0, Inspection and packaging = 0. One more hour of cutting and dyeing adds about $4.38 of profit; one more hour of finishing adds about $6.94.

32
New cards

Par, Inc.: which constraints are binding and which are non-binding?

Binding: Cutting and dyeing (4.375) and Finishing (6.9375). Non-binding: Sewing and Inspection and packaging (shadow price 0, unused capacity).

33
New cards

Allowable increase / allowable decrease (RHS)

As long as the RHS doesn't change by more than the allowable increase or decrease, the shadow price gives the exact change in the objective value per unit change in the RHS.

34
New cards

Range of feasibility

The range of RHS values over which the dual value (shadow price) stays valid. Formula: (RHS - allowable decrease, RHS + allowable increase).

35
New cards

The range of feasibility measures…

The right-hand-side values for which the dual prices (shadow prices) will not change.

36
New cards

Par, Inc. finishing constraint: RHS 708, allowable increase 192, allowable decrease 128. Range of feasibility?

(708 - 128, 708 + 192) = (580, 900)

37
New cards

Par, Inc. cutting and dyeing: RHS 630, allowable increase 52.36, allowable decrease 134.4. Range of feasibility?

(630 - 134.4, 630 + 52.36) = (495.6, 682.36)

38
New cards

Par, Inc. Standard bag: objective coefficient 10, allowable increase 3.5, allowable decrease 3.7. Range of optimality?

(10 - 3.7, 10 + 3.5) = 6.3 to 13.5

39
New cards

Par, Inc. Deluxe bag: objective coefficient 9, allowable increase 5.2857, allowable decrease 2.3333. Range of optimality?

(9 - 2.3333, 9 + 5.2857) = about 6.67 to 14.29

40
New cards

Excel Solver sensitivity report: what's in the Variable (Adjustable) Cells section?

Final Value, Reduced Cost, Objective Coefficient, Allowable Increase, Allowable Decrease (used for the range of optimality).

41
New cards

Excel Solver sensitivity report: what's in the Constraints section?

Final Value, Shadow Price, Constraint R.H. Side, Allowable Increase, Allowable Decrease (used for the range of feasibility).

42
New cards

Cautionary note: how is the dual value interpreted when the RHS is the amount of a resource available?

As the maximum amount you should be willing to pay for one additional unit of that resource.

43
New cards

Sunk cost

A cost that has already been paid or must be paid no matter what, so it doesn't change based on decisions. NOT reflected in the objective function coefficients. The dual value shows the full value (profit) an additional unit adds.

44
New cards

Relevant cost

A cost that depends on the decision being made. It IS reflected in the objective function coefficients. The dual value shows how much the resource's value exceeds its cost (the net benefit of getting more).

45
New cards

Par, Inc.: why are the 630 labor hours a sunk cost?

Par has to pay for those hours whether they use them fully or not, so the cost is already committed and isn't part of the decision.

46
New cards

True or False: The amount of a sunk cost will vary depending on the values of the decision variables.

False. Sunk costs don't change based on decisions.

47
New cards

Limitation of classical sensitivity analysis: simultaneous changes

It assumes only ONE coefficient changes at a time while everything else stays fixed. If two or more change at once, further analysis is needed.

48
New cards

True or False: When two or more objective function coefficients change simultaneously, further analysis is necessary to determine whether the optimal solution will change.

True

49
New cards

Limitation of classical sensitivity analysis: constraint (LHS) coefficients

It doesn't tell you how the solution changes if a coefficient of a constraint (like a resource usage rate) is modified.

50
New cards

Transportation problem: usual objective

Minimize the cost of shipping goods from several origins to several destinations.

51
New cards

Transportation network: nodes vs arcs

Each origin and each destination is a node. Each possible shipping route is an arc.

52
New cards

Transportation decision variable xij

The number of units shipped from origin i to destination j.

53
New cards

Constraint signs in a transportation problem

Supply constraints are "≤" and demand constraints are "=".

54
New cards

Number of decision variables in a transportation LP

of origins x # of destinations

55
New cards

Number of constraints in a transportation LP

of origins + # of destinations

56
New cards

True or False: A transportation problem with three sources and four destinations will have seven decision variables.

False. It has 3 x 4 = 12 decision variables (7 is the number of constraints).

57
New cards

True or False: If a transportation problem has four origins and five destinations, the LP formulation will have nine constraints.

True. 4 + 5 = 9 constraints (and 20 decision variables).

58
New cards

Foster Generators example: 3 plants (Cleveland 5000, Bedford 6000, York 2500) and 4 distribution centers (Boston, Chicago, St. Louis, Lexington). How many variables and constraints?

12 decision variables (3 x 4) and 7 constraints (3 + 4).

59
New cards

Write the LP: Origins 1 (100), 2 (200), 3 (300). Destinations A (300), B (300). Costs: 1A=2, 1B=4, 2A=3, 2B=5, 3A=7, 3B=6.

Min 2X1A + 4X1B + 3X2A + 5X2B + 7X3A + 6X3B s.t. X1A + X1B ≤ 100; X2A + X2B ≤ 200; X3A + X3B ≤ 300; X1A + X2A + X3A = 300; X1B + X2B + X3B = 300; all xij ≥ 0.

60
New cards

Variation: total supply EXCEEDS total demand

No change to the LP formulation is needed. Excess supply shows up as slack, which is the unused supply (amount not shipped) at that origin.

61
New cards

Variation: total supply is LESS THAN total demand

The LP has no feasible solution. Fix it by adding a dummy origin (fake supplier) with supply equal to total demand minus total supply.

62
New cards

Variation: maximization objective in a transportation problem

Use profit or revenue per unit as the objective coefficients and solve a maximization LP. The constraints do not change.

63
New cards

Variation: unacceptable routes

If a route isn't possible, remove the corresponding variable from the LP formulation.

64
New cards

True or False: When a route in a transportation problem is unacceptable, the corresponding variable can be removed from the LP formulation.

True

65
New cards

Transshipment problem

An extension of the transportation problem that adds intermediate nodes, called transshipment nodes, for locations like warehouses.

66
New cards

Objective of the transshipment problem

Determine how many units should be shipped over each arc in the network to satisfy destination demand at the minimum transportation cost.

67
New cards

Transshipment node constraint

Flow out - flow in = 0 (everything that comes in must go out). Example: -x13 - x23 + x35 + x36 + x37 + x38 = 0

68
New cards

Number of decision variables in a transshipment LP

(# of origins x # of transshipment points) + (# of transshipment points x # of destinations)

69
New cards

Number of constraints in a transshipment LP

of origins + # of transshipment points + # of destinations

70
New cards

Ryan Electronics transshipment example: 2 plants (Denver 600, Atlanta 400), 2 warehouses (Kansas City, Louisville), 4 retail outlets (Detroit 200, Miami 150, Dallas 350, New Orleans 300). Variables and constraints?

12 variables: (2 x 2) + (2 x 4). 8 constraints: 2 + 2 + 4.

71
New cards

Ryan Electronics: what do the constraints look like?

Plant supply: x13 + x14 ≤ 600 and x23 + x24 ≤ 400. Warehouses: flow out - flow in = 0. Retail demand: x35 + x45 = 200, x36 + x46 = 150, x37 + x47 = 350, x38 + x48 = 300.

72
New cards

In a transshipment problem, shipments…

Can occur between any two nodes.