principles, pre-tensioning, eccentricity
what is the neutral axis?
the cross section of the beam where there are no longitudinal stresses
why is reinforcement needed in concrete?
concrete is strong under tension but weak in compression, when a force is applied cracks are developed and so reinforcement is needed to bear the tensile stresses
what is pre-stressed concrete?
pre-compressed concrete where compressive stresses are applied prior to service using high strength steel
what are some of the benefits of prestressing concrete?
eliminates tensile stresses
concrete section is fully operative as there is no cracked zone
cross-section can be reduced (efficiency)
composite section remains elastic in service if no tension is allowed
deflection can be substantially reduced
what benefit is provided if all sections can contribute to load bearing capacity?
there is no cracked zone that increases self-weight without providing resistance so longer spans can be bridged
what are the different types of steel used for pre-stressing?
cold-drawn wires
3 or 7 wire strands
multi-strand tendons
where are cold-drawn wires applied?
architectural structures, precast concrete joists
where are 3 or 7 wire strands applied?
a wide range of precast concrete elements e.g. bridges
how is ultimate strength (fuk) calculated?
k x fyk where k>1.08 and fyk = yield strength
what is fp0.1k?
characteristic proof stress, the stress producing 0.1% permanent strain
what is fpk?
characteristic rupture stress, the ultimate tensile strength where prestressed steel breaks
how is design stress (fpd) for prestressed steel determined?
fpd=fp0.1k / 1.15
how is stress calculated before proof stress is reached?
Ļ=Epε
what is Ep for wires and bars, and strands and tendons?
195000 N/mm2 for wires and bars, 200000 N/mm2 for strands and tendons
what happens to stress of prestressed steel after proof stress is reached?
in the design model (Eurocode), a horizontal plateau at fpd is assumed for simplicity
what are the preparation steps when pretensioning concrete?
assemble, clean and demould casting bed and formwork
position strands (watch centring and distances between strands)
stress and lock off strands
how are strands tensioned and anchored?
strands are tensioned and the barrel is positioned
the wedges are positioned
the strands are released and prestress is transferred
describe the manufacturing sequence in pre-tensioning systems?
strands are tensioned
concrete is cast
transfer, strands are cut, prestress force is transferred and jacks are removed
once the concrete is cast, how long do strands remain stressed for?
until the concrete has developed enough compressive strength, usually 1-3 days
in an axially prestressed beam, why is there eccentricity?
there is a zone in tension due to the external moment but the prestressing force adds compression to all the fibres, resulting in the whole section being under compression
where does the maximum decompression occur?
at the bottom fibre in service because Mserv>Msw
what is the benefit of an eccentric prestress?
it is more efficient than axial prestress as:
for a given Mserv P can be reduced with eccentricity (more economical)
for a given P, maximum Mserv is increased increasing capacity
a more uniform stress distribution is achieved in the cross-section
what happens to the beam as a result of the eccentricity?
the beam cambers at the stage of transfer
applying prestressing force eccentrically induces a predeformation
deflection in service is minimised
what happens to the top fibre at transfer?
the top fibre is partially de-compressed or even put into tension