1/38
Non-Compliant
The Architect, due to oversight or other factors, fails to immediately condemn a section of work that is later discovered to be defective. The Contractor, aware of the issue, assumes that the work is accepted and proceeds to correct it on their own initiative before the final acceptance by the Owner.
Non-Compliant
During construction, the Contractor encounters unforeseen field conditions that require adjustments to the original drawings. The Contractor immediately submits the discrepancy of 6% margin to the Architect, explaining the necessity of the changes. However, due to the urgency of continuing the work, the Contractor proceeds with some minor adjustments without waiting for formal approval.
Non-Compliant
The architect writes to the contractor asking for the removal of a mechanic who was reportedly careless during a recent task. The contractor immediately complies, sending a formal response confirming the mechanic’s dismissal from the project. However, a few weeks later, the contractor assigns the same mechanic to a less visible task on-site, believing the initial issue was resolved.
Non-Compliant
The contractor observes that a minor leak in the site’s water line might eventually damage some materials, though it poses no immediate threat to safety or the integrity of the work. Acting on their own discretion, they repair the issue and submit a claim for emergency compensation.
Compliant
The Contractor is using a method or appliance that, while efficient in general, initially seems slow to the Architect due to its unfamiliarity. The ARchitect requests an increase in efficiency. In response, the Contractor makes minor adjustments to the system, which results in improved quality and progress, aligning with required standards.
Compliant
The Project Engineer seems to be following the instructions and directives of the Architect without delay, executing orders and ensuring materials, tools, and labor are supplied as needed. However, in the absence of the Contractor, the Project Engineer lacks the necessary authority to make certain key decisions on the project.
Compliant
The Architect condemns a section of the work due to a minor defect. The Contractor, in response, immediately takes the condemned work out and begins rebuilding it according to the specifications. However, the process takes a little longer than anticipated, leading to temporary delays. The Contractor is still fully compliant by addressing the issue promptly and rebuilding the work in accordance with the drawings and specifications.
Non-Compliant.
A sudden emergency occurs on the site, such as a structural failure that poses a risk to life and property. The Contractor immediately takes action, performing the necessary work to not affect his timeline. However, the Contractor does not notify the Architect and Engineer immediately due to the urgency of the situation, sending the notice slightly later.
Compliant
The Architect condemns a section of the work due to a minor defect. The Contractor, in response, immediately takes the condemned work out and begins rebuilding it according to the specifications. However, the process takes a little longer than anticipated, leading to temporary delays. The Contractor is still fully compliant by addressing the issue promptly and rebuilding the work per the drawings.
Non-Compliant
The Contractor submits the required information and evidence for approval, but the documents are delivered slightly late due to a delay in gathering details from the manufacturer. Despite this, the information provided is complete and meets all the necessary requirements, including performance capacities and manufacturer details.
Non-Compliant
The Architect requires an examination of certain completed work, suspecting it might be defective. The Contractor promptly provides the necessary labor and materials for the examination. Upon review, it turns out the work is in full compliance with the contract. However, the examination process results in some additional work that temporarily delays the project. The Contractor requests reimbursement for the labor and materials involved, plus a 10 % markup, and a suitable extension of time due to the delay.
Compliant
The Owner and Architect wish to inspect a particular area of the work, but due to ongoing operations, there is some minor obstruction or temporary equipment that makes access difficult. However, the Contractor immediately clears the path and provides access only to certain areas or restricts movements to specific times.
Non-Compliant
The Contractor appears to be complying by following the prescribed methods and appliances, and the work is progressing according to schedule. However, upon closer inspection, the quality of the work is subpar, or the progress rate is slower than it should be, even if the Architect hasn’t yet demanded improvements.
Compliant
The Architect suspects that part of the completed work is not in accordance with the plans and specifications and requests an examination. The Contractor promptly provides the necessary facilities, labor, and materials to uncover the work, as requested. However, during the examination, it is revealed that the work is actually in compliance, but the process of removing or tearing out parts of it temporarily disrupts the construction process.
Non-Compliant
The Architect requests an examination of certain completed work, suspecting it might be defective. The Contractor promptly provides the necessary labor and materials for the examination. Upon review, it turns out the work is in full compliance with the contract. However, the examination process results in some additional work that temporarily delays the project. The Contractor requests reimbursement for the labor and materials involved, plus a 15% markup, and a suitable extension of time due to the delay.
Compliant
The Contractor provides all the necessary facilities, and materials for inspection and tests promptly. However, the timing of the inspection interferes with the ongoing work, causing a brief delay.
Non-Compliant
The contractor is present on-site daily but does not hold a valid license as an engineer or architect. They supervise the work closely and inspect the construction every week.
Non-Compliant
The Contractor places all the required stakes and benchmarks accurately, but during the work, a slight disturbance occurs due to a heavy piece of equipment unintentionally moving a stake. The Contractor quickly notices the issue and replaces the stake at their own expense without being prompted by the Architect.
Non-Compliant
The Project Engineer is on-site and receives all directions from the Architect promptly, following through on every instruction without delay. However, the Project Engineer occasionally seeks the Contractor’s approval before executing some larger orders, causing delays in response.
Non-Compliant
The Contractor gives timely notice for the inspection of the work, but the Architect is delayed in attending the inspection due to scheduling conflicts. The work is ready, but because the Architect cannot inspect it promptly, the Contractor proceeds with covering part of the work as planned. The Architect later requests to uncover the work and the Contractor complies at their own expense.
Compliant
The Architect orders a re-examination of some questioned work, and the Contractor promptly uncovers the work for inspection. However, the work is found to meet all the requirements of the contract, and no issues are discovered.
Non-Compliant
During construction, the Contractor encounters unforeseen field conditions that require adjustments to the original drawings. The Contractor immediately submits the discrepancy of 5% margin to the Architect, explaining the necessity of the changes. However, due to the urgency of continuing the work, the Contractor proceeds with some minor adjustments without waiting for formal approval.
Non-Compliant
During a heavy storm, the contractor notices that part of the site’s scaffolding is at risk of collapsing, potentially endangering workers and adjoining property. Without consulting the architect or owner, the contractor immediately reinforces the scaffolding, preventing any damage or injuries. Later, they submit a claim for the emergency work but provide minimal details about the incident.
Compliant
A sudden emergency occurs on the site, such as a structural failure that poses a risk to life and property. The Contractor immediately takes action, performing the necessary work and installing temporary safety measures to protect life and property. However, the Contractor does not notify the Architect and Engineer immediately due to the urgency of the situation, sending the notice slightly later.
Compliant
The Contractor continues to use the original methods and appliances, which are slightly less efficient than expected. However, the quality of work remains high, and the project progresses steadily within the agreed timeline. The Architect does not request any changes, but the Contractor has already ensured that the work meets the required quality and progress as specified in the contract.
Compliant
The Contractor gives timely notice for the inspection of the work, but the Architect is delayed in attending the inspection due to scheduling conflicts. The work is ready, but because the Architect cannot inspect it promptly, the Contractor proceeds with covering part of the work as planned. The Architect later requests to uncover the work and the Contractor complies and includes it in the billing.
Non-Compliant
The architect submits a written request to the contractor to remove a foreman they believe is slowing the project's progress. The contractor, while respecting the architect's concerns, conducts an internal review and finds the issue was due to miscommunication rather than the foreman's competence. Without explicitly informing the architect, the contractor reassigns the foreman to a different role off-site while ensuring another qualified individual replaces him on-site.
Compliant
The Architect, due to oversight or other factors, fails to immediately condemn a section of work that is later discovered to be defective. The Contractor, aware of the issue, does not assume that the work is accepted and proceeds to correct it on their own initiative before the final acceptance by the Owner.
Compliant
The Owner and Architect wish to inspect a particular area of the work, but due to ongoing operations, there is some minor obstruction or temporary equipment that makes access difficult. However, the Contractor immediately clears the path and provides proper access, ensuring the inspection can take place without delay.
Non-Compliant
The Contractor is using methods and appliances that appear to be in line with the contract specifications. However, over time, the quality of work starts to fall short and the rate of progress slows, prompting the Architect to intervene.
Compliant
The Contractor provides all the necessary facilities, labor, and materials for inspection and tests promptly. However, the timing of the inspection interferes with the ongoing work, causing a brief delay.
Compliant
The Contractor begins laying out the lines and grades of the work as specified, but due to a misinterpretation of the site conditions, the initial layout seems slightly off to the Architect. However, upon further inspection, it was revealed that the discrepancy was minor and had no impact on the overall construction process, with the lines and grades eventually meeting the specified conditions.
Non-Compliant
The architect raises concerns about a laborer who is reportedly slowing down progress and requests their removal. The contractor evaluates the complaint and, instead of outright dismissing the laborer, reassigns them to an administrative support role that does not affect the pace of work. However, the contractor does not communicate this reassignment to the architect.
Compliant
The Architect orders a re-examination of the questioned work, and the Contractor uncovers the work for inspection. However, upon inspection, it is discovered that the work does not conform to the contract documents. The contractor rectifies everything and then requests for billing.
Compliant
The Project engineer begins laying out the lines and grades of the work as specified, but due to a misinterpretation of the site conditions, the initial layout seems slightly off to the Architect. However, upon further inspection, it was revealed that the discrepancy was minor and had no impact on the overall construction process, with the lines and grades eventually meeting the specified conditions.
Compliant
The contractor/engineer supervises the work personally, but they have delegated the inspections to a trusted senior foreman who conducts the weekly inspections and sends reports. The contractor is not directly inspecting the work but still oversees the overall progress and quality.
Compliant
The Engineer suspects that part of the completed work is not in accordance with the plans and specifications and requests an examination. The Contractor promptly provides the necessary facilities, labor, and materials to uncover the work, as requested. However, during the examination, it is revealed that the work is actually in compliance, but the process of removing or tearing out parts of it temporarily disrupts the construction process.
Non-Compliant
The Contractor places all the required stakes and benchmarks accurately, but during the work, a slight disturbance occurs due to a heavy piece of equipment unintentionally moving a stake. The Contractor quickly notices the issue and replaces the stake without being prompted by the Architect. He later requested for an additional payment.
Compliant
The Contractor decides to use a less common method or appliance to carry out certain operations, which initially seems inefficient or unconventional to the Architect. However, the chosen method actually results in a higher quality of work and maintains the expected rate of progress, ensuring timely completion of the project.