Municipal Exam 3: Drinking Water

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/30

encourage image

There's no tags or description

Looks like no tags are added yet.

31 Terms

1
New cards

Differences between wastewater and water?

  • Smaller pipes in water system generally 8” or less

  • Valves and hydrants

  • Pressure pipes everywhere

  • No flow direction

  • Looped

  • Storage


2
New cards

Characteristics of a Properly Functioning System

  1. Redundancy: water main break or contamination only effects a small portion of the system

  2. Quality: water leaving treatment plant is safe to drink throughout the entire system

  3. Quantity: ability to meet demands at all times

  4. Access


3
New cards

NR 811.70 Water Main Design

  1. Point of entry quality: maintained quality throughout the entire system

  2. Multidirectional flow: redundancy

  3. Adequate shut off valves: allows us to isolate a problem

  4. Adequate fire protection (hydrants)

  5. Adequate flushing

  6. Maximize turnover, minimize dead ends: stagnant water can have bacterial presence, organic matter can form carcinogens or disinfection by-products

  7. Palatability

  8. Deliver code complying pressure and flow


4
New cards

NR 811.70 Pressure

  • Sized based on hydraulic analysis for flow and pressure

  • Static pressure must be > 35 psi and < 100 psi

  • Minimum residual pressure must be above 20 psi at ground level for any flow

    • Static pressure: demand we see under normal conditions

    • Residual pressure: remain in the system when there is a high demand during say a fire


5
New cards

NR 811.70 Size and Fire Protection

  • Water mains that provide fire protection must be greater than or equal to 6 in

  • Minimum flow requirement is 500 gpm at 20 psi residual pressure


6
New cards

NR 811.70 Dead End and Valves

  • Dead ends

    • Minimized by looping

    • If they occur, they should terminate with a fire hydrant or flushing hydrant

  • Valving

    • No more than 500 ft in commercial, 800 ft in other districts


7
New cards

Why does pressure vary during the day?

  • High pressure at night

  • Pressure cycles through the day

  • Drop in pressure around 8 am then recovers mid day and then drops again around 5 pm

    • Drop because of high demands → draining storage

    • Then pumps kick on and begin filling tower

    • Another drop around 5 pm


8
New cards

Why does pressure vary with pipe size?

  • Q =vA

    • Small A = high v = higher headloss

    • small pipes = larger headloss → decreasing pressures


9
New cards
<p>How would an increase in demand affect pressure variation graphs </p>

How would an increase in demand affect pressure variation graphs

  • sharper and deeper declines with high demands


10
New cards
<p>What would the curves look like for an infinite diameter pipe? </p>

What would the curves look like for an infinite diameter pipe?

  • It would look similar to the 12 and 16” pipe curve


11
New cards
<p>How many ft does the water level in the storage tank vary? </p>

How many ft does the water level in the storage tank vary?

  • Look at pipes with no friction losses

    • High point = 53 psi

    • Low Point = 40 psi

53- 40 = 13 psi * (2.3 ft/psi) = 30 ft of variation


12
New cards
<p>Pipes in Series </p>

Pipes in Series

  • Q1 = Q2 = Q3 = Qn

  • hL tot = hL1 + hL2 + hL3 + hLn


13
New cards

Pipes in Parallel

  • Qtot = Q1 + Q2 + Q3 + Qn

  • hL1 = hL2 = hL3 = hLn


14
New cards

Importance of loops

  • Water quality

  • Redundancy

  • Hydraulic Performance


15
New cards

What do we do when it is not possible to have everyone on ONE zone?

Create Pressure Zones

16
New cards

Pressure Zone

  • Zone of similar pressure

    • We can create them through the use of network separation and valves

      • Pressure reducing valves


17
New cards

How to address water demands on the supply side?

  • Building a new reservoir

  • Increasing reservoir size

  • Increasing height of a dam

  • Putting pumps in


18
New cards

How to address water demands on the demand side?

  • Increasing efficiencies through conservation practices

  • Pricing policy

  • Effect behavioral changes


19
New cards

Water hammer

  • Pressure wave phenomenon created by sudden changes in fluid velocity

    • valve or pumps

    • vapor pocket collapse

    • rapid expulsion of air out of vent or partially closed valve


20
New cards

Explain the purpose of the public service commission (PSC)

  • The mission is to oversee and facilitate the efficient and fair provision of quality utility services in Wi

  • Excellent information on a utility - specifically financial and physical information

  • Sectoral breakdown of water usage and sales


21
New cards

Discuss the significance of unaccounted for water and define the different types

  • Non-revenue water

    • percentage of water loss

      • 5% is really low

      • Typically teens or up to 25% ish

      • Higher is a red flag

  • Types

    • Real Losses: These are actual water losses from the system before it reaches the customer (leaks)

    • Apparent Losses: These are losses that occur but are not due to physical leakage (metering discrepancies, billing anomalies, unauthorized usage)


22
New cards

Explain the danger in cross connections

  • Actual or potential connections between potable and non-potable water supply, constitute a serious public health hazard

  • Backflow (non‑potable source at higher pressure forces wastewater into the water main)

  • Backsiphonage (pressure drop pulls wastewater in


23
New cards

Three fundamental purposes of storage

  1. Emergency supply

    1. ~25% of total storage capacity

  2. Fire Protection (Conflagaration)

    1. 4h for fire flow more than 4000 gpm, 2h 2750 gpm

  3. Equalizing/Operating Storage

    1. Usually 15-20% of days supply


24
New cards

Fire Hydrants

  • Shall be provided at each street intersection

  • Spacing may range from 350 t0 600 ft

  • Connecting main between the supply main and the hydrant shall be a minimum of 6 in in diameter

  • 500 gpm at 20 psi


25
New cards

Hydrant Test Steps

  1. Locate hydrant(s) to be tested- inform public works

  2. Place gage on hydrant that will be residual hydrant- open valve

    1. Residual hydrant - measures residual pressure during test

    2. Collect static pressure from this hydrant

  3. Flow hydrant for test and measure pressure during test

  4. Slowly close valve on flowed hydrant, close valve on residual hydrant


26
New cards

Why perform hydrant tests?

  • Provides information about existing pressure and capabilities to meet fire flow needs

    • Extending line or adding new neighborhood

    • Adding new industries or other demands

    • Calibration of hydraulic model


27
New cards

Isolation valves

isolate portions of a system for repair, inspection, or maintenance

  • fully open or closed (should be operated periodically)

  • install one less at a junctions than legs coming in or out

  • gate valves and butterfly valves


28
New cards

Check Valves

Backflow preventors

29
New cards

Control Valves

  • Pressure reducing valves: establish lower pressure downstream

  • Pressure Sustaining valves: sustain pressure upstream


30
New cards
31
New cards

Network Modeling Rules

  • Flow into each junction must equal flow out of each junction

  • Algebraic sum of head loss around any closed loop must be zero