When calculating probabilistic activity times, the mean of the distribution of expected times, is a weighted average solved as
(a + 4m + b) / 6
The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a normal distribution.
False
Scrum takes a more just-in-time approach to project planning whereby planning is done as late as possible and when the most is known about the project. (Hint see section 5.6)
True
Technical dependencies on a project plan are easiest to see on a
PERT/CPM chart
Which type of precedence diagramming convention is most common
Finish to Start