Project (PMI):
a temporary endeavor undertaken to create a unique product, service or result.
Characteristics
Has an established objective
Has a defined lifespan with a beginning and an end
Involves several department and professionals
Involves doing something never done before
Has specific time, cost and performance requirements
Operational duty is the responsibility
Project Management:
planning scheduling and orchestration of project activities to achieve objectives within a specific period of time
Required skills:
Organizing, budgeting, staffing, monitoring, and communication
Program vs. Project
Program: group of related projects designed to accomplish a common goal over an extended period of time.
Project Management: a process of managing a group of ongoing, interdependent, related projects in a coordinated way to achieve strategic objectives
Project: completion of course in PM; Program: complete=ion of all courses in business major
Skill set should be aligned with project
Routine vs. Projects
Routine - class notes, Projects - term paper
Project Life Cycle: monitoring and controlling should be done throughout (ex. Time cost and quality)
Defining Phase (initiation)
Goals
Specifications
Tasks
Responsibilities
Planning Phase (listing items needed)
Schedules
Budgets
Resources
Risks
Staffing
Executing Phase (doing project)
Status reports
Changes
Quality
Forecasts
Closing Phase (finalization phase of project)
Train customer
Transfer documents
Release resources
Evaluation
Lessons learned
Defining the Project Manager’s Roles
Assigned to complete task:
Manages temporary, NON REPETITIVE activities; acting independently form the formal organization
Marshals resources for the projects
Communicates as the direct link to the customer
Works with a diverse troupe of characters
Responsible for performance and success
1.2 Agile Project Management.
Rolling wave by Larson Gray - progressive project management technique where near‑term work is planned in detail while future tasks are outlined broadly and refined as more information becomes available.
Emerged from the frustration of traditional PM processes = software development
Being used across industries to manage projects with high levels of uncertainty
Employs incremental, iterative process referred to as “rolling wave”
Active collaborate between project and customer = for smaller functional pieces
Works best in small teams (4/8 Members)
Often used in the defining phase to set specifications and requirements, followed by traditional methods for planning, execution, and closure
1.2.1 Agile burgers
APM - flexible, iterative design and build process
Agile Projects are characterized by a series of tasks that are conceived, executed and adapted rather than a pre-planned process
Respond to unpredictability, incremental work processes
Emphasize adaptability along with adequate ongoing communication with the project team and client = reduce risk and better end product IF unprecedented events occur
Linear vs. Adaptive (Agile) Project Management
Aspect | Linear (Predictive) | Adaptive (Agile) |
Process Flow | Sequential phases: Initiating → Planning → Executing → Closing | Iterative cycles: short sprints/iterations |
Planning Detail | Scope, schedule, and cost baselines locked early | Scope refined progressively as project evolves |
Tools Used | Gantt charts, CPM, WBS | Agile boards, burndown charts, sprint reviews |
Stakeholder Role | Limited after requirements are set | Continuous collaboration and feedback |
Best For | Stable projects (construction, compliance, manufacturing) | Dynamic projects (software, R&D, innovation) |
Risk/Benefit | Rigid; costly if requirements change mid‑project | Flexible; lower risk in volatile settings |
Rolling Wave Development
Iterations - last 1 to 4 weeks
Goal of iterations: make tangible progress such as:
Define key requirements
Solve technical problems
Create desired features to demonstrate to the customer
End of each iteration: progress is reviewed, adjustments made = beginning a different iterative cycle
Every new iteration = applying past iterations until project is complete and customer is satisfied
1.3 Current Drivers of Project Management.
Factors leading to increased use of project management:
Compression of the product life cycle
Knowledge explosion
Triple bottom line (planet, people, profit)
Increased customer focus
Small projects represent big problems
1.4 Project Management Today: A Socio-Technical Technical Approach
Technical Dimension (Science):
Consist of formal, disciplined, purely logical parts
Planning -> Scheduling -> Controlling
Sociocultural Dimension (Art):
Contradictory and paradoxical world of implementation
Centered on creating a temporary social system in a larger organizational environment combining talents of divergent professionals.