two types of conditions
-implied in fact
-implied in law
implied in fact conditions
if a contractor is hired to build a house, but can't start until they get a permit, it's implied that homeowner obtain a permit
implied in law
landlord has to make/give you space for you to pay rent
-"duh"
what happens if the condition fails
the duty never arises
-there is no performance owed and no breach
what happens if a breach is material
the aggrieved party is excused from performing
what happens if a breach is non material
aggrieved party is entitled to damages but still have to perform
what does the substantial performance doctrine do
tells you whether or not a breach is material
where does the substantial performance doctrine apply
-not everywhere
-construction contracts are its classic setting
-ask whether perfect performance is reasonable to demand
what does the substantial performance doctrine require
-that the owner received what they bargained for, with minor and unimportant deviations
-breach was unintentional and not in bad faith
the remedy offered under the substantial performance doctrine
non defaulting party recovers damages
time is of the essence
-if it IS, then failure to perform within time is a material breach
-under the UCC. 2-601 it's assumed that time is of the essence
when is non performance excused
1. legal impossibility
2. frustration of purpose
3. impracticability
legal impossibility
-cannot be performed
-death or incapacity of a party performing
-destruction of subject
frustration of purpose
-leasing along parade route and parade is cancelled
-something happened and now contract has no value to a party
impracticability
-becomes really detrimental to a party
-a lot more expensive/difficult
elements of impracticability
1. did an unexpected event occur
2. did event create extreme and unreasonable difficulty
3. did non performing party assume risk that this event could occur
4. was the nonperforming party at fault of causing the event
when does impracticability NOT apply
-increased production costs
-labor disputes
-change in market conditions
force majeure
parties negotiated what would happen if there was an act of god - then, that party is excused from performance
the perfect tender rule
UCC 2-601
-perfection is the standard
UCC 2-508, the seller's right to cure
if the seller sends the wrong products and the deadline has not yet passed they can: notify, then deliver
surprise exception to the UCC 2-508 rule
when the deadline has passed, except the buyer accepted nonconforming goods in the past
-they can still notify to fix
why does title matter
when it passes, the buyer owns the goods, and ownership has consequences
3 consequences of ownership
1. insurance interest
2. creditors and lenders
3. resale and value
insurable interest
the buyer can insure what it owns
-and owes property tax on it
creditors and lenders
creditors can reach the goods, the bank may take a security interest
resale and value
the buyer can resell the goods, and they sit on its balance sheet as an asset
UCC shipment contracts
when the goods are shipped - passed over to a common carrier
-buyer owns goods before they have possession
good faith purchaser for value
defense for a buyer when a prior owner wants the goods back
3 elements to good faith purchaser of value - ALL 3 REQUIRED
1. honesty in fact, no knowledge of fraud
2. voluntary transaction
3. paid value
what are the elements of passage of title
1. parties agree on when
2. identification of the goods
passage of title when goods are shipped
title passes when seller delivers to a common carrier
-parties can contract around with destination clauses
passage of title when there's no movement of goods
-seller may be required to ship a document of title
-if there's no doc of title, title passes at the later of: time contract is entered, or id of the goods