Chapter 7: Managing Risk

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/27

flashcard set

Earn XP

Description and Tags

Vocabulary practice flashcards covering key definitions, concepts, formulas, and visual frameworks from Chapter 7: Managing Risk.

28 Terms

1
New cards

Risk

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives.

2
New cards
<p>Risk Event Graph</p>

Risk Event Graph

A graphical model demonstrating that the chances of a risk event occurring are highest during the early stages of a project and decline over time, while the cost to fix a risk event increases over the project life cycle.

3
New cards
<p>Risk Management Process</p>

Risk Management Process

A four-step iterative framework consisting of Step 11: Risk Identification (analyze project to identify sources of risk), Step 22: Risk Assessment (assess severity, likelihood, and controllability), Step 33: Risk Response Development (develop strategies and contingency plans), and Step 44: Risk Response Control (implement strategy, monitor for new risks, and manage changes).

4
New cards
<p>Risk Breakdown Structure (RBS)</p>

Risk Breakdown Structure (RBS)

A hierarchical framework used in conjunction with the work breakdown structure (WBS) to help project teams identify and organize potential sources of risk across major categories such as Technical, External, Organizational, and Project Management.

5
New cards

Risk Profile

A list of questions addressing traditional areas of uncertainty on a project that have been developed and refined from previous, similar projects.

6
New cards

Scenario Analysis

The easiest and most commonly used technique for analyzing risks, in which team members assess the significance of each risk event in terms of the probability (likelihood) of the event occurring and the impact (consequences) of its occurrence.

7
New cards

Detection Difficulty

A measure of how easy it would be to discern that a risk event was imminent in time to take mitigating action, reflecting how much warning the project team would have.

8
New cards
<p>Risk Severity Matrix</p>

Risk Severity Matrix

A 5×55 \times 5 array structured around the likelihood and impact of risk events, divided into red (major risk), yellow (moderate risk), and green (minor risk) zones to prioritize which risks to address.

9
New cards

Failure Mode and Effects Analysis (FMEA)

An extension of the risk severity matrix that calculates overall risk value using a five-point scale for three dimensions: Impact×Probability×Detection=Risk Value\text{Impact} \times \text{Probability} \times \text{Detection} = \text{Risk Value}.

10
New cards

Mitigating Risk

A risk response alternative that focuses on reducing the likelihood that an adverse event will occur and/or reducing the impact that the event would have on the project.

11
New cards

Avoiding Risk

A risk response strategy that involves changing the project plan to eliminate the risk or condition before launching the project.

12
New cards

Transferring Risk

Passing risk to another party—usually resulting in paying a premium—using mechanisms such as fixed-price contracts, insurance, warranties, and performance bonds.

13
New cards

Build-Own-Operate-Transfer (BOOT)

A contractual provision on large international projects where the prime contractor builds the facility and assumes ownership until operational capacity is proven and debugging is completed before ownership is transferred to the client.

14
New cards

Accepting Risk

A conscious decision to retain the risk of an event occurring, either because the event is too large to mitigate or transfer, has a very slim probability, or can be absorbed using a contingency plan or reserve funds.

15
New cards

Contingency Plan

An alternative plan specifying what, where, when, and how much action will take place that goes into effect only after a foreseen risk event materializes or is triggered.

16
New cards

Opportunity

An uncertain event or condition that can have a positive impact on project objectives (also known as a positive risk).

17
New cards

Exploit

An opportunity response tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.

18
New cards

Share

An opportunity response strategy that involves allocating some or all ownership of an opportunity to another party who is best able to capture the benefit for the project.

19
New cards

Enhance

An opportunity management tactic designed to increase the probability and/or the positive impact of an opportunity.

20
New cards

Accept (Opportunity)

An opportunity response strategy where the project team is willing to take advantage of an opportunity if it occurs, but takes no active action to pursue it.

21
New cards

Budget Reserve

Contingency funds established to cover identified risks and allocated to specific work packages or deliverables within the project baseline budget.

22
New cards

Management Reserve

Independent contingency funds established to cover major unforeseen, unidentified risks associated with the total project, controlled jointly by the project manager and the owner or top management.

23
New cards

Time Buffer

Extra time reserved and assigned at critical moments in a project schedule (such as activities with severe risks, merge activities, or project completion) to cushion against potential delays.

24
New cards

Risk Register

A formal document that details all identified project risks, including descriptions, categories, probability of occurring, impact, responses, contingency plans, owners, and current status.

25
New cards

Change Management System

A formalized process designed to report, review, evaluate, record, and control proposed changes to the project baseline (scope, schedule, and cost).

26
New cards

Plan of Record

The current official project plan in terms of scope, budget, and schedule, which serves as the benchmark for future change requests and performance evaluation.

27
New cards

Criticality Index

In PERT simulation, the relative probability that an activity will become critical under many different possible activity duration distributions.

28
New cards

Weighted Average Activity Time (tet_e)

The PERT formula used to determine the expected duration of an activity based on a beta distribution: te=a+4m+b6t_e = \frac{a + 4m + b}{6}, where aa is optimistic time, mm is most likely time, and bb is pessimistic time.