project management exam

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/105

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 5:14 PM on 10/12/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

106 Terms

1
New cards

Project

Has a beginning and an end; produces a unique product

2
New cards

Project management

A discipline (set of methods, theories and techniques) that is both an art and a science

3
New cards

Operations

Have no defined end; produce similar, often identical, products

4
New cards

Project vs. operation example: Accounting

Project = implementing an accounting information system; Operation = daily entering sales receipts into the ledger

5
New cards

Project vs. operation example: Supply chain

Project = developing a supply-chain information system; Operation = responding to a supply-chain request using the SCM system

6
New cards

Project vs. operation example: iPhone

Project = designing a new version of the iPhone; Operation = routine manufacture of the iPhone

7
New cards

Project vs. operation example: Walmart RFID

Project = Walmart's RFID tag project; Operation = attaching tags to manufactured products

8
New cards

Who selects projects?

Executives

9
New cards

Role of functional managers in projects

Sponsor, lead or oversee projects within their departments

10
New cards

Part-time project leaders

Senior staff and functional managers tasked with leading smaller or part-time projects

11
New cards

Demand for project-oriented jobs

Rising (PMI 2025 Global Project Management Talent Gap)

12
New cards

Why learn PM as a student?

Organizations use PM to stay competitive; individuals need PM skills to be good team members/PMs; PM tools help accomplish personal objectives

13
New cards

Project success (iron triangle / triple constraint)

On time, on budget, on scope

14
New cards

Three project management functions

Project definition, project planning, project control

15
New cards

Project definition

Lays out the foundation for a project

16
New cards

Project planning

Puts together the details of how to meet the project's goals, given the constraints

17
New cards

Project control

Keeps the project moving toward the goal

18
New cards

Three skill sets for project managers

Project management, business management, technical skills

19
New cards

Project management skill set

The PM discipline (e.g. PMP certification); theory and techniques that apply to projects in any industry

20
New cards

Business management skill set

Soft skills such as leadership, communication and teamwork

21
New cards

Technical skill set

Field-specific competence: academic degrees, industry experience, software skills (e.g. MS Office, QuickBooks)

22
New cards

"PM is industry-independent; project managers are not"

PM techniques apply in any industry, but project managers must have good technical skills in their field

23
New cards

PMBOK

Project Management Body of Knowledge

24
New cards

Product life cycle

Industry specific; describes the work required to create the product

25
New cards

Project life cycle

Industry independent; focuses on managing the work

26
New cards

Product vs. project life cycle relationship

A product development life cycle can contain many projects

27
New cards

Three organization structures

Function-driven, project-oriented, matrix

28
New cards

Areas where organization structure impacts projects

Authority, communication, priority, focus, chain of command

29
New cards

Stakeholder

Anyone who contributes to the project or who is impacted by its result

30
New cards

Typical stakeholders

Project manager, project team, management, project sponsor, resource manager, the customer

31
New cards

Customer (stakeholder)

Establishes requirements and provides funding

32
New cards

Other potential stakeholders

Managers with decision authority, representatives of external constraints, advocates and opponents

33
New cards

Stakeholder role

A person's involvement and influence in the project

34
New cards

Stakeholder position

A person's formal job or title within the organization

35
New cards

Stakeholder register columns

Name, position, internal or external, stakeholder role, contact information

36
New cards

Leading the stakeholders

Control who becomes a stakeholder; manage upward

37
New cards

Managing upward

Managing someone who has more formal authority than you

38
New cards

Project success factors (Ch7)

Agreement on the goals, controlled scope, management support, a plan, good communication

39
New cards

Two key project definition documents

Project charter and responsibility matrix

40
New cards

Project charter

Lists the goals, constraints and success criteria for the project; announces that a new project has begun

41
New cards

Purpose of the project charter

Formally authorize the new project and the PM; demonstrate management support for the project and PM

42
New cards

How the charter gives the PM authority

Establishes legitimate authority by referencing the legitimate authority of the sponsor

43
New cards

Legitimate authority

Authority conferred by the organization

44
New cards

Expert authority

Authority that stems from performance on the job

45
New cards

Updating the charter

It's a tool for managing expectations and changes; update it to reflect project changes, and all stakeholders must agree

46
New cards

Charter minimum content

Purpose statement, scope descriptions, deliverables, cost and schedule estimates, measures of success, stakeholders, chain of command

47
New cards

Purpose statement

Describes what we will do on the project and why; must be clear enough to guide decision making; can include a measurable goal

48
New cards

Where project justification belongs

In a proposal, business case or cost-benefit analysis, not the purpose statement

49
New cards

Scope description

Describes major activities so it's clear if extra work is added later; can place the project in a larger scenario; states what's beyond scope

50
New cards

Deliverables

What the project is supposed to produce; can be intermediate, end or PM-related

51
New cards

Intermediate deliverable examples

Requirement documents, a description of a target market, a study of a new ER admission policy

52
New cards

End deliverable examples

A new piece of software, an advertising campaign, a new ER admissions process

53
New cards

PM-related deliverables

Charter, WBS, schedule, cost baseline, status reports, change logs

54
New cards

Measures of success

Specific, measurable goals (e.g. "no measurable oil spills"); can include exit criteria like customer acceptance criteria

55
New cards

Responsibility matrix

Describes the level of participation and authority of project stakeholders on major project activities

56
New cards

Responsibility matrix content

Major project activities, key stakeholder groups, codes for responsibilities

57
New cards

R (responsibility matrix)

Responsible for execution

58
New cards

A (responsibility matrix)

Approval authority

59
New cards

C (responsibility matrix)

Must be consulted

60
New cards

I (responsibility matrix)

Must be informed

61
New cards

Project risk

An uncertainty that can have a negative or positive effect on achieving project objectives

62
New cards

Known risks (known unknowns)

Future situations that can be partially planned for (e.g. 20% turnover rate for IT personnel)

63
New cards

Unknown risks (unknown unknowns)

Future situations that are unpredictable (e.g. an important supplier goes out of business)

64
New cards

Business risk

Selecting the right project; not the project manager's job

65
New cards

Project risk (vs. business risk)

Managing uncertainty to meet the stakeholders' objectives

66
New cards

Risk management

The means by which uncertainty is systematically managed to increase the likelihood of meeting project objectives

67
New cards

Risk management framework (5 steps)

1) Identify risks 2) Analyze and prioritize risks 3) Develop response plans 4) Establish contingency and reserve 5) Continuous risk management

68
New cards

Step 1: Identify the risks

Get information from stakeholders, use a risk profile, use historical records, and estimate schedules and budgets

69
New cards

Risk profile

A list of questions that address traditional areas of uncertainty on projects; creating one is an ongoing process

70
New cards

Condition (defining a risk)

A brief statement describing the situation causing concern or uncertainty

71
New cards

Consequence (defining a risk)

A brief statement describing the possible negative outcomes the condition may cause

72
New cards

Expected value of a risk

Probability × Impact

73
New cards

Expected value: Project A (0.4 × $2M + 0.6 × $500K)

$1,100,000

74
New cards

Expected value: Project B (0.3 × $3M + 0.7 × $200K)

$1,040,000

75
New cards

Five risk response strategies

Accept, avoid, contingency plans, transfer, mitigate

76
New cards

Accept the risk

Doing nothing

77
New cards

Avoid the risk

Avoid doing that part of the project, or choose an alternative way to do it

78
New cards

Contingency plan

Monitor the risk and have an alternative course of action ready

79
New cards

Detectability

The ability to detect the risk in time to respond

80
New cards

Trigger event

The line crossed between monitoring the risk and implementing the contingency plan

81
New cards

Transfer the risk

Shift consequences or responsibility to another party (e.g. buy insurance, hire an expert, use a fixed-price contract)

82
New cards

Mitigate the risk

Work hard to reduce the risk (e.g. competent personnel, analysis and validation techniques)

83
New cards

Expected value of contingency

Probability of risk event × cost of contingency

84
New cards

Contingency reserves

Account for identified risks (known unknowns)

85
New cards

Management reserves

Account for unknown risks (unknown unknowns)

86
New cards

Step 5: Continuous risk management

Monitor known risks with a risk log, check for new risks, repeat identification at milestones, prepare responses for new risks, retire risks that didn't materialize

87
New cards

Risk log

Records risk management strategies and is used to monitor known risks

88
New cards

Broad categories of IT project risk

Market, financial, technology, people, structure/process

89
New cards

Preplanning activities

Create the project definition (Ch6-7); develop a risk management strategy (Ch8)

90
New cards

Planning steps (in order)

Build WBS → identify task relationships → estimate work packages → calculate initial schedule → assign and level resources → develop budget

91
New cards

Does a WBS describe sequence?

Not entirely; a WBS is not used to describe sequence constraints

92
New cards

Sequence constraints

Certain tasks must be performed before others; governed by task relationships (task dependencies)

93
New cards

Task dependency

The logical relationship between activities that explains why one affects another (e.g. build the frame after pouring the foundation)

94
New cards

Finish-to-start (FS)

Task A must finish before Task B can start; most common (e.g. install software → train users)

95
New cards

Start-to-start (SS)

Task A must start before Task B can start (e.g. receive survey responses → tabulate responses)

96
New cards

Finish-to-finish (FF)

Task A must finish before Task B can finish (e.g. conduct production → conduct quality inspection)

97
New cards

Start-to-finish (SF)

Task A must start before Task B can finish; very rare (e.g. night shift → day shift)

98
New cards

Predecessor

The task that controls the relationship between two tasks; not necessarily the one that comes first

99
New cards

Successor

The task that follows a predecessor task, as determined by their logical relationship

100
New cards

Concurrent tasks

Tasks that can be performed at the same time