how do you calculate an EV
add up (probability x payoff) for every outcome
In an EV question, what if there’s a cost to pay
you subtract the cost from the total expected value calculation to get the net EV
In an EV question, how do you choose between options
You compare the expected values of each option, selecting the one with the highest EV.
what does EV = 0 mean?
fair game
EV: win £10 (p = 0.2), lose £3 (p = 0.8)?
(0.2×10) + (0.8x-3) = -£0.40
forward pass gives you..?
earliest start times. At a merge, then take the biggest
Backward pass gives you…?
Latest times, At a split, take the smallest
Float formula?
latest finish - earliest start - finish
whats a critical activity?
one with zero float
whats the minimum project time?
the end of the critical path
how do you show float on a gantt chart?
A dotted extension on the bar
how do you handle a worker limit
count the workers needed per time period, then shift non-critical activities using their float
mark-saver for gantt questions?
write how many workers each time period needs