Project Management Principals
Foundational guidelines that help guide strategy, decisions, problem solving, and behavior
not strict rules are laws
Principals (6)
Adopt a holistic view, focus on value, embedd quality into processes and deliverables, be accountable leader, integrate sustainability within all project areas, build an empowered culture
Project Management Mindset 3 dimensions:
proactive, ownership, value driven
Holistic View
Helps to identify the root causes problems instead of only treating symptoms
Value can be measured
using numbers, ROI, qualitative benefits like customer satisfactions, social impact, testimonials
Quality
means project deliverable or project meets or exceeds the projects target objectives
embedding quality at beginning of project
quality effects other performance domains
scope - quality ensures meet req, standards, and specifications to help prevent rework, and increase stakeholder satisfactions
schedule - it adds reviews, quality milestones, and early quality checks
finance - helps control costs by reducing waste, defects and work
stakeholder and resources - meet stakeholder expectations and right people/tools/resources are available
risk - reduces chance of defects, noncompliance, and quality problems
sustainability - triple bottom line
balancing social, environmental, and economic outcomes
adaptive and agile methods
iteratives/iterations and incremental
Development approach
method used to create or evolve a product, service, or result during a project
ex: predictive, hybrid, adaptive/agile
***PM uses chooses the development approach, consults the project management team
Predictive Dev Approach
requirements are clear and stable early in project
scope, schedule, and cost up front
called waterfall, plan driven, traditional
used for large projects, major investments, or regulated environments where STRONG change control is needed
often use phase gates before they move to next phase
scope is fixed, budget and schedule are variable**
Adaptive Dev Approach
Requirements are unclear, complex, uncertain
work is reviewed in short timeboxes so feedback can be used to adjut the work and evolve baseline
is called change driven or agile approach
often use short iterations
could be iterative or incremential approaches
Budget and schedule are fixed, scope is variable**
iterative approach
work is improved through repeated cycles
incremental approach
product is delivered in small usable pieces that build on eachother
Hybrid
combines predictive and adaptive
is useful when parts of projects are clear and others are unclear/uncertain, risky
ex: building home, adaptive for design changes and predictive for the build
work well when deliverables can be modularized (organized into separate pieces/modules) or handled by diff teams
** a project can use one main approach overall while using a diff approach for certain phases, deliverables, workstreams
Focus Areas as a Whole
the 5 PM focus areas apply to all industries and application areas, apply to all development approaches
Focus areas are NOT project phases
if a project has phases the focus area actions can happen inside each phase
are not sequential, often overlap and repeat during project
LOE for focus area can change depending on phase, lifecycle, dev approach
Initiating Focus Area
includes the actions used to define a new project or new project phase
***formal authorization to start a new project or phase
**Project manager is assigned during this initiation phase
goal to align stakeholder expectations, purpose, scope
during initiation, the team defines initial scope, initial financial resources, identifies stakeholders, assigns PM roles
common artifacts are the project charter and stakeholder register
Planning Focus Area
actions used to define project scope, refine objectives, and decide how work will be completed
may create artifacts like project management plan and product backlog (agile projects)
not always once, can be a feedback loop, rolling wave planning or progressive elaboration
are new info or changes are discovered, the plan may need to be updated
**key benefit is to define course of action needed to successfully completed project or phase
Executing Focus Area
action used to complete the project work according to current plan
involves coordinating resources, managing stakeholders, performing project activities
goal to keep the team focused on delivering project’s expected value**
Monitoring and controlling focus area
tracks, measures, reviews, regulates project process and performance
helps identify when changes to the plan are needed and support initiating those changes
monitoring includes comparing actual performance to planned performance and reporting project info
controlling includes analyzing variances, reviewing trends, evaluating options and recommending corrective action
**key benefit to keep project on track to meet expectations
happens through the project and runs in parallel with other focus areas
Closing Focus Area
includes actions used to formally complete or close a project, phase, or contract
used to terminate a project early when continuing no longer makes business sense
verifies required project work and actions from other focus areas have been completed
key benefit to ensure project, phase, contract is closed properly and transitioned to ops
closing confirms whether project delivered expected outcomes, outputs, benefits, and VALUE