What is the relationship between organizational culture and estimating?

Cultural norms affect the accuracy of estimates.

2
New cards

The process of forecasting or approximating the time and cost of completing project deliverables is called

estimating.

3
New cards

A home builder is collecting estimates for a house that he will have the funding to build in 12 months. Which of the following factors does he need to consider in regard to the quality of these estimates?

Planning horizon

4
New cards

The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the ________ factor.

padding estimates

5
New cards

A project manager is looking over the actual results of projects and comparing them to what was estimated. She notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is she recognizing?

Planning horizon

6
New cards

A good starting point for developing time and cost estimates is

past experience.

7
New cards

Which of the following is NOT one of the recommended guidelines for developing useful work package estimates?

Which of the following is NOT one of the recommended guidelines for developing useful work package estimates?

8
New cards

The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as

template method.

9
New cards

Which of the following is NOT true in regard to the level of detail estimates should contain?

Detailed estimates are crucial to project success; therefore, an effort should be made to make estimates as detailed as possible for all projects.

10
New cards

Which of the following top-down methods is used when projects closely follow past projects in regard to features and costs of those features, and result in costs being assigned by percentages to major segments of the project?

Apportion

11
New cards

Which of the following does NOT help describe a bottom-up estimating approach?

They are made by someone who uses experience and/or information from someone else to determine overall project cost and duration.

12
New cards

Top-down methods are used for all but which of the following intended usages?

Budgeting and scheduling

13
New cards

When someone uses experience and/or information from others to determine the project duration and total cost, ________ estimating is being used.

top-down

14
New cards

In practice, estimating processes are frequently classified as

top down or bottom up.

15
New cards

The information necessary to conduct a bottom-up estimate of project time and cost starts with the ________.

work package

16
New cards

Typical kinds of costs found in a project include all of the following EXCEPT

All of these are examples of costs found in a project.

17
New cards

The salary of the project manager would be an example of what type of cost found in a project?

Direct project overhead

18
New cards

Which of the following would best represent direct project costs?

Labor, materials and equipment

19
New cards

Costs that are not directly related to a specific project, such as advertising, accounting, and senior management's salary, are classified as ________ costs.

general and administrative overhead

20
New cards

Refining Estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of

changes in project scope.

21
New cards

The estimating factor that considers the decreasing accuracy of estimates as one forecasts activities that are further into the future is known as ________.

planning horizon

22
New cards

A project leader is forecasting how much money his department needs to support a new project. He estimates that two people and $25,000 in expenses will cover his needs. Because management typically insists on reducing forecasts by 20 percent, he increases his estimates to allow for that reduction. Which of the following factors is illustrated in this situation?

Padding estimates

23
New cards

The estimating factor that considers the skill level of participants doing the estimating is known as the ________ factor.

people

24
New cards

A construction estimator is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following methods is he using?

Ratio

25
New cards

The preferred method for situations where the cost and time estimates are important, in a fixed contract situation, and when the customer wants a lot of detail is the ________ approach to estimating project time and costs.

bottom-up

26
New cards

A scrum master is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. He is using which estimating approach?

Range estimating

27
New cards

Project costs such as labor and materials are typically classified as ________ costs.

direct

28
New cards

The salary of the project manager and temporary rental space for the project team would be classified as ________ costs.

direct project overhead

29
New cards

Refining estimates may be necessary for a number of reasons. For example, people working on prototype development needing time to interact with the design engineers after the design is completed is a good example of

hidden interaction costs.

30
New cards

A project network provides the basis for

scheduling labor and equipment.

31
New cards

When translated into a project network, a work package will become

one or more activities

32
New cards

Information to develop a project network is collected from the

work breakdown structure

33
New cards

A sequence of connected, dependent activities is termed a(n)

path

34
New cards

A(n) _________ activity has more than one successor activity.

burst

35
New cards

Activities which can take place at the same time are termed

parallel activity.

36
New cards

In a project network, recycling through a set of activities or ________ is not permitted.

looping

37
New cards

If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a

dangler path.

38
New cards

A ________ activity is one that has more than one activity immediately preceding it.

merge

39
New cards

Which of the following will correctly calculate the total slack in an activity?

Either LS − ES or LF − EF

40
New cards

A(n) ________ calculates project duration.

forward pass

41
New cards

For any activity that has one or more predecessors, the ________ time is always the largest early finish of any of its predecessors. If the early finish times of an activity’s predecessors were 85, 70 and 55, then this time would be the largest of these three early finish times or 85.

early start

42
New cards

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

backward pass

43
New cards

Which of the following correctly calculates the late start for an activity?

LF − DUR

44
New cards

A(n) ________ calculates how late an activity can start and finish.

backward pass

45
New cards

The likelihood the original critical path(s) will change once the project is initiated is referred to as

The likelihood the original critical path(s) will change once the project is initiated is referred to as

46
New cards

A network has only one critical path and the slack for noncritical activities is high. This network would appear to have a ________ level of sensitivity

low

47
New cards

The delaying of any activity on the ________ will delay the completion of the project by the same amount.

critical path

48
New cards

________ slack must be coordinated with all participants in the activities that follow in the chain.

total

49
New cards

The amount of time an activity can be delayed and yet not delay the project is termed

total slack

50
New cards

Which of the following is provided by both the project network and the work breakdown structure?

Activity duration

51
New cards

On a project network, the activity times are derived from the

work packages.

52
New cards

________ activities are to be completed immediately following a particular activity.

Successor

53
New cards

Activities that must immediately follow a given activity are called ________ activities.

successor

54
New cards

An activity that has more than one predecessor is a ________ activity.

merge

55
New cards

Activities that must occur immediately before a given activity are called ________ activities.

predecessor

56
New cards

Which of the following is NOT one of the basic rules to follow when developing project networks?

Conditional statements are allowed but looping statements are not allowed.

57
New cards

The activity time estimates used to build a project network are derived from ________.

work packages

58
New cards

An activity has a duration of 10 days. Its early start is 5 and its late start is 8. This activity has ________ days of total slack.

3

59
New cards

The backward pass in project network calculations determines all of the following EXCEPT

earliest time an activity can finish.

60
New cards

After the total slack for each activity is identified, the project manager can more easily identify the

critical path.

61
New cards

________ reflects the likelihood the original critical path(s) will change once the project is initiated.

Sensitivity

62
New cards

A purchasing agent is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, the purchasing agent has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. The purchasing agent and the installer share 10 days of

total slack

63
New cards

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a

risk

64
New cards

The likelihood of a risk occurring ________ as a project goes through its life cycle.

decreases

65
New cards

The chances of a risk event occurring as a project proceeds through its life cycle tend to

slowly drop

66
New cards

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is known as a ________.

risk

67
New cards

One common mistake made early in the risk identification process is to

focus on consequences and not on the events that could produce consequences.

68
New cards

What is the risk value of a risk whose impact score is 5, whose probability score is 5 and whose detection score is 1?

25

69
New cards

The ________ matrix is divided into red, yellow, and green zones representing major, moderate, and minor risks.

risk severity

70
New cards

Risks are evaluated in terms of

likelihood and impact

71
New cards

The risk assessment form contains all of the following EXCEPT

who will detect the occurrence of the risk event.

72
New cards

When considering risk response development, changing the plan to eliminate the risk or condition is known as ________ the risk.

avoiding

73
New cards

Performance bonds, warranties, and insurance are examples of ________ a risk.

transferring

74
New cards

Flooding would be devastating to the project; however, it is very unlikely. The project manager is most likely to ________ this risk.

retain

75
New cards

When considering risk response development, reducing the likelihood that an event will occur and/or reducing the impact that an adverse event would have on a project is known as ________ the risk.

mitigating

76
New cards

A fixed price contract is an example of

transferring risk

77
New cards

Which of the following risks are likely to be retained?

Risks of low likelihood

78
New cards

Risks that can result in a system or process that will not work are known as

technical risks

79
New cards

A Risk Response Matrix contains all of the following EXCEPT

when the risk will occur

80
New cards

A key distinction between a risk response and a contingency plan is

a risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.

81
New cards

Just as contingency funds are established to absorb unplanned costs, managers use ________ to cushion against potential delays.?

Time buffers

82
New cards

Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ________ reserves.

cotingency

83
New cards

When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?

All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.

84
New cards

Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource

smoothing.

85
New cards

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by ________ constraints.

technical

86
New cards

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?

time

87
New cards

A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.

technical or logic

88
New cards

If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.

equipment

89
New cards

A project engineer has been scheduled to run the product system test at the same time as building a marketing prototype. This is an example of what type of resource constraint?

People

90
New cards

A special truck that is needed on the project has been assigned to another project. This is an example of what type of resource constraint?

Equipment

91
New cards

In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ -constrained project.

time

92
New cards

A project scheduler is trying to reallocate resources in a time-constrained project to create smoother resource utilization. The scheduler should first identify activities with the

most slack

93
New cards

A project scheduler is trying to reallocate resources in a time-constrained project to create smoother resource utilization. The scheduler should first identify activities with the

a longer project duration.

94
New cards

After resource leveling or smoothing, one goal is that the amount of resources needed over the life of the project will be ________.

reduced

95
New cards

In a resource-constrained project the second priority in assigning resources is usually given to activities with the

smallest duration

96
New cards

In scheduling resource-constrained projects, ________ are typically used rather than optimum mathematical solutions.

heuristics

97
New cards

When a project is classified as resource-constrained, a resource constraint exists, and positive slack is insufficient, then the project duration is typically ________.

extended

98
New cards

When scheduling activities in a resource-constrained project, typically the activity scheduled first has the ________ amount of slack.

least

99
New cards

All resource leveling techniques involve

delaying noncritical activities.

100
New cards

While balancing assignments, a project manager must also balance:

Talent development.