21 Terms

1
New cards

What is lean production?

A set of strategies designed to reduce waste in the production process while maintaining or improving quality.

2
New cards

What are the seven types of waste in lean production (TIM WOOD)?

Transportation, Inventory (stock), Motion, Waiting, Over-production, Defects

3
New cards

What is continuous improvement (kaizen)?

A Japanese philosophy and process involving regular scheduled meetings where staff suggest ideas to improve quality and reduce waste.

4
New cards

What is just-in-time (JIT) production?

An inventory control method where stock is delivered just before it is needed, minimizing or eliminating inventory holding costs.

5
New cards

What is cradle-to-cradle design and manufacturing?

A model of creating products that minimizes waste and negative environmental impacts through biological and technical cycles (sustainability).

6
New cards

What is the biological cycle in cradle-to-cradle design?

Using biodegradable raw materials that are naturally broken down by biological agents like bacteria and fungi.

7
New cards

What is the technical cycle in cradle-to-cradle design?

Designing products using materials that can be disassembled, reused, or recycled once no longer needed.

8
New cards

What is quality control?

The inspection of a finished product to find defects and remove them after production before delivery to customers.

9
New cards

What is quality assurance?

Strategies to prevent defects and improve products throughout the production process, involving employee empowerment and self-checking

10
New cards

What is a quality circle?

A group of employees from diverse areas who meet regularly to discuss potential improvements to product quality and waste reduction.

11
New cards

What is benchmarking?

The process where a business compares itself on specific criteria against industry leaders to learn from their techniques and improve performance.

12
New cards

What is Total Quality Management (TQM)?

A quality management system where every employee is jointly responsible for product quality, emphasizing employee empowerment and internal customers.

13
New cards

What is the International Organization for Standardization (ISO)?

An independent global body that promotes commercial standards, such as ISO 9000, awarded for quality assurance systems.

14
New cards

What is a Gantt chart?

A project management tool that illustrates a project plan, showing tasks, durations, dependencies, and timelines over weeks or months.

15
New cards

What is Critical Path Analysis (CPA)?

A project planning tool (network analysis) showing the sequence of tasks, dependencies, and the minimum time needed to complete a project.

16
New cards

What is Earliest Start Time (EST)?

The earliest time that a task can begin in a critical path network diagram.

17
New cards

What is Latest Finish Time (LFT)?

The latest time that a task can finish without delaying the overall project completion time.

18
New cards

What is Free Float?

The amount of time a task can overrun its estimate without delaying the next task: EST of next task - EST of current task - duration.

19
New cards

What is Total Float?

The amount of time a task can overrun its estimate without delaying the whole project: LFT of current task - duration - EST of current task.

20
New cards

What is the critical path?

The sequence of tasks with zero total float that determines the minimum total time required to complete a project.

21
New cards

What is a dummy activity in a critical path diagram?

A dotted line with zero duration or cost used purely to show logical relationships and dependencies between tasks.