1/13
Looks like no tags are added yet.
What characterizes a predictive project approach?
Work progresses in sequence through well-defined phases.
What characterizes an adaptive or agile project approach?
Activities repeat in cycles, and requirements evolve throughout the project.
When is most business analysis performed in a predictive project?
Early in the project, especially during feasibility and analysis and planning.
What level of requirements detail is typical at the start of an adaptive project?
A high-level understanding. The team adds detail as the project progresses.
How does the BA’s work differ between predictive and adaptive projects?
The core tasks are similar. Predictive projects concentrate analysis early, while adaptive projects repeat analysis throughout the project.
What does the BA do during feasibility in a predictive project?
Conduct a needs assessment to understand the business need.
What does the BA do during analysis and planning in a predictive project?
Plan the analysis and help define requirements.
What does the BA do during design in a predictive project?
Facilitate solution design.
What does the BA do during build in a predictive project?
Trace and monitor requirements as the solution is built.
What does the BA do during testing and evaluation in a predictive project?
Help test and evaluate the solution and plan for deployment.
Why can a late requirement change add risk in a predictive project?
Work already based on the original requirement may need to be redesigned, rebuilt, or retested.
Which factors shape how an organization tailors its BA practices?
Organizational structure, culture, methodology, and the project manager’s role.
A BA defines most requirements early, then traces them through construction. Which approach is this?
Predictive.
A BA starts with a broad product goal and refines requirements after each round of feedback. Which approach is this?
Adaptive or agile.