134 Terms

1
New cards

CAA


Why must a party terminate an agreement & what processes must be followed?

  • All promises fulfilled

  • Parties agree to terminate

  • Breach of contract

  • One party follows process to terminate laid out in CAA


  • Party must give 30 days notice

  • All invoices to date must be paid

  • Architect submit invoice of work to date

  • Architect must hand over all work

  • If services are deemed completed, client may get irrevocable licence to use “the design”

  • Any urgent work must be completed prior to termination


2
New cards

CAA

How should a dispute be resolved under the CAA?

  • address quickly and professionally manner

  • Architect and client must continue other duties

  • Mist give written notice of dispute to other party and meet within 5 days

  • If no resolution - must use a mediator - if can’t agree in one, one is assigned to them

  • If mediation not successful then legal action may be required


3
New cards

CAA

What is the function of the Client Architect Agreement?

Provide a clear outline between client and architect

  1. Defines roles and responsibilities of client and architect

  2. Defines services to be provided and fees to be paid

  3. Identifies budget for cost and total project cost

  4. Includes intellectual property agreement

  5. Identifies other consultants necessary

  6. Describes insurances and liabilities

  7. Outlines dispute resolution, termination and general conditions


4
New cards

CAA

What are some general conditions in the CAA?

  • all requests, approvals and notices must be in writing

  • Cannot transfer / novate agreement without consent

  • Applicable law of agreement is state / territory where site is located

  • Agreement supersedes prior agreements

  • No expressed or implied warranties that building is fit for purpose


5
New cards

CAA

What should you consider with regards to special conditions in the CAA?

Only alter if you have advise from legal to prepare / include a special condition

6
New cards

CAA

What what be considered risk areas and could be thought about early to incorporate appropriate clauses in the CAA?

  1. Administrative work

  2. Compliance with authorities

  3. Assessment of alternatives

  4. Design and documentation responsibility

  5. Shop drawing preparation

  6. Issuing of CAD information

  7. Definition of practical completion

  8. Principal contractor clauses

  9. QS’s role

  10. Defects handling and Defect Liability Period

  11. Building maintenance

  12. Height safety and WHS

  13. Commissioning - loose furniture, signage, wall hangings, window treatments etc.


7
New cards

CAA

What are come clients obligations under CAA?

  • provide timely and accurate information to architect

  • Not reasonably delay the project

  • Only issue instructions to builder through architect

  • Agree on a reasonable budget with architect

  • May payment as required

  • Engage consultants as required

  • Allow architects to photograph / record project

  • Attribute the architect

  • Notify architect of confidential requirements

  • Inform architect of initial program


8
New cards

CAA

What are some architects obligations under the CAA?

  • provide services in agreement with reasonable skill and professionalism

  • Act as clients agent

  • Maintain records and keel client informed of progress

  • Coordinate consultants

  • Engage consultants if required

  • Advise client on changes to works and costs

  • Advise of any conflicts of interest

  • Maintain registration

  • Comply with code of practice


9
New cards

CAA

What should be considered when determining insurances in CAA?

  • agree to holding PI, PL and workers compensation insurance

  • Architects total liability to client is limited

    • No liability to separate or consequential loss

    • No liability after 3 years of service

    • Lower limit better for you - matching PI may strain cover

    • Writing $0 / NA / NIL means not capped - unlimited


10
New cards

CAA

What should be considered when determining the following in the CAA?

  • costs

  • Time and program

  • Establishing fees

  • Specialist consultants


Costs

  • determine realistic budget at outset

  • Ensure client understands between total project cost and cost of the works


Time and program

  • Set realistic programme for services and each phase at outset

  • Keep client informed of progress, be aware of unpredictable approvals


Fees

  • Ensure understanding of scope of services, negotiate scope not fees, provide hourly rates for additional unknown services, client understands monthly invoice with 10 days to pay


Specialist consultants

  • Who engaging extra admin fee for engaging subbies required?


11
New cards

CAA

Who owns the copyright and moral rights under the CAA AIA?

Copyright

  • architect retains copyright and grants the client an express, non-exclusive non-transferable and revocable license to use the design on the site

  • License may be revoked by the architect is any invoice becomes overdue


Moral rights

  • The architect must be attributed in all 2-3D representation of the project


12
New cards

CAA

What are the core architectural services?

  1. Concept design

  2. Design development

  3. Planning - development application

  4. Construction documentation

  5. Contractor selection - tender phase

  6. Contract administration


13
New cards

CAA

What are additional services?

  1. Feasibility study

  2. record documentation - existing buildings

  3. Planning / DA negotiation

  4. 2D/3D visualisation / marketing drawings

  5. Trade breakdown packages

* specific requested services can be added to schedule section of agreement


14
New cards

CAA

What should be remembered when completing part services?

  • clearly define your scope of services and ensure client understands this

  • Have a CAA

  • Don’t do services outside your scope


15
New cards

Commissions & Briefs


Q1. What should be included in the fee proposal?

Q2. What are some common risks to architects fees?


Q1

  1. Intro - give understanding of project & site

  2. List qualifications & experience

  3. List break down of core services & deliverables & additional work

  4. List of fees & disbursements & hourly rates

  5. List assumptions & exclusions

  6. Outline terms of engagement (contract)

  7. Insurances


Q2

  1. Initial client brief

  2. Client inexperience - ongoing changes

  3. Authorities

  4. Accuracy of site information

  5. Consults unknown to architects

  6. Change in legislation

  7. Weather


16
New cards

Commissions & Briefs


Q1. A prospective client comes to you & asks for your services and what you charge, how should you respond?

Q2. What should be discussed at this initial meeting?

Q1

  1. Do not answer this on the spot, more information is required.

  2. Say thank you and that you are very interested.

  3. Ask them to set up a meeting to understand and discuss further

  4. Ask for the site address to do some due diligence before the meeting, onsite planning controls, opportunities or constraints


Q2

  1. The brief

  2. The budget

  3. The consultants

  4. Fees basis

  5. Authorities

  6. Documentation

  7. Builder negotiation

  8. Services during construction

  9. Client changes

  10. Job continuity

  11. CAA


17
New cards

Commissions & briefs


How do you calculate hourly charge out rates?

Reflects the total cost per hour to provide the service including salary, a factor for overheads & realistic allowance for profit


(Salary/ no. of hours per year) x overhead profit (2.5-3) + profit factor (25%)

1657.5

18
New cards

Commissions & Briefs


Q1. What should you always try to negotiate before lowering your fee?

Q2. What are the different ways fees can e calculated?


Q1

  1. Reducing scope

  2. Limiting number of design options

  3. Using standard systems rather than designed

  4. Require client to engage consultants

  5. Specifying that some design activities are done by the contractor, based on performance specifications and SD’s


Q2

  1. Percentage of cost of works - adjusted during project to account for changes

  2. Lump sum - set from scope / brief

  3. Hourly rates - typical for unknown scope, extra work (keep timesheets records)

  4. Combination of above

(ALL EXCLUDING GST)


19
New cards

Commissions & Briefs


How are hourly charge rates included in fee calculations?

Information for establishing fees for architectural services includes:

  • Historical records of the cost to the practice to provide services for the type of project

  • Understanding the scope of services required

  • Realistic hourly rates for staff

  • Appropriate margin of profit

  • Appreciation of market conditions


20
New cards

Commissions & Briefs


How do you know what fees to set for any particular project?

Establishing fees for services includes:

  • historical records of the cost to provide services for the type of project

  • Understanding the scope of services required

  • Realistic hourly hates for staff

  • Appropriate margin for profit

  • Appreciation of market conditions


21
New cards

Commissions & Briefs


Q1. What are the roles of an architect?

Q2. Why should someone commission the services of an Architect?

Q1

To be an independent certifier, valuer & assessor of quality


Q2. Architects must obtain necessary qualifications & have completed at least 2 years experience:

  • Governed by Architects Act & Code of Conduct

  • Proficient in all elements of NSCA

  • Complete regular CPD’s

  • Public entitled to services of professional registered architects


22
New cards

Commissions & Briefs


Q1. Are we still liable for free work?

Q2. What are the risks?

Q1

Yes.

Advised that free work still be managed with a simple contract, used to limit certain liabilities.


Q2

  • Architects still under duty of care, still liable

  • Client may not understand value, effort, time & creativity of good design

  • Protect copyright & moral rights


23
New cards

Commissions & Briefs


Are we still liable for part services?

Yes

Pre-purchase inspections / valuations - don’t accept this obligation

Sketch & DD drawings - low risk

Does. Doc. with CA - not ideal

CA only - allow extra fees to become familiar with docs

Pro-bono - still liable, standard of care still applies

24
New cards

Commissions & Briefs


How would you structure your fees at the start of a project if you were engaged for full services under a traditional lump sum contract?

SK & DD - 30%

Doc - 30%

Tender - 5%

Construction & DLP - 30%

25
New cards

Commissions & Briefs


What should an architect do before accepting a commission from a potential client?

  • Assess if they have ability to undertake the commission

  • Check insurances are adequate for size of job

  • Ensure have capacity to undertake

  • Research the client & make sure they’re someone you want to do business with

  • What can be outsourced?

  • Can you do work profitably?

  • Does it align with business plan?

  • Are you familiar & capable of meeting scope s3vices implied. H procurement model? (Novation?)


26
New cards

Commissions & Briefs


Q1. What is a brief and what does it do?

Q2. What is the scope?

Q1

Brief is a written document provided by the client, outlining their requirements for the project including accomodation, cost & programme

  • describes facilities to be provided & activities to be performed

  • Identify broad policies within which these are to be achieved in respect of time, cost & quality

  • Brief should not propose design solutions


Q2

Scope is the physical form of the brief

27
New cards

Commissions & Briefs


  • What happens if the client hasn’t got a brief?


  • The architect can provide a service in controlling & documenting the brief to assist the client - return brief

  • This is not a core service & may attract additional fees

  • In CAA AIA client must provide a brief


28
New cards

Commissions & Briefs


Q1. What are some brief requirements?

  • Q2. What are some typical headings?


Q1

  • Aim of the project

  • The functions, requirements

  • Clients emotional requirements

  • Non-negotiable’s, benchmark against which design will be measured

  • Financial xxxxx

  • Size constraints

  • Authorities

  • Program / time scale


Q2

  • Client

  • Site

  • Project

  • Project Management


29
New cards

Commissions & Briefs


Q1. What should be considered when marketing your services?

Q2. What are the ways architects win work.

Q1

  • what kind of arch. want to be?

  • Is there a market for these services?

  • Understand the client & their business / motives

  • Create a business plan?

  • Understand value of your services vs cost


Q2

Mechanical

  • learn craft, build reputation, find good partners, focus on what you want to do, join organisations, understand client, learn the players, ask for work, follow up, get out of the office

Organic

  • Be likeable, be interesting, be passionate, find right cultural fit, take a risk, take a stand, right place right time


30
New cards

Commissions & Briefs


What is a feasibility study and it’s aim?

  • To determine if it is a viable project in relation to budget & can assist in setting out the brief

  • Typically undertaken to determine the current value / dollar worth of the project

  • May entail comparing different project options


31
New cards

Commissions & Briefs


Q1. What might be some reasons for resigning a commission?

Q2. What are some measures to ensure you get paid?

Q1

  • no payment fees

    • Refuse to pay for increased services

    • Refuse pay for site surveys

    • Refuse pay for specialist consultants

  • Unrealistic budget / time constraints

  • Bypassing of architect

  • Design conflict

  • Personality conflict & ill health


Q2

  • initial CAA

  • Take deposit

  • Resort to security of payment act

  • Ask court for order to pay you

  • Unconditional bank guarantees


32
New cards

Commissions & Briefs


Q1. Should you charge for this initial meeting?

Q2. What are some considerations when formulating a fee proposal?

Q1

No charging may establish a contract exposing yourself to risk of dispute before project has begun. Not charging establishes a sense of moral obligation on client behalf.


Q2

  • The proposal is in architects control until sent

  • It should be fair & demonstrate trust of client

  • Period between phone call and proposal may be significant

  • Should be tailored to the client

  • Architect should be able to explain and defend it

  • It should hopefully just confirm for client what already decided and discussed


33
New cards

Building contracts

What common issues does the ABIC major works contract provide for?

  • urgent instructions

  • Seperate party

  • Change of type of security given by contractor

  • Provision of security payments for off-site plant and materials

  • Provision by owner of security to contractor

  • Dangerous or contaminated materials

  • Encroachment

  • Quality assurance systems

  • Seperate contractors

  • Amendments to program and consequences of amendment

  • Alternative dispute resolution

  • Expert determination of disputes

  • Arbitration of dispute

  • Conract confidentiality


34
New cards

Building contracts

What is the difference between ABIC Simple and Major works contracts?

Simple works - suitable for projects small or simple - $3mil or less - single dwelling


Major works - suitable for more complex projects - $3 mil +

  • has additional provisions for issues commonly arising in large scale projects

  • Not appropriate for single resi - home building act says must have staged payment regime for “owner occupied” - builders will seek monthly payment as will impact on cash flow


35
New cards

Building Contracts

What is the definition of the following terms:

  • contract documents

  • Contract price

  • Official document


  • all are defined terms within the selected building contract in ABIC xxx

  • Contract docs - special conditions, conditions of contract, spec, drawings and other docs nom.

  • Contract price - lump sum including worms PC and provisional sums, a talk of owner supplied goods, rise and fall, statutory taxes, import duties, exchange rates, industrial awards and gst,

  • Official docs - notices, approvals, certification, permit, license

  • PC - architect deems works substantially complete and any incomplete works or defects are minor in nature and number, commissioning tests have been completed, approvals required for occupation have been obtained


36
New cards

Building Contracts

When is security released back to the contractor?

ABIC MW 2018

  • 50% of security released when architect issues notice of practical completion

  • Cash retention - architect gives builder certificate equal to 50% of amount of security at same time as PC certificate issued

  • Unconditional guarantee - owner must return one of the two guarantees

  • Remainder released when architect issues final certificate less any sum still owing to client

  • Cash retention - architect issues final certificate with security amount and amount owing to client

  • Unconditional guarantee - certificate in favour of contractor then owner to provide unconditional guarantee draw on security to that amount and return remainder


37
New cards

Building Contracts

If unconditional guarantee is nominated as the preferred security, what must occur?

ABIC MW 2018

  • Within 10 days after contract executed, contractors must provide 2x unconditional guarantees equal in value to the nominated % in schedules

  • If no % nominated, 2 × 2.5% if contract price is default

  • Must be a type approved by the principal

  • If owner is a business it must be excl. GST


38
New cards

Building Contracts

When can the owner draw on security?

  • architect issues certificate in favour of owner where contractor fails to meet obligations to make relevant payments within relevant timeframes

  • Contractor doesn't dispute the architects certificates

  • Owner have complied with procedures set out within contract including giving notice when relevant


39
New cards

Building Contracts

What is the architects role in regards to security?

ABIC MW 2018

  • Under the concequences of their decisions, the risk each party bears and when security should be released

  • Must understand implications of various notices under contract


40
New cards

Building Contracts

What are the different types of contracts?

  • Lump sum - builder takes risk - builder takes scope and price - no more cost to client

  • Cost plus - risk to client - fixed % or guaranteed max price or max price - may be good for unknown scope, disputes may arise, no contingency

  • Schedule of rates - builder quotes on quantities

  • Incentive contracts - fixed price incentive with bonus or cost reimbursement - fee adjusted

  • Desk - build - contractor handles both - hard to project likely cost and quantity

  • Guaranteed maximum - builder compensated for costs incurred and naegun but there is max price failing - builder tweaks cost overruns


41
New cards

Building Contracts

What must the architect do when filling out contract information schedules?

  • Fill in all sections

  • Take advice on anything that is unclear

  • Consult client when necessary

  • Read the contract clauses referenced

  • Review special conditions

  • DO NOT amend the contract

  • If necessary to amend get legal practitioner to do so


42
New cards

Building Contracts

What is the general sequence of ABIC Major Works contract?

  • Schedules - party and project details, contract docs and special conditions, guarantees, sums

  • Obligations of parties prior to works

  • Security

  • Liabilitinsurance

  • The site

  • Obligations of parties throughout the works

  • Claims to adjust contract

  • Variations to works

  • Adjustments of provisional and prime cost sums

  • Adjustment of time

  • Completion of the works

  • Payment of works

  • Disputes, termination, misc. And definitions


43
New cards

Building Contracts

What is the architects role during construction?

clients agent / representative on the building site:

  • Issue client directions to builder

  • Asses whether works have been performed in accordance with the contract


Independent valuer / certifier- Legally required to be independent to:

  • Act as independent, suitable qualified person to certify works performed by builder

  • Certify claims made by the builder


Must know the building contract back to front - the client and builder will look to you


44
New cards

Building Contracts

How long is the statutory right to rescind the contract under an ABIC Simple Works contract and when does it start?

Cooling off period is 5 days from:

  • When owner received executed contract

  • Owner becomes aware that they are entitled to a copy of the executed contract


45
New cards

Building Contracts

If the owner or principal decided to exercise their rights and rescind the contract, what must take place?

  • must be within the rescind period

  • Client must provide written notice to the builder

  • Notice must be given directly to the builder or sent to address as per their contact details

  • Contractor may keep any expenses they incurred until the date they receive notice, but: Must return all other money to owner, and the owner is not liable to contractor for rescinding contract


46
New cards

Building Contracts

What are some considerations to contract selection?

  • Differing procurement models require differing contracts

  • Proceed cautiously in making recommendations

  • Significant PI insurance implications

  • Client's will ask - should provide informed opinion

  • Consult acumen or lawyer

  • Architect should be familiar with range of contracts

  • Familiarity with a contract won't overcome difficulties of selecting the wrong contract

  • Get advice


47
New cards

Building Contracts

What can inform the type of contract selected?

  • Since and complexity of the project

  • Specific needs of the project

  • State legislation

  • Impact on architects services


48
New cards

Building Contracts

What is the goal of the ABIC suite of contracts?

Developed by Master Builders Australia and AIA to provide a contract in plain English to balance competing rights and interests between contractors and principals, the produce a fair and workable contract, bringing certainty to dispute resolution and efficiency to deliverables.

49
New cards

Building Contracts

What contracts for part of the ABIC suite?

  • Basic works

  • Early works

  • Simple works

  • Major works


50
New cards

Building Contracts

Under the ABIC contract, who is intended to administer the contract?

The architect is intended to be the superintendent

51
New cards

Building Contracts

As the contract administrator, what must you alert the client of in contract selection?

It is vital that you advise your clients at least on the differences between the types of contracts and impact it will have on cost, their obligations and your administration of the contract - they MUST understand what they are agreeing to

52
New cards

Building Contracts

What are the consequences of getting a tender set of tender documents wrong?

  • Least to non-conforming tenders and less tenderers to chose from

  • Lead to significant financial consequences for your client


53
New cards

Building Contracts

What are the consequences of not acting inpartially?

  • Breach of duty of care to client - pay damaged to client


54
New cards

Building Contracts

What is the purpose of a building contract?

Legally binding document to define the relationship between parties to a building and construction project

55
New cards

Building Contracts

How are project types classified?

Either large or small scale depending on:

  • build size

  • Complexity

  • Cost

  • Number of build members on size


56
New cards

Building Contracts

What should be considered when selecting a type?

  • project type - size, scale complexity, level of scope of works documented, no. Of buildings on site

  • Contract value - large sum, require flexibility and design changes

  • Client considerations - experience sophistication, objectiveness and preference of contractural relationship


57
New cards

Building Contracts

What does Section B - documents setout?

  • discrepancies in documents - must provide notice to architect in writing and architect must promptly resolve

  • Order of precedence of docs: special conditions (Schedule 2), conditions of contract (schedule 1), specifications, drawings and other docs


58
New cards

Building Contracts

What is security and its purpose? When is it especially useful?

  • to provide financial protection to principal and contractor if the contractor fails to fulfil their obligations

  • When builder seeking pre-payment for goods and material


59
New cards

Building Contracts

How may security be provided under ABIC MW contract?

  • cash retention

  • Unconditional bank guarantee


60
New cards

Building Contracts

When is security held by the principal until?

  • the project is completed (eg. PC & FC), or

  • Contractor fails to comply with its obligations and the architect determines that principal can draw


61
New cards

Building Contracts

If parties wish for security to be provided under the contract what must they do?

  • Nominate they want it in schedules

  • Nominate which form of security

  • If not nominated, contractor can choose


62
New cards

Building Contracts

If cash retention is selected, what is the principal entitled to do?

  • owner may withhold up to 10% of each progress claim until value equates to nominated percentage of contract price

  • if no percentage is nominates, then 5% default in contract

  • Must be held in separate bank account as trustee for contractor including interest earned


63
New cards

Building Contracts

What does schedule 1 contain?

  • key information - party details, site info and financial details

  • Contract specifics - which remainder of contract is based on


64
New cards

Building Contracts

What are the consequences of missing schedule items?

The parties cannot retrospectively insert the terms or rely on them

65
New cards

Building Contracts

What does schedule 2 contain?

Special conditions

66
New cards

Building Contracts

What does section A contain?

‘Overview’ - provides parties with overview of how to conduct themselves. Parties must act reasonably and cooperative, and work through disputes to achieve effective project delivery

67
New cards

Building Contracts

What are some of the contractors obligations?

  • work diligently and maintain clean site

  • Warrants has capacity to entire contract

  • And is registered and licensed


68
New cards

Building Contracts

What are some client obligations?

  • Give possession of site

  • Appoint architect as contract administrator

  • Pay contractor the contract price

  • Warrants they have funds to pay contract price


69
New cards

Building Contracts

What are some of the architects obligations?

  • administer contract on behalf of the owner

  • Act as assessor, valuer and certifier


70
New cards

Building Contracts

What is an architects instruction?

  • instructions given to builder from architect at any rioting or orally if urgent


71
New cards

Contract Administration - Time

What are the 3 fundamental aspects of a building project?

  1. Time

  2. Cost

  3. Quality


72
New cards

Contract Administration - Time

What 2 issues does time revolve around?

  1. Time by which a party’s obligations under the contract are performed?

  2. The consequences for the party if they fail to perform their obligations by the required time


73
New cards

Contract Administration - Time

Which party are time constraints primarily imposed on?

Builder - promising to supply goods and services within a certain time

74
New cards

Contract Administration - Time

What is the architect’s role in relation to time?

  • supervise the contractural mechanisms

  • Assess claims


75
New cards

Contract Administration - Time

If a party fails to complete their obligations on time, can the innocent party terminate the contract?

No, contract has mechanisms for dealing with late performance. Breach of other important terms may give right to terminate or sue for damages

76
New cards

Contract Administration - Time

What is the prevention principle?

Where principle through own actions prevented contractor from completing contract on time, principle cannot insist on timely completion.

77
New cards

Contract Administration - Time

Can the principle claim damages when their ‘acts of prevention’ lead to contractor not completing works by date of PC?

No, they cannot claim disputes

78
New cards

Contract Administration - Time

Must the contractor complete the works (in relation to the prevention principle)?

Within a reasonable time

79
New cards

Contract Administration - Time

What should you and the client ensure is included on the contract to combat the prevention principle?

  • extensions of time clause

  • Let lawyer know if not in contract


80
New cards

Contract Administration - Time

When can the security be released?

  • read the contract - in contract

  • Architects ‘ superintendents decision\

  • Understand conditions of release

  • Contract allows to be held for considerable time - refer schedules


81
New cards

Contract Administration - Time

How do building contracts differ on counting time and delays?

  • differ on counting time - know how to count days

  • Differ on who carries risk on delays


82
New cards

Contract Administration - Time

What MUST you make every effort not to do during construction?

Do not delay the contractor in achieving practical completion

83
New cards

Contract Administration - Time

What is Float and who ‘owns’ it?

  • measure of predicted free time in a program between non-critical activities not affecting finishing time

  • Adjustment of time in contract critical to who owns float


84
New cards

Contract Administration - Time

What is a unilateral extension of time?

Where the superintendent grants EoT even when contractor doesn’t apply for it.

85
New cards

Contract Administration - Time

Where does the superintendent / architect adjust the contract?

  • in a progress certificate payment, or

  • In a final certificate


86
New cards

Contract Administration - Time

Is a variation the same as an EoT under ABIC?

No, there are different processes and time frames to follow.

87
New cards

Contract Administration - Time

What are the key things to consider when dealing with delays?

  1. What are the terms of the contract

  2. Precise cause of delay and responsibility for it

  3. Impact on program

  4. Impact on contract price


88
New cards

Contract Administration - Time

Where cam you dine the meaning of a ‘day’?

  • in the contract- usually calendar day or business day

  • If ‘ day’ only stated them assumed to be calendar


89
New cards

Contract Administration - Time

What is the commencement date?

Date of execution of the contract or day works begin or access to site - check the contract

90
New cards

Contract Administration - Time

What is a construction program?

Schedule of sequence of different activities taking place at the site, designed so project can be completed in fastest time possible.

91
New cards

Contract Administration - Time

What is the critical path?

In a construction program, shortest sequence of planned building activities possible to achieve the date for practical completion

92
New cards

Contract Administration - Time

What is important when reviewing shop drawings?

  • review, do not check, builder checks

  • Review against design, use stamp

  • Architect should not assume responsibility for their correctness, ask if they have checked them.


93
New cards

Contract Administration - Time

How should you manage shop drawing process?

  • Ask whether fabrication commenced - may be wasting time

  • Get correct consultants involved


94
New cards

Contract Administration - Time

Are shop drawings needed?

  • think before specifying need for shop drawings

  • They require time and responsibility to review


95
New cards

Contract Administration - Time

What are the key principles of architect’s instructions?

  • know your authority

  • Everything in writing

  • Do not tell the builder how to build


96
New cards

Contract Administration - Time

Should the contractor do all it reasonable can to mitigate the impact of delay?

Yes, it cannot sit on hands and wait to proceed

97
New cards

Contract Administration - Time

What is effect of the delay event?

Impact of event on critical path, varies from contract to contract

98
New cards

Contract Administration - Time

What are the possible clauses associated with the effect of delay event?

  1. Delay event causes delay in work by contractor

  2. Delay event causes delay in achieving PC

  3. Delay even causes delay in achieving PC by the date for PC


99
New cards

Contract Administration - Time

What should you check in each contract in regards to the effect of delay event?

What the clause states in regards to the effect of delay and assess whether relevant test of delay has been met

100
New cards

Contract Administration - Time

What must the contractor submit if they wish to claim EoT?

They must strictly comply with the procedures laid out in the contract.

AND

They must submit separate notices for both the delay event and claim for adjustment of time.