1/4
Looks like no tags are added yet.
why flood defense scheme needed
1998 flood- over 150 homes and businesses flooded
railway station and roads closed
total cost of damage £12.5 million
2007 flood- river cherwell rises by 8 feet due to 10 hours of torrential rainfall
theatre, railway station, bus station, leisure centre- 3 feet underwater
total cost of damages £3.2 billion
what was the scheme
create a flood storage resevoir by building embankments (2850m long)
flow control system to convey constant amounts of water as resevoir collects rain
cost £18.5 million
Biodiversity Action Plan Habitat- replant trees and hedgerows, convert places into parkland. for better absorption of water , increase interception reduce surface runoff.
pros
value of property in area increased as no longer have risk of flooding
QOL improved as attractive green areas created
new habitats made
A361 not closed in flood, people get to school and work
£100m will be saved as no repairs need to be made
level of anxiety with population reduced due to reduced risk
441 houses and 73 businesses protected
cons
cost about £18.5 million, extremely expensive
part of floodplain will still flood if river levels too high
location
south England, ,a town that sits on the river cherwell, which is a tributary of the river thames. has a population of 46,000 people. 50km north of oxford