CIE 415 Project Management Quiz

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/58

encourage image

There's no tags or description

Looks like no tags are added yet.

59 Terms

1
New cards

Project

Temporary endevor undertaken to create unique product/service/result

2
New cards

Product Project (built) life cycle phases

  • scope definition

  • design

  • procurement/construction

  • operation and management

  • rehabilitation/restoration

  • replacement

  • decommissioning and demolition


3
New cards

Service/result project (non-built) life cycle phases

  • scope definition

  • creation

  • final report


4
New cards

Scoping/Design

  • Define needs and objectives

  • Identify reasonable alternatives

  • Obtain stakeholder input

  • Analyze alternatives

  • Client review/approval

  • Prepare contract/construction documents


5
New cards

Project Design aspects

  • Data gathering

  • Analysis and assessment

  • Darft Product

  • Review/Finalize


6
New cards

Procurement/Construction

  • Contractor Bidding/Proposing

  • Review Bids/Proposals

  • Award/Contract Selection

  • Construction

  • Inspection

  • Project Acceptance


7
New cards

Procurement/Construction Requirements/Issues

  • All work is to be completed in accordance with drawings and specifications

  • Changes may need to be made

  • All proposed Changes must be evaluated to ensure design integrity is not compromised


8
New cards

Operations and Maintenance

  • Operation Personnel should be involved during design and construction

  • successful operation is proof of good desgin

  • deferred and inadequate maintenance of civil infrastructure is a major problem throughout the world

  • Maintenance costs must be included in project life cycle costs when comparing alternatives

  • Need for adequate maintenance must be considered during design so proper access can be provided


9
New cards

Rehabilitation/Restoration and Replacement challenge

Can we design new systems which will make eventual replacement easier

10
New cards

Rehabilitation/Restoration and replacement concern

System is in use and providing a service that must continue, even with increased cost for renewal


11
New cards

Decommissioning and Demolition

  • Not traditionally considered during design, but presents considerable engineering challange in cases (decommissioning nuclear power plant)

  • May have significant economic and environmental considerations and impacts

  • Costs must be considered in life cycle analysis


12
New cards

Project Planning

  • Process of identifying all activities and milestones necessary to complete the project

  • Key to effective project management and project success

  • First step in scheduling process

  • “Time Well Spent” “Failing to plan is planning to fail”


13
New cards

Getting started to plan the project

  • Identify Project Objectives

  • Identify Project Requirements

  • Identify Project Attributes


14
New cards

Scoping the Project

What you.your team will do and not do (Tasks and Deliverables)


15
New cards

Ex. Scoping the project Tasks (New-Multi-Use Trail on abandoned railroad)

  • Site Visit

  • Documentation Review

  • Survey/UAV video

  • Determine Deisgn Parameters

  • Develop stakeholder engagement plan

  • develop alternatives

  • client meetings


16
New cards

Ex. Scoping the project Deliverables (New-Multi-Use Trail on abandoned railroad)

  • Conceptual Plans

  • Preliminary Design Reoprt

  • Environmental Analyses

  • Approval Plans

  • Cost Estimates

  • Final Plans

  • Permits


17
New cards

Scope Control

Actively manage the scope of the project and work


18
New cards

Scope Creep

  • Uncontrolled expansion to product or project scope without adjustments to time, cost, and resources (PMBOK, 2013)

  • May be caused by engineer or client

  • May happen slowly, and not be detected in a timely manner

  • Change is inevitable


19
New cards

Risks of lack of scope control

  • Schedule slippage

  • cost overruns

  • Decline in team morale

  • Loss of client trust and satisfaction


20
New cards

How to manage project scope

  • Avoid doing more than what was agreed upon, expected, or necessary

  • resist the desire for perfection

  • determine if new requirement are within agreed upon scope

  • identify new items of work, scope changes in a timely manner


21
New cards

Resist the Desire for perfection


22
New cards

Quality Definition

  • Crosby (1979) Quality is Free - The first erroneous assumption is that quality means goodness, or luxury, or shininess, or weight

  • Snyder (1993) - Quality in engineering is a measure of how well engineering services meet the client’s needs and conform to governing criteria and current practice standards

  • Quality in a sevrice or product is not what you put into it, it it what the customer/client gets out of it


23
New cards

3 legs of quality

  1. Client/owner/customer wants/needs

  2. Governing Criteria

  3. Standard of Care


24
New cards

Delivering Quality

Achieving balance in 3 legs of quality

25
New cards

When is it ok to exceed expectations

  • You have met all requirements

  • You can afford to exceed expectations; provide extras are within budget and schedule constraints

  • Client values the extras you are giving them

  • BEWARE OF SCOPE CREEP


26
New cards

Standard of Care

  • Hawkins (2005) - The level of competence practitioners in their field customarily expect given the circumstances

  • ACEC - A professional Engineer are negligent if they fail to use the skill and care that a reasonably careful professional engineer would have used in similar circumstances


27
New cards

Quality costs=

Control costs+Failure Costs

28
New cards

Quality Costs


Used to track effectiveness of the TQM process to select quality improvement projects

29
New cards

Control Costs

Prevention costs+Appraisal Costs

30
New cards

Failure Costs

Internal Failure Costs_External Failure Costs

31
New cards

Prvenetion Costs

Costs resulting for quality activies to avoid deviations

32
New cards

Appraisal costs

costs resulting from quality activities employed to determine whether a product, process, or service conforms to established requirements

33
New cards

Internal Failure Costs

Costs incurred due to scrap, rework, reinspection, price reduction due to nonconformance

34
New cards

External Failure Costs

Costs incurred once project is in the hands of the client, increased maintneance, correction of errors, litigation costs, decreased reputation

35
New cards

Costs of conformance (to avoid failures)

  • Training

  • Document Process

  • Equipment

  • Time to do it Right

  • Testing

  • Destructive Testing Loss

  • Inspections


36
New cards

Costs of Nonconformance (because of failures)

  • Rework

  • Scrap

  • Liabilites

  • Warranty Work

  • Lost Business


37
New cards

Continuous Improvement

  • What do we need to achieve

  • How are we going to achieve it

  • How are we doing

  • What are we learning

  • How do we improve


38
New cards

What do we need to achieve

  • What are the priority results areas

  • Customers, Stakeholders & Suppliers

  • Employee

  • Missions & Values

  • Determine Where We are now

  • Incentives

  • Alignment


39
New cards

How are we going to achieve it

  • Asses Possibilities and Risks

  • Set Goals

  • Make Performance Agreements

  • Prioritize

  • Develop Action Plan

  • Allocate Resources

  • Incentives


40
New cards

How are we Doing

  • What & How to measure and track

  • Information Needs

  • Analyze Performance Data

  • Assess Performance

  • Assess & Validate Direction and Goals

  • Share Results

  • Incentives


41
New cards

What Are we Learning

  • How Do we Communicate

  • What are the outcomes

  • How do we manage knowledge

  • Assess expectations

  • Where do we go from here

  • employee engagement

  • incentives


42
New cards

How do we improve

  • Lead responsibly

  • What actions are necessary

  • Time

  • Resoucres

  • Outcomes

  • Assess Possible Options

  • Incentives


43
New cards

Metrics

  • Determine Factors most important to the customer

  • Colect Data

  • Analyze

  • identify


44
New cards

Benchmarking

How are we doing against toughest competitore/companies recognized as industry leaders. Seeks imporvement by measuring against other organizations

45
New cards

Camp (1989)

Benchmarking is the search for industry’s best practices that lead to superior performance

46
New cards

Peer Review

Practice of obtaining and independent unbiased evaluation of the adequacy and application of engineering principles, standards and judgement from an independent group of professionals having substantial experience in the same field of expertise

47
New cards

Peer review is in addition to

normal quality control and checking procedures required

48
New cards

ASCE Policy Statement 351 (July 9, 2016)

Promotes and supports the use of peer reviews for projects

49
New cards

Written guidelines

For tasks that are likely to be repeated

50
New cards

Written guidelines for

  • Technical Tasks

  • Managment tasks

  • Inspections

  • Maintenance tasks


51
New cards

Written Guidelines Benefits

  • Increased efficiency and consistency

  • Avoidance of “reinventing the wheel”

  • Training new personnel

  • Reduced negative impacts of staff turnover

  • reduced liability


52
New cards

Pareto Analysis

Bar Graph plotting cause of defect vs % of defects. Finds the most influential causes

53
New cards

SWOT acronym

  • Strengths

  • Weaknesses

  • Opportunities

  • Threats


54
New cards

Strengths and Weaknessess typically

Internal characteristics

55
New cards

Opportunities and Threats typically

Extenral characteristics

56
New cards

SWOT Goals

  • Maximize Strengths

  • Minimize impact of weaknesses

  • Capitalize on opportunies

  • mitigate threats


57
New cards

Value =

(Function+Performance)/Cost

58
New cards

Value Engineering

Systematic process designed to focus and improve upon the major elements of complex or high-cost projects


59
New cards

Value Engineering employs

Multi-disciplined team of experts to develop recommendations aimed at improving value of a project during it design phases