G.D.P: Gross Domestic Products

  • Sum of all goods and services produced in a country 

    • Measured on a monthly, quarterly, or annual basis 

  • In construction the government tracks this through all the permits pulled 

  • U.S. GDP is approximately $21 trillion 

  • U.S. Federal Debt ~ $40 trillion 

  • U.S. construction market ~5% of G.D.P -> $1 Trillion 


2
New cards

Types of Construction Projects

  1. Residential

  2. General Building

  3. Infrastructure

  4. Industrial


3
New cards

Residential

  • Project where people reside 

  • Generally Privately funded and owned

  • 40-50% of construction markets 

    • Supply and demand 

    • Consumer confidence: whether or not we can purchase 

    • Interest rates ~6%


4
New cards

Examples of residential construction projects

Houses, apartments, condominiums, duplex, town homes, trailer/trailer parks

5
New cards
6
New cards

Two Types of General Building Construction Projects

  1. Institutional

  2. Commercial


7
New cards

General Building: Institutional

Has a specific charter or purpose

  • Generally publicly owned 

  • Generally not for profit 


8
New cards

Examples of Institutional Construction Projects

Library, school buildings, residence halls, court house, prisons, police stations


9
New cards

General Building: Commercial

  • For commerce 

  • Generally for profit 

  • Generally privately owned 


10
New cards

Examples of a Commercial Construction Project

Hotels, Stores, stadiums

11
New cards

Infrastructure Construction Projects

  • 20% of construction markets 

  • Can be private or public 

  • Examples: Fiber optic, underground utilities, roads 


12
New cards

Industrial Construction Projects

  • 5-10% of construction markets 

  • Can be public or private 

  • Process, convert, or manufacture 

  • Examples: windmills, solar farms, nuclear power, data centers, wastewater treatment plant, factories 


13
New cards

Three Primary Participants in a Construction Project

  1. Owner

  2. Designer

  3. General Contractor


14
New cards

Owner

  • Take possession of the project 

  • Fund the project


15
New cards

Designer

  • Create plans and design work 

  • Architect and/or engineer (A/E) 

    • Architects: Create layouts (rooms), aesthetics, mood/environment, safety, egress, people conveyance, etc. 


16
New cards

General Contractor

direct contract with owner

17
New cards

4 Primary Org Structures

  1. Traditional

  2. Turnkey

  3. Owner-Builder

  4. Professional Construction Manager


18
New cards

Traditional

  • 3 separate primary positions 

    • Owner hires a separate A/E and G.C

    • Owner can hire multiple prime contractors 


19
New cards

Turnkey

  • Single firm hired by the owner responsible for design and construction 

  • Single firm can be: 

    • Single, full service firm providing design and construction services

      • Seen a lot in home building 

        • Overlap of design and construction process 

        • Which can 

          • Reduce overall project time, save money by modifying design, provide better communication between D&C, easier on owner

          • Fast paced: which can cause opportunity for errors or rework 

          • Risk of all responsibility on one firm 

    • Two separate firms (or more) combine for the project duration to fulfill design and construction 

      • Joint Venture (J.V.)

      • Bridgeway Commons (D.F.D)


20
New cards

Owner Builder

  • Owner responsible for design and construction

  • Examples: DOT, Counties, Cities, etc


21
New cards

Professional Construction Manager

  • 2 approaches

    • 1) G.C. - C.M Builds 

      • C.M. is responsible for cost and schedule 

      • Often called “C.M. at risk” 

      • Often the A/E is hired before the G.C./C.M

      • Example: U.S. Bank Stadium 

    • 2) Construction Manager

      • C.M. is not responsible for cost and schedule 

      • Advise the owner

      • C.M. is a 4th party entity 

      • Example: Marquette Interchange (WI DOT) 


22
New cards

Bidding Requirements

  • Invitation + Instructions

  • Information

  • Bid Form

  • Bid Bond


23
New cards

Invitation + Instructions


  • Who: Owner 

  • What: Type of project 

  • When: Bid date 

  • Where: Submit bid, project location 

  • How: Submit the bid 


24
New cards

Information

Ex: soil boring logs, wage rates, etc.

25
New cards
26
New cards

Bid form

  • G.C. provides their affiliation and price 

  • Owner can reject any and all bids 

  • Base bid with option for alternates 

  • Purpose of alternates: Bid evaluation 


27
New cards

Bid Bond

  • Owner requires G.C. to post a bond to bid the project 

  • Bid bond amount can be: 

    • A stated (flat) amount $ (sometimes called a guarantee) 

      • Ex. $75,000

    • % of Bid Price 

      • Ex. 5%

  • Surety companies sell bonds 

    • Ex. capital identity, west bend 

  • Ex. SQH $40,000,000 Bid 

    • (10% -> $4,000,000 Bid Bond) 

  • If a G.C. is selected by the owner and fails to enter/sign the construct, the owner can “cash” the bond

    • The G.C. forfeits the contract 

  • Owner can apply the cashed bond to cover the difference with the selected 2nd lowest bidder


28
New cards

Contract Forms

  • Agreement

  • Performance Bond

  • Payment Bond

  • Certificates


29
New cards

Agreement

  • Signed document between owner and contractor 

  • A/E has a separate contract with owner (Professional Services Contract) 

  • Witness sometimes notary of the public 


30
New cards

Performance Bond

  • Protects owner if signed contractor defaults and does not perform or complete the project 

  • Amount 

    • Public: 100% of Bid Price

    • Private: 0-100% of bid price value 


31
New cards

Payment Bond

  • File a lien for unpaid work 

  • Owner can require a lien waiver to make payment


32
New cards

Certificates

  • Examples:

    • Insurance

    • License

    • Affiliation 

    • DBE: Disadvantage Business Enterprise


33
New cards

DBE

  • Types: 

    • Military owned business (51% ownership atleast) 

    • Woman owned business

    • Veteran owned 

    • Disabled veteran owned business

    • Small business in HUD (Housing Urban Development Enterprise Zone) 

      • High unemployment rates 

      • High poverty 

      • Low economic output 

  • Stated % of the contract must go to the DBE firm (0-45%) 


34
New cards

Contract Conditions

  • General conditions

  • Supplemental conditions

  • Addenda and contract modifications


35
New cards

General Conditions

  • Brood definitions and processes 

  • Appendix D

  • Ex

    • Time, 100% complete

    • Changes in work 


36
New cards

Supplemental Conditions

  • Modifies general conditions

  • Ex. SQH, Deadline July 1 (2022) 


37
New cards

Addenda & Contract Modifications

  • Both modify the construction dates 

  • When? 

    • Addenda

      • Competitive $

      • Before Bid Date

    • Change Order 

      • Negotiated 

      • After Bid Date 


38
New cards

Commercial Contract Terms

  • Terms of monetary contract value between owner and G.C.

  • Terms also apply to “Professional Services Contracts” 

    • Owner and A/E

  • Also apples to G.C. and Subs, material suppliers, equipment rentals


39
New cards

4 Primary Commercial Contract Terms

  1. Lump Sum 

  2. Unit Price 

  3. Guaranteed Maximum Price (G.M.P.)

  4. Cost Plus 

  • Project May have multiple terms 

  • Competitive -> price (and also proposal, approach) 

  • Negotiated -> less competitive 


40
New cards

Lump Sum

  • Owner requests a single bid price for all work 

  • Owner can request a base bid (Lump Sum + Alternates) 

  • Used on building construction, but also other types of construction 

  • Any significant changes in project scope are processed with a Change Order 

    • Not competitive 

  • Pre bid scope changes are processed with an addendum 

    • Competitive 

  • Scope change must be “significant” in magnitude 

    • Ex. of not significant: change in paint color, patterns, ect. 

    • Ex. of significant: change in light fixtures 


41
New cards

Lump Sum: Owner Risks

  • Changes in design -> drive up costs “Negotiated”

  • G.C. can cut corners


42
New cards

Lump Sum: Contractor Risks

  • Constructions schedule changes and equipment/material deliveries

  • Actual costs > estimated cost

    • Mistakes during installation 

    • Increase in quantities

    • Miscalculations 

    • Fuel prices 

    • Weather 

  • Owner changes and time of change 


43
New cards

Unit Price

  • Owner provides a list of work items and estimated quantities, then bidder(s) provide unit price and total amount for each 

  • Typically, lowest grand total amount is awarded to that bidder 

  • Contracted G.C. is paid for actual quantities furnished and installed 

  • Common on Infrastructure 

  • Any significant changes require a change order 


44
New cards

Unit Price: Owner Risks

  • Actual quantity > estimated quantity, exceeds contract amount 

  • Owner changes impacting the contract amount

    • Missing items 

  • G.C. cuts corners 


45
New cards

Unit Price: Contractor Risks

  • Actual costs > unit bid price + amount 

    • Fuel prices 

    • Material supplier prices 

  • Owner changes impacting production and schedule 

    • Timing of the change 


46
New cards

Guaranteed Max Price

  • Owner sets a ceiling or maximum predict to build, and selected G.C. builds at or below the maximum 

  • Any savings can be shared 

  • Very common in Turnkey or C.M. organization structures 

  • Savings can be shared 


47
New cards

Guaranteed Max Price: Owner Risks

  • G.M.P is set too low 

  • G.C. cuts corners to enhance the savings 

  • Owner changes exceed G.M.P 


48
New cards

Guaranteed Max Price: Contractor Risks

  • Must build at or below G.M.P

    • Wage rates, fuel costs,ect. 

  • Owner changes reducing savings and sharing amount 


49
New cards

Cost-Plus

  • Owner pay G.C. for their time and materials then add: 

    • Flat fee amount- Ex. $10,000

    • Percent Fee - Default 3.25%

  • Generally little design, no G.M.P.  at start, high risk, emergency repairs 

  • Sometimes called I.D.I.Q: Indefinite Delivery/Indefinite Quantity 

    • Examples: International Projects, water main breaks 


50
New cards

Cost-Plus: Owner Risks

  • Unknow final const at start of construction 

  • Unknow completion 

  • Contractor resource load (people, equipment) and production 


51
New cards

Cost-Plus: Contractor Risks

  • Safety 

  • Unknown completion 

  • Profit


52
New cards

Contractor Cash Flow

  • Working capital = short term assets - short term liabilities 

    • Assets: cash on hand, accounts receivable, land, office, equipment 

    • Liabilities: accounts payable, debt, mortgage, claims 

    • Ratio = (short term assets/short term liabilities) > 1.2


53
New cards

Techniques to Achieve a Positive Cash Flow

  • Reduce costs

  • Bank-Line-Of-Credit

  • “Borrow” cash from another project 

  • Add on hand material invoices to pay requests 

  • Mobilization bid item 

  • Unbalance the bid -> artificially inflate the early work items the deflate the later