Ch. 12: Finite Scheduling, Theory of Constraints, Drum, Buffer and Rope

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/27

encourage image

There's no tags or description

Looks like no tags are added yet.

28 Terms

1
New cards

Finite Capacity Scheduling

  • AKA finite scheduling

  • Production planning method that creates creates realistic schedule

  • Considered limited resource

    • Machine availability, labour and materials

  • Ensures efficiency


2
New cards

Features of FCS

  • Bottleneck management

  • Capacity management

  • Realistic scheduling


3
New cards

Benefits of FCS

  • Increased efficiency

  • Reliable delivery dates

  • Cost reduction

  • High accuracy

  • Optimized utilization

  • Enhanced visibility


<ul><li><p>Increased efficiency </p></li><li><p>Reliable delivery dates </p></li><li><p>Cost reduction </p></li><li><p>High accuracy </p></li><li><p>Optimized utilization</p></li><li><p>Enhanced visibility </p></li></ul><p></p>
4
New cards

CUTE

  • Common Utility Equipment

  • Used by different departments

  • : Check in desks at airports


5
New cards

Scheduling in Manufacturing

  • Inv. For smooth demand

  • Machine schedules

  • Union contracts

  • Social or behaviourial issues


6
New cards

Scheduling in Service

  • Schedule staff

  • Maintain inventories

  • Legal issues for flexibility

  • Social and behavioural


7
New cards

Scheduling Criteria

  • Min completion time

  • Max. Utilize of facilities

  • Min WIP inventory

  • Min customer waiting time

    • Optimism resources so objectives are met


8
New cards

Planning Files

  • Am item master file obtaining information about each component

  • A routing file indicates each component’s flow through the shop

  • A work-center master file contains information about the work center


9
New cards

Forward Scheduling

  • As soon requirements are known

  • Produces feasible schedule even if they don’t meet due dates

  • Results in buildup of WIP inv.


<ul><li><p>As soon requirements are known </p></li><li><p>Produces feasible schedule even if they don’t meet due dates </p></li><li><p>Results in buildup of WIP inv. </p></li></ul><p></p>
10
New cards

Backward Scheduling

  • Begins with due dates and schedules final operation first

  • Schedule produced backwards

  • Resources may not be available


<ul><li><p>Begins with due dates and schedules final operation first</p></li><li><p>Schedule produced backwards </p></li><li><p>Resources may not be available </p></li></ul><p></p>
11
New cards

Critical Ratio

  • An index number found by dividing the time remaining until the due date by the work time remaining on the job

  • Jobs with low critical ratios are scheduled ahead of jobs with higher critical ratios

  • Performs well on average job lateness criteria

= due date - today’s date / work/lead time remaining

= time remaining / workdays remaining


12
New cards

Critical Ratio Technique

1. Helps determine the status of specific jobs
2. Establishes relative priorities among jobs on a common basis
3. Relates both stock and make-to-order jobs on a common basis
4. Adjusts priorities automatically for changes in both demand and job progress
5. Dynamically tracks job progress

13
New cards

Assignment Method

  • Special class of linear programming models that assigns tasks or jobs to resources

  • Min cost or time

  • 1 worker = 1 machine


14
New cards

Limitations of Rule Based Dispatching Systems

  • Needs to be revised to adjust to changes

  • Don’t look up or downstream

  • Do not look beyond due dates


15
New cards

Divergence Points

The specific stage in a production process where a generic, unfinished product is customized or finalized into a specific end item


16
New cards

Demand Management

  • Appointment or reservation systems

  • FCFS sequencing rules

  • Discounts or other promotional schemes

  • When demand management is not feasible, managing capacity through staffing flexibility may be used


17
New cards

Constraint

  • Anything that prevents the system from achieving a goal

  • Internal or external

  • Always at least 1


18
New cards

Theory of Constraints

  • System based methodology that identifies and address the weakest link in a process

  • Limits goals to be achieved


19
New cards

Five Focusing Steps

  • Help identify limiting factor

  1. Identify

  2. Exploit

  3. Subordinate

  4. Elevate

  5. Repeat


20
New cards

Drum Buffer Rope

  • Drum: Constraint that sets the pace for entire process

  • Buffer: Small amount of time or resources (inventory) placed before the constraint

  • Rope: Communication that inventory has been consumed to trigger more inventory to be released into the process without creating excess


21
New cards

TOC Step 1: Identify the Constraint

  • Look for signs to a constraint

  • Gather data from work software

  • Audits/inspections

  • Metrics: Overall Equipment Effectiveness and Overall Labor Effectiveness

  • Root cause analysis

  • Ask operators


22
New cards

TOC Step 2: Exploit the Constraint

  • Ensure it is running at 100% capacity using your resources

  • Non-constraints should NOT run at 100%


23
New cards

TOC Step 3: Subordinate All Non-Constraints

  • Look for factors outside the constraint

  • Without looking it could lead to build ups from non bottlenecks

  • Need to give a measure of control


24
New cards

TOC Step 4 : Elevate Constraint Performance

  • Max and take action to break the constraint

  • Serious changes; new tech and redistribution of resources

  • Establish best practices

  • Analyze KPIs

  • Perform time studies

  • Eval. Resources


25
New cards

TOC Step 5: Repeat

  • Look for the next one

  • New bottle necks with take the place


26
New cards

Benefits of DBR

  • Reduces WIP

  • Increases throughput: Bottleneck is fully utilized

  • Improves delivery times



27
New cards

Key Technologies in TOC

  • AI and Machine Learning

  • Predictive Analytics

  • Process mining tools

  • Simulation models

  • IoT

  • Automation tools


28
New cards

TOC and Tech in Practice

  • IT Service Management (ITSM)

  • Manufacturing

  • Software development