Tariffs, Metering, and Power Factor

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/39

flashcard set

Earn XP

Description and Tags

Comprehensive practice flashcards covering tariffs, metering systems, power factor correction, instrument transformers, and grid management concepts from the Phase 6 Electrical Craft Practice notes.

40 Terms

1
New cards

Maximum Demand (MD)

The highest power (measured in kWkW or kVAkVA) drawn by an electrical consumer over a specified measuring interval, typically 15 minutes15\text{ minutes} or 30 minutes30\text{ minutes}.

2
New cards

Load Factor

The ratio of average load to maximum demand over a specified period of time (Load Factor=Average LoadMaximum Demand\text{Load Factor} = \frac{\text{Average Load}}{\text{Maximum Demand}}), where a higher value indicates steady, more cost-effective energy usage.

3
New cards

Diversity Factor

The ratio of the sum of individual maximum demands to the maximum demand of the entire group (Diversity Factor=∑Individual Maximum DemandsGroup Maximum Demand\text{Diversity Factor} = \frac{\sum \text{Individual Maximum Demands}}{\text{Group Maximum Demand}}), which is always greater than 11 (>1> 1) and allows supply sizing below total connected load.

4
New cards

Two-Part Tariff

An electricity tariff consisting of a fixed standing charge (€/day\text{€/day}) to cover network capacity and capital availability, combined with a variable unit charge (€/kWh\text{€/kWh}) for the actual energy consumed.

5
New cards

Standard Variable Tariff (SVT)

An electricity price plan with no fixed end date where unit rates can rise or fall based on wholesale market changes, typically carrying no exit fees but often priced higher than fixed deals.

6
New cards

Fixed-Term Tariff

An electricity pricing contract that fixes unit rates and standing charges for a set duration (typically 1 to 2 years1\text{ to }2\text{ years}), providing budget certainty against price hikes but often subject to early exit fees.

7
New cards

Night-Saver Tariff

A dual-rate tariff structure offering discounted unit rates during night hours (e.g., 11 p.m. to 8 a.m.11\text{ p.m. to }8\text{ a.m.} or 11 p.m. to 7 a.m.11\text{ p.m. to }7\text{ a.m.}) and higher rates during daytime hours, suited for night storage heating or electric vehicle charging.

8
New cards

Time-of-Use (ToU) Tariff

A tariff enabled by smart metering where electricity prices vary across distinct time bands (such as off-peak, shoulder, and peak hours) to incentivise shifting power consumption away from periods of high grid demand.

9
New cards

Public Service Obligation (PSO) Levy

A statutory levy charged to all final electricity consumers in Ireland to recover additional generation costs from sustainable, renewable, alternative, and indigenous fuel sources (such as peat) for environmental protection and supply security.

10
New cards

Maximum Import Capacity (MIC)

The agreed limit of electrical power (rated in kVAkVA) contracted between a commercial/industrial consumer and ESB Networks to meet the site's maximum power requirements.

11
New cards

Excess Capacity Charge

A penalty fee billed to non-domestic consumers on maximum demand tariffs for every kVAkVA drawn above their contracted Maximum Import Capacity (MIC) during a billing period.

12
New cards

Low Power Factor Surcharge

A tariff penalty applied to industrial and commercial consumers in Ireland when their reactive energy consumption (kVArhkVArh) exceeds one-third (13\frac{1}{3}) of their total active energy consumption (kWhkWh) in a billing period.

13
New cards

Demand Charge (Low Voltage Maximum Demand)

A charge levied on large business consumers for every kWkW of average power exceeding a 30 kW30\,kW threshold drawn during peak hours (17:00 to 19:0017:00\text{ to }19:00, Monday to Friday) during the winter months (1st November to end of February1\text{st November to end of February}).

14
New cards

50% Rule (Maximum Demand Billing)

A tariff regulation specifying that the maximum demand billed in any two-month period will be either the actual measured maximum demand or 50%50\% of the highest maximum demand billed in the preceding five billing periods, subject to a minimum of 30 kW30\,kW.

15
New cards

Winter Demand Reduction Incentive (WDRI)

A scheme during November/December and January/February where the ESB restricts maximum demand metering from the standard weekday 13-hour window (8 a.m. to 9 p.m.8\text{ a.m. to }9\text{ p.m.}) to just the two-hour evening peak (5 p.m. to 7 p.m.5\text{ p.m. to }7\text{ p.m.}), rewarding demand reduction.

16
New cards

Active Power (PP)

The true, wattful power component that performs physical work, produces light, or creates heat in an AC electrical circuit, measured in kilowatts (kWkW) and calculated as P=V×I×cos⁡(ϕ)P = V \times I \times \cos(\phi).

17
New cards

Reactive Power (QQ)

The wattless, non-working power component measured in reactive kilovolt-amperes (kVArkVAr) that sustains oscillating electromagnetic fields in inductive devices, calculated as Q=V×I×sin⁡(ϕ)Q = V \times I \times \sin(\phi).

18
New cards

Apparent Power (SS)

The vector combination of active power (kWkW) and reactive power (kVArkVAr) supplied to an AC circuit, measured in kilovolt-amperes (kVAkVA) and expressed by the power triangle relationship S=P2+Q2=V×IS = \sqrt{P^2 + Q^2} = V \times I.

19
New cards

Power Factor (PF)

The ratio of active power (kWkW) to apparent power (kVAkVA), represented by cos⁡(ϕ)\cos(\phi), indicating the overall electrical efficiency of power delivery to an installation.

20
New cards

Capacitor Rating Formula (QcQ_c)

The mathematical formula to determine the required power factor correction capacitor rating: Qc=P×[tan⁡(ϕ1)−tan⁡(ϕ2)]Q_c = P \times [\tan(\phi_1) - \tan(\phi_2)], where ϕ1=arccos⁡(initial PF)\phi_1 = \arccos(\text{initial PF}) and ϕ2=arccos⁡(target PF)\phi_2 = \arccos(\text{target PF}).

21
New cards

Current Transformer (CT)

An instrument transformer used to step down high primary currents (100 A to 4000 A100\,A\text{ to }4000\,A) to standardised, safe secondary currents (5 A5\,A or 1 A1\,A) for measurement and system protection.

22
New cards

CT Secondary Open-Circuit Hazard

The dangerous failure condition occurring when a CT secondary circuit is opened under load, causing all primary current to act as magnetising current, producing lethal kilovolt (kVkV) spikes, insulation breakdown, and core saturation.

23
New cards

CT Burden

The total impedance of the secondary circuit connected to a current transformer, rated in volt-amperes (VAVA), which must not be exceeded if the rated accuracy class is to be maintained.

24
New cards

Voltage Transformer (VT)

An instrument transformer designed to scale high or medium distribution voltages (such as 400 V400\,V or 11 kV11\,kV) down to a standard 110 V110\,V secondary level for instrumentation and protection.

25
New cards

VT Secondary Short-Circuit Hazard

The hazardous failure state of a voltage transformer acting as a voltage source, where a secondary short circuit causes massive overcurrent that destroys the windings unless protected by secondary fuses.

26
New cards

Smart Meter

An electronic metering device equipped with an analog-to-digital converter, microprocessor, and two-way communication module that records consumption in 30-minute intervals and sends readings directly to the utility.

27
New cards

Base Load

The continuous minimum level of electricity demand on the electrical grid across a 24-hour cycle, supplied by the most cost-effective and efficient generating stations running continuously.

28
New cards

Pumped Storage

The technique of storing potential energy by using inexpensive, off-peak night electricity to pump water to an elevated reservoir, later releasing it through turbines during peak hours to modify the daily load curve.

29
New cards

Turlough Hill

Ireland's pumped storage hydroelectric generating station located in County Wicklow, used to balance national electricity grid demand by pumping water at night and generating power during peak hours.

30
New cards

Ardnacrusha

The ESB's first hydroelectric power generating station, commissioned on the River Shannon in 1947 to harness renewable water energy for national supply.

31
New cards
<p>Two-Wattmeter Method</p>

Two-Wattmeter Method

A power measurement method used on a three-phase, three-wire system (balanced or unbalanced) where the total real power is the algebraic sum of both readings: Total Power=W1+W2\text{Total Power} = W_1 + W_2.

32
New cards
<p>Three-Wattmeter Method</p>

Three-Wattmeter Method

A power measurement configuration used on a three-phase, four-wire supply with a neutral conductor to determine the total real power of an unbalanced load: Total Power=W1+W2+W3\text{Total Power} = W_1 + W_2 + W_3.

33
New cards
<p>Optical Scatter Smoke Detector</p>

Optical Scatter Smoke Detector

An optical detector comprising a matte black chamber, a light source focusing onto a light trap, and a right-angle photocell that detects light scattered by smoke particles to trigger an alarm.

34
New cards
<p>Analogue Meter Dial Reading Rule</p>

Analogue Meter Dial Reading Rule

The standard procedure of reading dials from left to right, recording the lower number whenever a pointer sits between two figures (or recording 99 if the pointer is between 99 and 00).

35
New cards
<p>National Grid System Architecture</p>

National Grid System Architecture

The electrical infrastructure hierarchy where bulk electricity is generated at power stations, stepped up to high transmission voltages (400 kV/220 kV400\,kV / 220\,kV), stepped down at substations, and distributed by ESB Networks at low utilization voltages (230 V/400 V230\,V / 400\,V).

36
New cards

ESB Networks Customer Interface Code Requirements

Regulations mandating commercial and industrial consumers to maintain a minimum power factor of 0.950.95 lagging to avoid penalty charges, with the authority holding the right to refuse connection for new loads below 0.850.85.

37
New cards

Commission for Regulation of Utilities (CRU)

The independent statutory regulator in Ireland responsible for consumer protection, energy safety, utility market oversight, and the phased deregulation of retail electricity suppliers.

38
New cards

Deregulation of Irish Electricity Supply

The policy process concluded in 2011 ending price regulation on ESB Customer Supply once its domestic market share dropped below 60%60\% and at least two competitors reached 10%10\% market share, prompting its rebranding as Electric Ireland.

39
New cards

Bulk Group Power Factor Correction

A central power factor correction system where a bank of capacitors is connected across the main incoming busbars and automatically switched in stages via contactors to compensate overall installation load.

40
New cards

Individual Power Factor Correction

Connecting static power factor correction capacitors directly across individual inductive loads (e.g., motor terminals) so that capacitance is introduced only when the specific load operates, reducing cable currents locally.