1/14
Looks like no tags are added yet.
When is an exclusion clause valid
-Clause has been properly incorporated into contract
-Clause is reasonable per statute
When has a clause been properly incorporated
-Exclusion clause must be given at the time the contract is made
-If document is signed
-If document not signed, clause must have been sufficiently highlighted
Substantial performance
Contract has mostly been completed. Payment for work carried out should be made
Severable contracts
Contracts in stages
Discharged through frustration
Destruction of subject matter
Personal incapacity
Non-occurrence of an event
Government intervention
Impact of frustration
-Any monies paid must be returned
-Any sums due cease to be payable
-Expenses may be retained
Repudiatory breach
-Fundamentally important term has been breached
-Injured party has been deprived of benefit of contract
-Anticipatory breach (duty to mitigate does not arise until breach is accepted)
Remoteness of damages
-Arise naturally from the breach
-Be reasonably foreseeable
Expectation interest
Put the parties in the position they would have been had the breach of contract not happened
Reliance interest
Suing for costs incurred
Specific performance
Court directs a party to complete their contractual obligation though does not happen if:
-performance requires supervision
-contract is for personal service
-damages are adequate
Injunctions
Court directs party to stop breaching contractual obligations
Mandatory Injunction
Defendant required to undo something that was in breach of contract
Prohibitory Injunction
Defendant must promise not to do something (observe a negative promise)
Asset-freezing injunction
Defendant prohibited from dealing with an asset