The first step in installing any tubing or piping system is _______.

Planning

2
New cards

The data for all relevant instrument loops is usually contained in a(n) ______.

P&ID

3
New cards

Which of the following documents may contain the process piping system operating pressures and temperatures?

Project piping specifications

4
New cards

When planning the location of instrumentation piping and tubing, ____________.

Making plans to avoid present and future obstructions

5
New cards

The range for the ideal bend radius for piping or tubing is ________.

two-and-a-half to three times the outside diameter

6
New cards

Developing an isometric sketch requires the use of _______.

fitter's math

7
New cards

All the items that are needed to properly install a particular instrument, and any instruments identical to it, are typically listed on a(n) _________.

bill of materials

8
New cards

Before bending piping or tubing, an instrument fitter must know the ________.

distance to the first bend and its angle

9
New cards

The basis for all tubing or piping line measurements is typically the _____.

center line

10
New cards

How does the springback for copper tubing compare to the springback for stainless steal tubing?

Copper tubing has less springback.

11
New cards

What is the gain for a 45-degree bend in 1/2-inch tubing?

1/16 inch

12
New cards

A support that permits movement in the presence of slowly applied pressure but locks up to become rigid during rapidly applied loads is a ______.

snubber

13
New cards

Tubing installations should be supported at a minimum of every _______.

3 feet (0.9 meters)

14
New cards

Unlike most piping and conduit, tubing requires cushioning to protect against _______.

outer wall damage

15
New cards

What sometimes separates tubing runs from cable runs in cable trays?

Partitions

16
New cards

According to OSHA standards, the minimum headroom for piping installations in pedestrian areas is _______.