Operations and Supply Chain Management: Inventory, Production, Lean, and Projects

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/53

flashcard set

Earn XP

Description and Tags

Vocabulary practice flashcards covering inventory systems, manufacturing planning and control, Lean/JIT production, and project management methodologies.

54 Terms

1
New cards

Inventory (APICS Definition)

Those stocks or items used to support production (raw material and work-in-process items), supporting activities (maintenance, repair and operations), and customer service (finished goods and spare parts).

2
New cards

Work-in-Process (WIP)

Inventory items that are currently undergoing conversion into finished products within the transformation process.

3
New cards

Cycle Stock

Components or products that are received in bulk by a downstream partner, gradually used up, and then replenished.

4
New cards

Safety Stock

Extra inventory that companies hold to protect themselves against uncertainties in either demand or replenishment lead time.

5
New cards

Anticipation Inventory

Inventory held in advance to meet anticipated surges in customer demand.

6
New cards

Hedging Inventory

A form of inventory buildup used to buffer against potential disruptive events (such as strikes, price increases, or civil unrest) involving speculation.

7
New cards

Transportation Inventory

Inventory that is moving from one link in the supply chain to another, often described as being in the pipeline.

8
New cards

Smoothing Inventory

Inventory used to smooth out operational differences between upstream production capacities and downstream customer demand fluctuations.

9
New cards

Independent Demand Inventory

Inventory items whose demand levels originate from outside the organization and are beyond a company's complete control, requiring forecasting.

10
New cards

Dependent Demand Inventory

Inventory items whose demand levels are tied directly to the company's planned production of another parent item.

11
New cards

Periodic Review System

An independent demand inventory system in which the inventory level of an item is checked at regular intervals and restocked to a predetermined target level, calculated as Q=R−IQ = R - I.

12
New cards

Continuous Review System

An inventory system where inventory levels are constantly monitored, and a fixed order quantity is released as soon as the stock drops to the reorder point.

13
New cards

Economic Order Quantity (EOQ)

The order quantity that minimizes the sum of annual ordering and holding costs, located at the point where yearly holding costs equal yearly ordering costs: EOQ=2×D×SHEOQ = \sqrt{\frac{2 \times D \times S}{H}}.

14
New cards

Reorder Point (ROP)

The inventory level that triggers a replenishment order, calculated under certainty as demand rate multiplied by lead time (ROP=d×LROP = d \times L).

15
New cards

Single-Period Inventory System

An inventory model used when items are perishable or demand occurs at only a single point in time, balancing expected shortage costs against expected excess costs.

16
New cards

Bullwhip Effect

An extreme change in the supply position upstream in a supply chain generated by a small change in demand downstream.

17
New cards

Inventory Pooling

Holding safety stock in a centralized location so that multiple customer zones share the safety inventory, lowering total system holding costs.

18
New cards

Planning and Control

A set of tactical and execution-level business activities that includes master scheduling, material requirements planning (MRP), production activity control (PAC), and vendor order management.

19
New cards

Sales and Operations Planning (S&OP)

Tactical capacity planning that establishes overall production, workforce, and aggregate inventory levels at the monthly product-family level.

20
New cards

Master Production Schedule (MPS)

A detailed planning process that controls the timing and quantity of production for specific end products and serves as the primary coordination point between sales and manufacturing.

21
New cards

Projected Ending Inventory (EItEI_t)

The estimated on-hand inventory at the close of time period tt, calculated as EIt=EIt−1+MPSt−max⁡(Ft,OBt)EI_t = EI_{t-1} + MPS_t - \max(F_t, OB_t).

22
New cards

Available to Promise (ATP)

The number of end-item units available to commit to new customer orders each week after accounting for quantities already booked.

23
New cards

Material Requirements Planning (MRP)

A planning process that translates the master production schedule into planned component orders using bills-of-material, explosion, and backward scheduling.

24
New cards

Bill of Material (BOM)

A comprehensive listing of the subassemblies, intermediates, parts, and raw materials required to manufacture one unit of a parent assembly.

25
New cards

Product Structure Tree

A graphical hierarchy illustrating how lower-level components and subassemblies in the bill of materials are assembled into a Level 0 end item.

26
New cards

Exploding the BOM

The process of working backward from the master production schedule of a Level 0 end item to determine the required quantities and order dates for subassemblies and components.

27
New cards

Net Requirements (NRtNR_t)

The actual component deficit that must be satisfied in time period tt, calculated as NRt=max⁡(0,GRt−EIt−1−SRt)NR_t = \max(0, GR_t - EI_{t-1} - SR_t).

28
New cards

Scheduled Receipts (SRtSR_t)

Units of an item that are already on order from a previous replenishment decision and are scheduled to arrive in period tt.

29
New cards

Production Activity Control (PAC)

An execution-level manufacturing function that ensures in-house operations proceed according to plan and alerts managers to operational disruptions.

30
New cards

Vendor Order Management

An execution-level purchasing function that ensures externally ordered materials arrive on time from supply chain partners and initiates corrective action when problems arise.

31
New cards

Lean

A production philosophy emphasizing the minimization of all resources, including time, by identifying and systematically eliminating non-value-adding activities.

32
New cards

Just-in-Time (JIT)

A philosophy of manufacturing synonymous with Lean that focuses on the planned elimination of waste and continuous productivity improvement.

33
New cards

Waste (Muda)

Any process, step, or activity that does not add value to the finished good or service from the customer's perspective.

34
New cards

Lean Six Sigma

A combined methodology integrating the organizational structure and statistical variance reduction of Six Sigma with Lean's emphasis on waste reduction.

35
New cards

Kanban System

A visual production control system utilizing physical cards, containers, or marked spaces to signal the withdrawal and production of inventory across a supply chain.

36
New cards

Two-Card Kanban System

A specific kanban implementation utilizing one card to authorize the physical movement of parts and a second card to authorize component production.

37
New cards

Move Card

A kanban card indicating when a container of parts should be transferred to the subsequent step or work center in the process.

38
New cards

Production Card

A kanban card that provides authorization to manufacture an additional container of parts at the current work station.

39
New cards

Pull System

A production environment where downstream customer demand triggers upstream material movement and assembly, preventing unneeded inventory buildup.

40
New cards

Project

A temporary endeavor undertaken to create a unique product, service, or result, characterized by non-routine tasks, distinct start and completion dates, and cross-functional teams.

41
New cards

Triple Constraint

The foundational project trade-off model balancing scope, time, and cost to optimize quality and customer value.

42
New cards

Concept Phase

The initial project phase involving broad scope definition, preliminary feasibility assessment, and rough budget estimates typically within ±30%\pm 30\%.

43
New cards

Project Definition Phase

The second project phase, focusing on organizing project structure, defining tentative schedules, and narrowing budget estimates to within ±5%\pm 5\% to 10%10\%.

44
New cards

Planning Phase

The third project phase, where detailed schedules, task networks, work breakdown structures, budgets, and specific individual staffing assignments are finalized.

45
New cards

Performance Phase

The fourth project phase, consisting of directing, coordinating, and executing the project baseline plan.

46
New cards

Post Completion Phase

The final project phase, where the final deliverable is evaluated, project personnel are reassigned, and a formal post-implementation review is conducted.

47
New cards

Gantt Chart

A graphical scheduling tool displaying planned activity durations and tracking progress across a calendar timeline, but lacking explicit precedence logic.

48
New cards

Critical Path Method (CPM)

A network-based project management scheduling technique that uses a single deterministic duration estimate for each task to evaluate project duration and slack.

49
New cards

Activity on Node (AON)

A project network format where individual tasks are designated by lettered nodes and precedence constraints are indicated by directional connecting arrows.

50
New cards

Forward Pass

The left-to-right calculation process across an activity network to identify earliest start (ESES) and earliest finish (EFEF) dates for every project task.

51
New cards

Backward Pass

The right-to-left calculation process through an activity network to determine latest finish (LFLF) and latest start (LSLS) dates without extending overall project completion.

52
New cards

Critical Path

The longest continuous sequence of activities through a project network, dictating the shortest possible time in which the project can be completed, with all activities possessing zero slack.

53
New cards

Slack Time

The amount of time an activity can be delayed without delaying the project finish date, calculated as LS−ESLS - ES or LF−EFLF - EF.

54
New cards

Crashing

Shortening the overall duration of a project by adding resources to compress task times along the critical path at minimum incremental cost.