4x
Every scaffold And component supports its own weight and four times the max extended loads
6x
Suspension ropes, wires, and synthetic, support minimum six times the max load intended
4 to 1
Supported staff holds taller than four times their minimum base width must be restrained from tipping by guy tying or bracing
25 50 75
Duty ratings in pounds per foot
Light weight 25 Med 50 Heavy 75
Load 25
Full Thick? Nominal?
10ft, 8ft
Load 50
Full Thick? Nominal?
8ft, 6ft
Load 75
Full Thick? Nominal?
6ft, not permitted
Brick layers
50 PSF max load Never more than three tiers stacked directly in a line
Horse Scaffold
No more than two tiers/10 feet whichever is less horses directly over horses
Form & Bracket
No more than two employees in any 8 feet. Tools and materials capped at 75 pounds.
Float/Ship
750 pound max load Intended
Mobile w riders
Moves with Employee only if surface is within 3° of level
10ft
Fall protection required for each employee 10 feet above lower level
38”-45”
Top rail height on support scaffold placed in service after January 1, 2000
10ft
Toe boards require a long platform edge is more than 10 feet above lower level
50lbs
Scaffold toe boards withsand 50 pounds force in any downward horizontal direction
No 18 gauge
Screen between toe boards and top rails is number 18 gauge US standard wire 1 inch mesh
Scaffold falls are
Construction Falls are
10
6