Prestressed Concrete: Fundamentals, History, and Analysis

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/20

flashcard set

Earn XP

Description and Tags

Vocabulary practice flashcards covering prestressed concrete terminology, mechanical principles, historical developments, and elastic stress analysis formulas.

21 Terms

1
New cards

Prestressing

The artificial creation of stresses in a structure prior to loading so that the stresses that exist under load are more favourable, aiming to keep concrete in compression throughout its service life.

2
New cards

Pre-tensioning

A prestressing method in which steel tendons are tensioned before concrete is poured and released from anchorages after the concrete hardens, transferring force by bond stresses.

3
New cards

Post-tensioning

A prestressing method in which concrete is poured and allowed to harden before tendons (sheathed or unbonded) are tensioned and anchored against the hardened concrete member.

4
New cards

Unbonded Tendons

Prestressing strands or wires coated with grease or bituminous material and encased in plastic, preventing bond stresses from developing between the tendon and the concrete.

5
New cards

Bonded Tendons

Tendons housed in metallic or plastic sleeves or formed ducts that are tensioned after concrete hardens and filled with pressurized grout, enabling stress transfer to the concrete via bond stresses.

6
New cards

Transfer

The critical design stage immediately after the prestress force has been fully applied to the concrete and before any long-term stress losses have occurred.

7
New cards

Flexural Bond Stresses

Bond stresses that develop along bonded tendons when a member is subjected to external loading, typically remaining negligible until flexural cracks occur.

8
New cards

Kern Area

The region within a cross-section bounded by eccentricity limits e1=IAy1e_1 = \frac{I}{A y_1} below the neutral axis and e2=IAy2e_2 = \frac{I}{A y_2} above the neutral axis, within which a tendon develops no tension in the section.

<p>The region within a cross-section bounded by eccentricity limits $$e_1 = \frac{I}{A y_1}$$ below the neutral axis and $$e_2 = \frac{I}{A y_2}$$ above the neutral axis, within which a tendon develops no tension in the section.</p>
9
New cards

Passive Prestressing Force (Arch Action)

The compressive reactions at the abutments of an arch that evolve directly from and increase in proportion to the magnitude of the applied load.

<p>The compressive reactions at the abutments of an arch that evolve directly from and increase in proportion to the magnitude of the applied load.</p>
10
New cards

Line of Thrust

The internal path representing the trajectory of the resultant compressive force in a structural member under combined axial force PP and transverse load WW.

11
New cards

Eugene Freyssinet

French engineer recognized as 'the father of prestressed concrete,' who understood concrete creep and developed practical prestressed concrete applications beginning in 19081908.

12
New cards

Creep

The time-dependent strain of concrete under sustained stress, investigated by Sir William Glanville, whose understanding was critical to overcoming long-term prestress losses.

13
New cards

Veurdre Bridge Trial Arch (1908)

Freyssinet's first prestressing project in Moulins, France, featuring a 50 m50\,\text{m} span and 2 m2\,\text{m} rise that utilized a prestressed tie between pile-supported abutments.

14
New cards

Live-End Anchorage

An anchorage positioned at the end of a post-tensioned member through which the tendon projects and where a hydraulic jack is attached to tension the tendon.

15
New cards

Dead-End Anchorage

A fixed anchorage embedded within the concrete member opposite the jacking end that secures the tendon during post-tensioning.

16
New cards

Minimum Cover for Circular Ducts (cmin,bc_{\text{min},b})

The diameter of the circular post-tensioned duct, not to exceed a maximum of 80 mm80\,\text{mm}.

17
New cards

Minimum Cover for Pre-Tensioned Tendons (cmin,bc_{\text{min},b})

A cover depth defined as kϕk\phi, where k=1.5k = 1.5 for plain wire or strand, and k=2.5k = 2.5 for indented wire.

18
New cards

Sign Convention (Prestressed Analysis)

Compressive stresses are defined as positive (++), tensile stresses as negative (−-), and tendon eccentricities below the centroidal axis as positive (++).

19
New cards

Hogging Moment (Eccentric Prestress)

An internal upward bending moment induced by positioning the prestress force PP at an eccentricity ee below the neutral axis, directly counteracting external gravity moments.

20
New cards

Critical Prestress Condition for No Tension (Axial)

The condition where the bottom fibre stress equals zero under maximum bending moment (MmaxM_{\text{max}}), requiring a minimum concentric force of P=MmaxAzbP = \frac{M_{\text{max}} A}{z_b}.

21
New cards

Moment Capacity Increase from Eccentricity

An increase in a beam's maximum bending moment capacity by the value P×eP \times e, achieved by placing the prestressing tendon at eccentricity ee rather than concentrically.