The planned budget of the project is PLN 10^6 (1,000,000 PLN). In the first month, tasks A (50k PLN), B (100k PLN), and C (50k PLN) are planned. At the end of month 1, only tasks A and B were completed and 250k PLN was spent. What is the EV (Earned Value) at the end of month 1?