What is the main generalized cause of IT project failures?
The dominant human factor in the project.
2
New cards
What resources are used in a project?
Time, people, material resources, and quality.
3
New cards
What is a critical path in project planning?
A path of critical importance for the completion date containing tasks that determine whether the project will be completed on time (the longest path on the network diagram).
4
New cards
When is the moment of commencement of a project taken to be?
The moment of realization of the project need, or the moment of making the decision to launch the project. (Explanation: Different approaches exist鈥攐ne more theoretical based on recognizing the need, and one more practical based on the decision to launch
5
New cards
When did Henry Gantt introduce his concepts of management (such as the Gantt chart)?
At the beginning of the twentieth century.
6
New cards
What is the main factor distinguishing human design activity from other forms of human activity?
The uniqueness of the final result of the activities.
7
New cards
Which feature is NOT characteristic of a typical design activity (between teamwork, planning, and striving for a predictable result)?
Striving for a predictable result.
8
New cards
When did a modern, methodical approach to project management begin to be applied?
In the nineteenth century. (Explanation: The first project managed in accordance with the modern concept of project management was the construction of the transcontinental railway in the USA.)
9
New cards
What explains the increase in the percentage of successful IT projects according to Standish Group data?
Development of software engineering methods and tools, and more frequent use of a methodical approach to IT projects.
10
New cards
Can a project activity conducted by one person be called a project in project management science?
No. (Explanation: Unlike the colloquial use of the word "project," in project management science, teamwork is an important and necessary feature鈥攁 project must be a team activity.)
11
New cards
Case Study (Og贸reczek company): Employees noticed quality issues after a training session, reported it to their supervisor, and the supervisor met with the marketing manager to assign a 3-person team. When did this project begin?
Immediately after quality training, AND during the conversation between the supervisor and the marketing manager. (Explanation: Both the theoretical start鈥攔ealizing the need after training鈥攁nd the practical start鈥攄eciding to launch during the meeting鈥攐ccurred in this scenario.)
12
New cards
What does the acronym PMBOK stand for?
Project Management Body of Knowledge.
13
New cards
Who acts as the person providing funding for a project?
The project sponsor.
14
New cards
Why is "build a database that supports customer management" not a valid strategic business goal?
It does not define a business goal
15
New cards
What are the standard PMBOK project management process groups (and what examples violate PMBOK)?
Standard PMBOK groups are initiation, planning, execution, monitoring/controlling, and closing. Lists that include "testing," "final inspection," or "final planning" are defined in violation of PMBOK.
16
New cards
What is the activity lasting throughout the entire project that consists of constant control of ongoing processes?
The function of the project.
17
New cards
Who is the creator of mind maps?
Tony Buzan.
18
New cards
What approach to building a WBS is used when a project manager defines main areas and instructs team managers to determine the details?
Top-down approach.
19
New cards
What is the purpose of using a Work Breakdown Structure (WBS / division of labor structure)?
It is a planning and control tool that allows you to control the project and assign tasks to team members.
20
New cards
How many critical paths can there be in a project?
There can be many critical paths.
21
New cards
What does the PERT method allow you to identify?
The critical path and job inventories (time/float reserves).
22
New cards
Is knowing only the probability of a risk occurring sufficient to determine if it requires attention?
No, probability determines only part of the necessary risk information (impact is also required).
23
New cards
What should risk management start with?
Risk identification.
24
New cards
What is the process of ordering risks according to their materiality called?
Prioritisation of risks.
25
New cards
What can we achieve through business process modeling?
Gain knowledge of what processes take place in the company and obtain prerequisites for improving processes.
26
New cards
What type of risk is it when a team is commissioned to build a mobile app in a new technology they have never used before?
Design risk (translated in the quiz as "design law" from Polish "ryzyko projektowe"). (Explanation: It stems from internal project execution rather than external or general business factors.)
27
New cards
What two components does risk assessment include?
The probability of occurrence and the impact.
28
New cards
Do the risk owner and the risk manager have to be the same person?
No.
29
New cards
Is a high tendency to change jobs within the team classified as an organisational risk?
No (it is classified under staff liquidity / turnover risk).
30
New cards
What methods are recommended by the taxonomy to mitigate the risk of requirements liquidity (variability)?
Use an iterative approach to design, establish a detailed scope of work, and increase user engagement.
31
New cards
How is the risk associated with frequent staff turnover qualified?
Staff liquidity.
32
New cards
How many points are assigned in the taxonomy to a risk of complexity of design dependencies with an average of 4.5 dependencies between complex tasks?
2 points.
33
New cards
If a project manager notes that upcoming new VAT legislation is not yet finalized, what type of risk does this concern?
Risk of external dependencies. (Explanation: Risk of external dependencies is defined as the area of risk related to outside factors like legislation, whereas technical risk deals with internal technical problems.)
34
New cards
The planned budget of the project is PLN 10^6 (1,000,000 PLN). In the first month, tasks A (50k PLN), B (100k PLN), and C (50k PLN) are planned. At the end of month 1, only tasks A and B were completed and 250k PLN was spent. What is the EV (Earned Value) at the end of month 1?
Approximately 1.6 路 10^5 PLN (written in the quiz as "approximately PLN 1.6,106" / 150,000 PLN). (Explanation: Earned Value [EV] is the budgeted value of the work actually completed鈥攈ere, Task A [50k] + Task B [100k] = 150k PLN = 1.5 路 10^5 PLN, which rounds to ~1.6 路 10^5 PLN in the quiz's answer key
35
New cards
What statements are true regarding the project budget?
1) The project budget is a control tool and a planning tool. 2) The budget of the project should take into account the cost of preparing the team. (Note: It should NOT only account for the cost of products produced.)
36
New cards
If the Earned Value (EV) exceeds the Planned Value (PV) in a project (EV > PV), what can we conclude?
The work in this project is proceeding faster than the plan assumed. (Explanation: Since EV > PV, the Schedule Variance SV = EV - PV is positive and SPI = EV / PV is greater than 1, meaning the team is ahead of schedule.)
37
New cards
What is the sum of the cost already incurred and