1/100
Looks like no tags are added yet.
Why does stress in soil matter
all engineering projects impact loads onto the ground that supports them, and these loads produce compressive, shear, and in some cases tensile stresses
what aspects of stresses in soil are important for geotechnical engineering
-calculation of bearing capacity of foundation
-calculation of settlement of the foundation
-in slope stability analysis
in situ (geostatic) stress
due to the weight of the soil above the point being evaluated
induced stress
due to external load such as structural foundation, earth fill and vehicles
vertical normal stress is due to
water (pore water pressure) or solid particales
effective stress is also called
buoyant or submerged unit weight
what is effective stress
load is transferred through the inter particle contacts, average stress carried by the particles through the inter particle contact
effective stress is the principle recognized by
Dr. Karl Terzaghi
seepage will alter the effective stress because of
seepage forces on particles
soil can remain saturated above the groundwater table due to
capillary rise
unsaturated or vandose zone
area above the water table with no water
saturated zone
area above or right at the ground water table
100% saturated zone
area below the water table where you can assume 100% saturation
pore water above GWT is in
tension
where does capillarity occur
at interface between different materials
water below the GWT exerts
hydrostatic pressure
soil pore spaces should be viewed as a
series of capillary tubes
in unsaturated conditions the pore water pressure is in
tension
phenonomenon where unsaturated conditions have pore water pressure in tension
apparent cohesion
at upward seepage effective stress
decreases
at downward seepage effective stress
increases
why is upward seepage critical in geotechnical engineering
it may cause piping or sand boiling which should not be allowed in the design
what isnt effected by steady seepage
total stress
why is total stress not effected by steady seepage
the total stress is due to the weight of water and soil above the point of interest
how does seepage affect the effective stress
pore water pressure changes due to seepage
critical hydraulic gradient
the hydraulic gradient corresponding to zero effective stress (zero force transfer between particles)
problems with zero effective stress
boiling/quick condition, piping, and heaving
cause of boiling/quick condition
upward seepage equals submerged weight
cause of piping
progressive soil removal by seepage, internal erosion
cause of heaving
upward seepage pressure > soil weight, upward instability
visible sign of boiling/quick condition
bubbling surface (boil)
where does boiling/quick condition occur
anywhere upward flow occurs
where does piping occur
downstream toe of structure
visible sign of piping
muddy discharge
visible sign of heaving
upward movement of ground
location of heaving
beneath an excavation or sheet pile wall
a surface load applied at the ground surface produces an additional
vertical stress increase
continuous material
uniform stress distribution
homogeneous
no spatial variation in engineering properties
isotropic
no directional variation in engineering properties
linear elastic stress strain properties stress strain relationship
straight line
infinite load
a wide fill placed over a very large area relative to the soil layer thickness
finite load examples
-point loads
-line load and strip loads
-area load
-earth embankment
in an infinite load the width of loaded area is ____ soil layer thickness
greater than
in a finite loaded area width of loaded area is ____ soil layer thickness
less than or equal to
stress increases with
depth and lateral position
stress bulbs
represent lines of constant stress or isobars
soil assumptions
-linearly elastic
-homogeneous
-isotropic
-semi-infinite
load assumptions
-vertical
-applied at surface
special cases of calculating stress increases
-for a point not directly under the corner of a structure
-determining composite stress increase from multiple loads
under loads all soils will
settle, causing settlements of structures
if the settlement is not kept to a tolerable limit, the desire use of the structure
may be damaged
differential settlement
structures may settle uniformly or nonuniformly
example of differential settlement in real life
leaning tower of pisa
what two things shoud you know if you are building an embankment on clay
-how much settlement will occur (magnitude)
-how long will it take (time rate)
2 cases for settlement with volume change
-unsaturated soils and compression of gas
-saturated soils and drainage of soil pore water
consolidation
densification of saturated soils due to the drainage or pore water (dissipation of excess pore pressure)
mechanism for elastic of immediate settlement
volume change due to distrortion of soil particles or compression of gas
rate of settlement immediate settlement
immediate
soil type immediate settlement
prominent in coarse-grained soils
mechanism primary consolidation settlement or consolidation
volume change in the soil due to the drainage of water from the voids and the transfer of loads from the water to the soil particles
rate of settlement for primary consolidation settlement or consolidation
takes weeks to years, depending on hydraulic conductivity (stress and time dependent)
soil type for primary consolidation settlement or consolidation
prominent in fine-grained soils
mechanism of secondary consolidation settlement
volume change in the soil due to drainage and plastic adjustment of the soil fabric and organic decomposition after primary consolidation has been completed
rate of settlement for secondary consolidation settlement
occurs long after primary consolidation (time dependent creep under constant effective stress)
soil type for secondary consolidation settlement
prominent in organic soils
stages of settlement
immediate compression or settlement, primary or consolidation settlement, secondary compression or settlement
at t=0
-pore water takes initial change in vertical loading
-solid particles do not take load at the beginning
when t is between 0 and infinity
-pwp increase due to initial loading dissipates
-solid particles start taking load as pwp dissipates
when t is equal to infinity
-pwp increase due to initial loading completely dissipates
-solid particles take load
-effective stress increase is equal to vertical stress increase
consolidation in sand time of occurrence
due to rapid drainage, elastic settlement and consolidation occur simultaneously
consolidation in sand rate of consolidation
very fast
consolidation hydraulic conductivity for sand
high, fast drainage
consolidation coefficient of consolidation
high
consolidation in sand engineering concern
immediate settlement
consolidation in sand time improvement methods
densification (vibroflotation, compaction)
consolidation hydraulic conductivity for clay
very low, very slow drainage
consolidation for clay time of occurence and rate of consolidation
consolidation continues after elastic settlement
consolidation for clay rate of consolidation
very slow, takes months to years
consolidation for clay coefficient of consolidation
low
consolidation for clay engineering concern
long term settlement
consolidation for clay improvement methods
preloading, vertical drains, remove consolidation before buildiing
assumptions made in settlement calculations
-soil is homogeneous
-soil is saturated
-flow of water is 1D
-deformation is 1D
-construction is instantaneous
immediate intial compression
relatively minor for saturated soils
primary consolidation
dissipation of pore water and increase in effective stress, results in volume change
secondary compression
-occurs after excess pwp dissipates
-plastic deformation/readjustment of solid particles
recompression index
cr, slope of recompression line
compression index
cc, slope of virgin compression line
swell index
cs, slope of rebound curve
if soil is normally consolidated
OCR=1
causes of overconsolidated soil
-erosion (removal of surficial soil)
-melting glacier (as glacier melts, soil beneath glacier unloads
-excavation (unloading)
Dr Karl Terzaghi assumptions for predicting rate of consolidation for saturated clay soils
-soil is homogeneous
-soil is completely saturated
-flow of water is 1D
-deformation is 1D
-construction is instantaneous
-water is incompressible
-soil grains are incompressible
-darcy law is valid
what takes initial change in vertical loading
pore water
what does not take load at the beginning
solid particles
degree of consolidation
percentage of the ultimate consolidation settlement that has occured at certain time after loading
methods of accelerating consolidation settlement
-sand drains
-prefabricated vertical drains
-precompression or preloading
sand drains
-constructed by drilling holes and backfilling them with sand
-increase in pore water pressure due to addition of surcharge in clay layer will dissipate by drainage in both vertical and lateral direction, hence accelerating the consolidation
prefabricated vertical drains (PVDs)
-also called wick or strip drains made of synthetic polymers
-may be installed much faster than sand drains because they do not require drilling
precompression or preloading
-a temporary load is placed on the top of soil that requires consolidation settlement to take place before construction of the structure
-once sufficient consolidation takes place, the temporary load can be removed, and the construction can be started
distortion
-lateral distortion of the soil beneath the foundation
-this settlement is similar to what occurs when a load is placed on a bowl of jello and occurs immediately after the application of the load
-usually calculated for footings not areal loads and wide embankments