Time value of money
A dollar today is worth more than a dollar later because it can be invested; only compare cash flows after moving them to the same point in time
Future value (compounding)
Moves money forward in time: FV = PV × (1 + r)^t
Present value (discounting)
Moves money backward in time: PV = FV / (1 + r)^t
Discount rate and risk
Higher risk → higher required return → higher discount rate → lower present value
Discounted cash flow (DCF)
(1) Forecast future cash flows, (2) discount each CF_t to today and add them up: PV = Σ CF_t / (1 + r)^t
Net cash flow
Cash inflows (revenue, other receipts) minus cash outflows (investment/capex, O&M costs, taxes) in a given period
Net present value (NPV)
PV of future cash flows minus the upfront cost: NPV = CF0 + Σ CF_t / (1 + r)^t, where CF0 is usually negative (the investment); the value created today
NPV decision rule
NPV > 0 → accept (creates value); NPV = 0 → breakeven, investors earn exactly their required return; NPV < 0 → reject
NPV = 0 subtlety
You can receive more total dollars than you paid and still only break even, because the money comes back later than you paid it out
Internal rate of return (IRR)
The discount rate that makes NPV = 0; a % rate (NPV is a $ amount). Accept if IRR > required return (hurdle rate)
Discounting at a 100% rate
Divide by 2, 4, 8 … for years 1, 2, 3. Example: $100 per year for 3 years = 50 + 25 + 12.5 = $87.50 today
Wind project example ($250M cost; CFs 80, 100, 120; 5%)
PVs ≈ 76.2 + 90.7 + 103.7 = 270.6 → NPV ≈ $20.6M > 0; IRR ≈ 9.05% > 5% → accept
Bond valuation
PV of coupons + face value. 2-year, $1,000 face, 5% coupon, 8% required return: 50/1.08 + 1,050/1.08² ≈ $946 (below face because the coupon rate is below the required return)
Stock valuation (one period)
(Dividend + expected price) / (1 + r). $3 dividend + $110 price next year at 10%: 113 / 1.10 ≈ $102.73
Excel NPV pitfall
=NPV(rate, CF1:CFn) starts at t = 1, so add CF0 separately: =NPV(rate, CF1:CFn) + CF0. IRR uses all cash flows: =IRR(CF0:CFn)
Why energy projects fit DCF
Large upfront investment, cash flows over a long but finite life → DCF, NPV and IRR evaluate them; the same timing logic underlies the LC