The phase with the largest fee share (35-40%) is ____.
Construction Documents
Schematic Design typically bills about ____% of the fee.
15-20
Design Development typically lasts ____ months.
2-4
Construction Documents typically last ____ months.
3-8
Bidding and Negotiation bills about ____% of the fee.
5
The longest phase, lasting 1-3 years, is ____.
Construction Administration
Which phase's primary objective is a clearly defined, feasible concept the client accepts?
Schematic Design
Which phase leaves no major issue unresolved that could force restudy in CDs?
Design Development
The B101 lists ____ project phases.
Five
The last step of every design phase is formal client ____.
Approval (in writing)
True or False: Design stops at the end of Design Development.
False
An SD estimate by cost per square foot has what accuracy?
15-20%
Which estimate is most accurate?
Unit price
Which estimate is typical in Design Development?
Assemblies/systems
Cost per bed or per seat is which estimate?
Order of magnitude
Unit price estimates follow the ____ format.
MasterFormat
Assemblies/systems estimates follow the ____ format.
UniFormat
Detailed cost estimating is an ____ service under B101.
Additional
The architect does not ____ that bids will match the estimate.
Warrant
If the lowest bid exceeds the budget, name the owner's B101 options.
Increase budget, rebid or renegotiate, revise scope, terminate, or other alternative
When the owner cuts scope to meet budget, the architect revises CDs ____ additional compensation.
Without
Which phase takes the most time and resources?
Construction Documents
The written part of the contract package is the project ____.
Manual
Divisions 1-49 of the specifications are part of the ____.
Project manual
Instructions to bidders are a ____ requirement.
Bidding
General and supplementary ____ set out contract rights and duties.
Conditions
Which set is NOT part of the contract documents?
Bidding requirements
Issued during bidding, ____ clarify the bidding documents.
Addenda
Issued after signing, change orders are contract ____.
Modifications
Contract form and conditions are separated to hide the ____ ____.
Contract sum
Who controls means and methods of construction?
Contractor
Quantities and relationships are best shown in the ____.
Drawings
Qualities and workmanship are best placed in the ____.
Specifications
CSI's master list of spec divisions is ____.
MasterFormat
The three parts of a spec section are General, ____, and Execution.
Products
MasterFormat Division 00 is ____.
Procurement and Contracting Requirements
MasterFormat Division 01 is ____.
General Requirements
Which division covers Openings?
Division 08
Which division covers Thermal and Moisture Protection?
Division 07
Which division covers Finishes?
Division 09
Which division covers Concrete?
Division 03
Which division covers Masonry?
Division 04
Four specifying methods: descriptive, performance, reference standard, and ____.
Proprietary
Which spec names exact products by manufacturer and model?
Proprietary
Which spec states the end result and testing criteria, naming no products?
Performance
Which spec describes material characteristics without brand names?
Descriptive
Which spec cites ASTM, ANSI or UL standards?
Reference standard
'UL Class A roof, flame spread 25 or less, R-14' is which spec type?
Performance
'48-mil PVC membrane over 2 in. insulation' is which spec type?
Descriptive
Public projects list several brands to allow full and open ____.
Competition
Which AIA document is Instructions to Bidders?
A701
Which bond guarantees the contractor completes the work?
Performance bond
Which bond guarantees subs and suppliers get paid?
Payment bond
A payment bond is also called a labor and ____ bond.
Material
A ____ bond guarantees the winning bidder will sign and furnish bonds.
Bid
True or False: The architect may answer one bidder's question verbally.
False
Responses to bidders are issued in writing as ____.
Addenda
The ____ conference gives bidders a clear view of scope.
Pre-bid
Who makes the final prequalification decision?
Owner
Without prequalification, the award goes to the lowest ____ and responsive bidder.
Responsible
A letter of ____ lets work start before the formal agreement.
Intent
In design-bid-build, the contractor is hired during which phase?
Bidding and Negotiation
Which bidding type uses one prime contractor and multiple subs?
Cost plus a fee
Who alone can alter construction documents after an RFI?
Architect
A graphic RFI response that changes the documents is a job ____.
Drawing
Which form asks a contractor to price a possible change?
Proposal request (G709)
Which form directs work before price or time is agreed?
Change directive (G714)
Which document legally changes contract sum or time?
Change order
Change orders typically total ____% of construction value.
1-5
Largest change order source?
Field conditions (50%)
Owner directives make up ____% of change orders.
35
Accepted nonconforming work requires a ____ to the contract sum.
Credit
Who approves a product substitution?
Owner
Submittals are reviewed only for ____ with the contract documents.
Conformance
Action or informational: which submittals need architect approval?
Action
The contractor can't start submittal-related work until it is ____.
Approved
Application and Certificate for Payment is ____.
G702
The Continuation Sheet is ____.
G703
The Certificate of Substantial Completion is ____.
G704
The Contractor's Affidavit of Payment is ____.
G706
The Affidavit of Release of Liens is ____.
G706A
The Consent of Surety to Final Payment is ____.
G707
The Field Observation Report is ____.
G711
G709 is a proposal ____.
Request
G714 is a construction change ____.
Directive
Withheld payment percentage until completion is ____.
Retainage
A schedule of ____ breaks the contract sum into work portions.
Values
The owner normally has ____ days to pay an application.
30
The architect certifies payment for ____ work.
Completed
The architect makes how many formal 'inspections'?
Two
The two inspections are for substantial and ____ completion.
Final
Substantial completion means occupancy, not ____ complete.
Fully
Substantial completion starts the ____ periods.
Warranty
Who sets the substantial completion date?
Architect
The list of items left to finish is the ____ list.
Punch
Which reconciles allowances and alternates at the end?
Final change order
A ____ is a legal claim on property until a debt is paid.
Lien
Contractor correction period after completion is ____ year(s).
One
The architect checks record drawings for ____, not accuracy.
Compliance
Architect's construction phase duties end with the final ____.
Certificate for Payment