SCM 1000 Intro to Project Management Midterm

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/69

flashcard set

Earn XP

Description and Tags

Project Managment

70 Terms

1
New cards

What are the 4 Agile Values? (Prioritized side vs. less prioritized side)

1. Individuals & interactions > processes & tools

2. Working software > comprehensive documentation

3. Customer collaboration > contract negotiation

4. Responding to change > following a plan

2
New cards

Scrum Role: Product Owner (PO)

Represents the customer/business. Owns and prioritizes the Product Backlog (decides what gets built and in what order).

3
New cards

Scrum Role: Scrum Master

Coach/facilitator who removes roadblocks (impediments) and protects the team from distractions. Not a boss/manager.

4
New cards

Scrum Role: Development Team

Self-organizing group (3–9 people) that decides how to build the work during a Sprint.

5
New cards

Key Scrum Events: Sprint vs. Daily Stand-up

Sprint: Fixed 1–4 week time-box to build a usable product increment.

Daily Stand-up: 15-min daily check-in (What did I do yesterday? What will I do today? Any blockers?).

6
New cards

Project Manager vs. Functional Manager

Project Manager: More Responsibility Less authority on project

Functional Manager: More authority Less Responsibility on project

7
New cards

Project Sponsor

The person or group who provides resources and financial support for the project and is accountable for enabling success.

8
New cards

Core Team vs. Subject Matter Experts (SMEs)

Core Team: Stay on the project from start to finish.

SMEs: Specialists brought in temporarily for specific technical tasks.

9
New cards

Project vs. Program vs. Portfolio

Project: A temporary endeavor that creates a unique product, service, or result.

Program: A group of related projects managed in a way to obtain mutual benefits that cannot be obtained individually.

Portfolio: A collection of projects and programs grouped together to meet high-level strategic business goals.

10
New cards

Triple Constraint (Iron Triangle) + Modern Additions

Scope, Time, Cost (changing one forces at least one other to change).

PMBOK Additions: Quality, Resources, Risk.

11
New cards

What defines Project Success (beyond the Iron Triangle)?

Finishing on time, on budget, meeting scope/quality, & Customer Satisfaction (if the customer hates it, it's still a failure).

12
New cards

Who provides resources, promotes/protects the project at higher levels of management, and stays active from chartering to closure?

Project Sponsor (Executive champion who funds and protects the project; PM manages day-to-day execution).

13
New cards

Scope, schedule, budget, risk, quality, and resources are collectively known as project __________.

Project Constraints (The expanded Triple Constraint / Iron Triangle).

14
New cards

Project vs. Operation difference?

Project: A temporary endeavor that creates a unique product, service, or result (has a defined beginning and end).

Operations: Ongoing, repetitive work required to keep an organization running effectively day-to-day (no definitive end point).

15
New cards

When is Plan-Driven preferred vs. When is Agile preferred?

Plan-Driven: When the product to be delivered is well understood upfront

Agile: When the scope isn't well defined or the environment is changing rapidly

16
New cards

In Agile & Plan-Driven life cycles, which constraints are fixed and which are iterative?

Agile:

  • Fixed: Time & Cost

  • Flexible: Scope

Plan-driven:

  • Fixed: Scope

  • Flexible: Time & Cost


17
New cards

How do Core Team Members vs. SMEs differ, and what do they have in common?

Differ in: Duration on project, input into planning, and skill set.

Same: Both must work within project constraints.

18
New cards

What are the 3 sides of the PMI Talent Triangle?

1. Ways of Working (Technical PM skills)

2. Power Skills (Leadership)

3. Business Acumen (Understanding company's long-term strategic objectives).

19
New cards

What is the correct top-down order of Strategic Planning?

1. Mission & Vision

2. Strategic Planning

3. SWOT Analysis

4. Portfolio Management (Project Selection).

20
New cards

Vision Statement vs. Mission Statement

Vision: The big-picture, long-term dream of where the company wants to go.

Mission: The shorter statement of how you achieve it day-to-day (purpose/core goals).

21
New cards

What does SWOT stand for, and what is its purpose?

Strengths & Weaknesses (Internal) + Opportunities & Threats (External).

Purpose: To match a company's capabilities with market conditions to select valuable projects.

22
New cards

What document specifically defines why a project is being undertaken from a strategic and financial standpoint?

Business Case (Not source selection criteria, which is used later to evaluate vendors).

23
New cards

When identifying potential projects during strategic planning, what is the recommended target for the number of project ideas to generate relative to your available time and resources?

Identify approximately twice as many potential projects as the organization has time and resources to perform (since not all ideas will fit the company vision or be a good strategic fit).

24
New cards

What document provides a narrative description of products, services, or results to be delivered by a project?

Project Statement of Work (SOW)

25
New cards

Who has the authority to make strategic trade-offs regarding which portfolios, programs, and projects to pursue a Portfolio Manager or a Program Manager?

Portfolio Manager (Program managers manage interdependent projects within an approved program, whereas portfolio managers manage the strategic mix and trade-offs of overall programs/projects).

26
New cards

What are the three core financial analysis tools used to evaluate the cost-value of potential projects?

Payback Period (PP), Internal Rate of Return (IRR), and Net Present Value (NPV).

27
New cards

When evaluating project selection, what three major types of environments must be analyzed for their potential impacts?

Political, market, and social environments.

28
New cards

What term collectively refers to an organization’s focus on social, environmental, and economic health?

Triple Bottom Line.

29
New cards

On an Agile or adaptive project, what is the primary delivery goal to get fast user feedback and validate value?

Produce a Minimum Viable Product (MVP).

30
New cards

What is the primary purpose of Financial Models in project selection, and what is their major blind spot?

Purpose: To determine if a project is profitable and financially viable.

Blind spot: They do not ensure alignment with strategic goals.

31
New cards

What are the four main Financial Models covered, and what are their basic acceptance rules?

  1. NPV (Net Present Value): Accept if > 0 (higher is better).

  2. IRR (Internal Rate of Return): Accept if greater than the cost of capital/hurdle rate (higher is better).

  3. BCR (Benefit-Cost Ratio): Accept if greater than 1.0.

  4. Payback Period (PP): Shorter is better; must meet the required threshold.


32
New cards

What is the core limitation of the Payback Period (PP) model?

It ignores cash flows that occur after the payback period is reached and does not account for the time value of money.

33
New cards

In a Weighted Scoring Model, how do you calculate a project's final score, and which project wins?

Multiply each criterion's rating by the category weight, sum them up, and the project with the highest total score is selected first.

34
New cards

What is Sensitivity Analysis, and why is it used in project scoring models

A technique used to study how changes in uncertainty, weights, or scores impact the overall model results (checking if your winning project flips when conditions change).

35
New cards

When evaluating an external vendor, contractor, or supplier, what are the four main categories of Source Selection Criteria?

  1. Technical (can they deliver the right specs?)

  2. Managerial (do they have good leadership/planning?)

  3. Financial (are they financially stable?)

  4. Operational (do they have the equipment and reliable processes?)


36
New cards

Product Scope

Characteristic features and functions of what is being created

37
New cards

Scope Creep

Uncontrolled Expansion to what was agreed upon

38
New cards

Scope Overview

  • Used to prevent scope creep

  • Considered to be the projects boundaries

  • Quantifying the scope helps with understanding the size of the project


39
New cards

Business Case

Provides justification for undertaking a project, program, or portfolio. Evaluates cost, benefit, and risk of alternative options and provides rationale for preferred solution

40
New cards

Title

A unique and meaningful title is important, and it reflects key characteristics of a project

41
New cards

Background

Used to provide more detail to the scope statement and business case (it is optional)

42
New cards

Milestone Schedule

Summary level project schedule comprised of major milestones or completion of deliverables

43
New cards

Acceptance Criteria

markers against which deliverables can be evaluated for completeness and correctness

44
New cards

Risk

An uncertain event or condition that, if it occurs, has a negative (threat) or positive (opportunity) effect on project objectives.

45
New cards

Assumption

Ideas made during project planning that are treated as factual, although they have not been proven

46
New cards

Constraint

Anything that limits project implementation, such as fixed budgets, strict deadlines, or limited resource availability.

47
New cards

Resource Estimated

A preliminary budget with level of confidence in the estimate, identifies expenses project manager can authorize, and expenses sponsor needs to control.

48
New cards

Stakeholder List

A list of those affected by knowing what they care about and who are the key stakeholders being affected.

49
New cards

Lessons Learned

Knowledge gained from one project that can be implemented in other projects in the future

50
New cards

Charter Decision Matrix: When is NO project charter required?

  • Resources: Little to no monies, supplies, or changes.

  • Multidisciplinary: Only 1 discipline involved or impacted.

  • Complexity: Little to no complexity.

  • Technology: No technology changes.

  • Risk: Minimal impact on the customer.

  • Staff: Small team (2–3 people) to reach a solution.


51
New cards

Charter Decision Matrix: When is a Mini Charter required?

  • Resources: Requires moderate resources.

  • Multidisciplinary: 2 to 3 disciplines or more than one site.

  • Complexity: Moderate complexity; affects care/operations delivery.

  • Technology: IS (Information Systems) consult needed.

  • Risk: Moderate impact on the customer.

  • Staff: Small team needed to generate solutions.


52
New cards

Charter Decision Matrix: When is a Full Project Charter required?

  • Resources: Requires significant and/or additional FTEs (Full-Time Equivalents/money).

  • Multidisciplinary: More than 3 disciplines involved or impacted.

  • Complexity: Very complex.

  • Technology: IS resources assigned (heavy tech integration).

  • Risk: Significant impact on the customer.

  • Staff: Requires a large team across multiple departments.


53
New cards

Which project phase does the Project Charter complete, and which phase does it authorize?

It is the primary deliverable of the Initiating phase, completing Initiating and formally authorizing Planning.

54
New cards

What is the Rough Order of Magnitude (ROM) accuracy for a charter's summary budget?

-25% to +75% accuracy.

55
New cards

What should a PM do if a sponsor requests several changes when reviewing the project charter?

Negotiate with the sponsor to see how to best accommodate their requests without agreeing to unreasonable expectations. (Never blindly agree, flatly refuse, or put it to a team vote.)

56
New cards

Business Case vs. Scope Overview in a Project Charter

Business Case: Explains Why the project is needed (strategic/financial justification).

Scope Overview: Explains What is included and excluded (project boundaries).

57
New cards

What are the exact steps for handling project risks after identifying them?

Assess each risk based on probability and likely impact, and then create a risk response plan (with an assigned owner) for each major risk.

58
New cards

What charter component documents significant points/events and is best combined with acceptance criteria?

Milestone schedule. (Acceptance criteria = how the customer judges whether deliverables were completed satisfactorily.)

59
New cards

Major Risks

Risks with high probability and high impact that sit above the threshold line on a risk assessment matrix and require a formal response plan and an assigned risk owner.

60
New cards

Team Operating Principles

Guidelines established by the team detailing how meetings will be run, decisions will be made, work gets done, and members will treat each other with respect.

61
New cards

Lessons Learned Register

An accumulation of knowledge and insights gained from current and past projects that can be cataloged and referenced for future initiatives.

62
New cards

Charter Signatures and Commitment

The final ratification step where the Project Sponsor, Project Manager, and core team sign the charter to show mutual agreement and time commitment (completes Initiating and starts Planning).

63
New cards

Six-Step Negotiation Process

Advance fact-finding → Determine minimum acceptable results → Identify underlying needs → Explore creative solutions → Negotiate → Document agreement


64
New cards

Three Levels of Project Management Hierarchy

1. Executive Level (CPO, Project Sponsor, Steering Committee)

2. Managerial Level (Project Manager, Functional Manager, Scrum Master)

3. Associate Level (Core Team Members, Subject Matter Experts)

65
New cards

Project Culture vs. Code of Conduct

Project Culture is the shared values, norms, rewards, and risk tolerance of the group

Code of Conduct is a formal set of ethical rules

(PMI's four values: Responsibility, Respect, Fairness, Honesty. “Authority” is excluded).

66
New cards

Predictive (Waterfall) vs. Agile Triple Constraints

Predictive: Scope is fixed while time and cost are estimated.

Agile: Time and cost are fixed (via sprints) while scope is flexible and evolves through the Product Backlog.

67
New cards

Power culture

Getting the job done (supervisor exerts economic/political power, everyone tries to please the boss)

68
New cards

Role culture

Formal authority (follow appointed roles, respect regulations and laws)

69
New cards

Task culture

Worker development (skill-based assignments, self-motivated workers, deference to knowledge)

70
New cards

Personal culture

Designations of responsibility (interest in worker needs, worker development critical to success)