Comprehensive fill-in-the-blank review flashcards covering Chapter 5230, ASME B31.1, ASME Section I power piping requirements, and ASME B31.5 ammonia refrigeration codes.
For power piping systems operating at temperatures over 750∘F, __________ are recommended instead of standard bolts.
Bolt studs
In ASME B31.1 power piping systems, threaded joints are strictly prohibited at temperatures above __________.
925∘F
For steam service over 250psi or water service over 100psi and 220∘F, the pipe shall be seamless, have a minimum ultimate tensile strength of 48,000psi, and have a weight at least equal to __________.
Schedule 80
Brazed socket-type joints for valves and fittings must be made with suitable brazing alloys having melting points above __________.
840∘F
For all piping lines under pressure and above 250∘F, gaskets are recommended to be metallic, asbestos, or other __________.
nonburning material
Pipe type prohibited in high-pressure steam or heating media systems
Furnace butt-welded pipe (Grade F)
Copper pipe, copper tubing, and brass pipe may be used for power piping service provided the operating temperature does not exceed __________.
406∘F
When steam pipes pass through combustible partitions, floors, or walls, metal sleeves must provide an all-around clearance of not less than __________ under hot and cold conditions.
1/4inch
By definition, a slow-opening valve requires at least __________ of the operating mechanism to change from fully closed to fully opened.
five 360∘ turns
Outside screw and yoke (OS&Y) stem design is mandatory for threaded stem valves of size __________ and larger for pressures above 600psi.
NPS 3
Minimum pipe schedule and construction required for bypasses lines
Must be at least Schedule 80 seamless, and may be integral or attached.
Following erection, all power piping systems must be capable of withstanding a hydrostatic test pressure of __________ the design pressure continuously maintained for at least 10min.
1.5times
Piping systems are considered safe for occasional operation if pressure or temperature exceeds nominal design values by 15% for no more than 8hr at any one time and not more than __________.
800hr/year
Piping systems are considered safe for occasional operation if pressure or temperature exceeds nominal design values by 20% for no more than 1hr at any one time and not more than __________.
80 hours/ year
Boiler blowoff piping must be capable of withstanding the maximum allowable working pressure of the boiler by either 225psi or __________, whichever is less.
25%
Required routing and bend specifications for pipe connections between a boiler and a blowoff tank
Must be made as direct as possible using sweep bends having a radius of 3 times the diameter of the pipe.
Component required to connect the outlet piping with the vent pipe on a boiler blowoff tank
A 43 in siphon breaker
Boiler blowoff tank vent sizing ratio relative to the inlet or outlet size
Equal to 2.5 times the size of the inlet or outlet
Before discharging into a sanitary sewer, boiler blowoff must pass through a blowoff tank or apparatus that reduces the pressure to not more than 5pounds and the temperature to not more than __________.
140∘F
Blowoff tanks must be installed with a clearance space of not less than 12inches between the tank and the floor, and not less than __________ between the tank and the wall.
18inches
Boilers having more than __________ of water heating surface shall be provided with at least two means of feeding water.
500square feet
Minimum delivery pressure required for each boiler feedwater source
3% higher than the highest setting of any safety valve on the boiler
Feedwater supply requirement for boilers fired with solid fuel not in suspension
Must be provided with at least two means of feeding water that cannot be subject to the same type of interruption (commonly accomplished by making one source steam-operated).
Boiler feed line valve arrangement and globe valve flow direction
The feed pipe must be equipped with a check valve and at least 1 feedwater valve (stop valve, globe valve, or plug cock) placed between the check valve and the boiler. When a globe valve is used, the water inlet must enter under the disk.
Feedwater piping and valves between the feed pump and the boiler must meet or exceed the MAWP of the boiler by 225psi or __________ the MAWP, whichever is lesser.
1.25times
The temperature in degrees Fahrenheit of saturated steam can be approximated from gauge pressure using the formula: __________ plus 198.
(psig)×14
The suggested steel pipe support spacing in Table 121.5 is based on a fixed beam support with a maximum bending stress not exceeding __________.
2,300psi
Threaded hanger rods used for supporting pipe of nominal size 2inch and smaller must not be less than __________ in diameter.
3/8inch
The steam gage valve must be fitted with a tee or lever handle arranged to be __________ when the valve is open.
parallel to the pipe
Under ASME BPE standards, equipment parts subjected to Steam in Place (SIP) should withstand continuous flow of saturated steam at a minimum temperature of 266∘F for a minimum duration of __________ under steady-state conditions.
100hr
The Permissible Exposure Limit (worker exposure) of ammonia in refrigeration systems is __________.
50parts per million
At atmospheric pressure, the flammable limits of ammonia vapor by volume in air are __________.
15% to 28%
In a restricted ammonia machinery room, no permanently installed flame-producing device or hot surface above __________ is permitted.
800∘F
Components in direct contact with ammonia must not contain copper, brass, zinc, __________, or alloys of these materials.
mercury
If an ammonia refrigeration system has any component designed for operating temperatures below __________, the piping must meet ASME B31.5 impact test requirements.
−20∘F
For carbon steel welded ammonia piping, pipe sizes of 11/2inch and smaller must be __________.
Schedule 80
In public hallways or lobbies of commercial occupancies, ammonia piping systems are restricted to containing not more than __________ of refrigerant.
3.3pounds
Ammonia piping crossing an open passageway in a building must be installed at least __________ above the floor, unless positioned against the ceiling.
7.25feet
The storage tank capacity for anhydrous ammonia must be limited to __________ of water weight capacity at 60∘F.
56%
Refrigerant piping with a surface temperature of 140∘F or higher that is located less than __________ high or near passageways must be insulated or guarded.
7.25ft
In ammonia refrigeration piping systems, all joints larger than 2inch NPS must be __________.
welded
The discharge termination of an ammonia relief valve to atmosphere must be at least 15feet above ground and at least __________ from any window, ventilation intake, or personnel exit.
20feet
An ammonia pressure vessel of __________ or more internal gross volume must be protected by two parallel pressure relief devices connected to a three-way type stop valve.
103feet3
Beyond the system charge itself, the maximum weight of refrigerant stored in an ammonia machinery room receiver must not exceed __________.
330pounds
Ammonia compressors driven by motors exceeding __________ must be equipped with antirecycle timers to prevent short cycling and overheating.
250horsepower
On an ammonia pipe marker conforming to ANSI A13.1 guidelines, the physical state section is printed in sky blue for vapor and in __________ for liquid.
yellow
On an ammonia pipe marker, an operating pressure exceeding __________ is classified as high pressure and printed in black letters on a red band.
70psig
Quarter-turn valves may be utilized in ammonia refrigeration service provided they feature an actuator with a minimum operating stroke duration of __________.
60seconds
Emergency mechanical ventilation systems in an ammonia machinery room must supply at least 30ACH and be actuated automatically by a refrigerant detector set at __________.
150ppm