What is the purpose of a business case?

Justifies the investment by explaining expected benefits and business value.

2
New cards

What is the purpose of a project charter?

Formally authorizes the project and establishes the project manager’s authority.

3
New cards

Who typically authorizes a project charter?

The project sponsor or another authorized initiator.

4
New cards

What is the purpose of a project management plan?

Describes how the project will be executed, monitored, controlled, and closed.

5
New cards

What does requirements documentation describe?

Stakeholder needs and product or project requirements.

6
New cards

What does the project scope statement define?

Deliverables, acceptance criteria, boundaries, exclusions, assumptions, and constraints.

7
New cards

What is a WBS?

A hierarchical decomposition of the total project scope into manageable deliverables and work packages.

8
New cards

What is decomposition?

Breaking major deliverables into smaller components or work packages.

9
New cards

What is the scope baseline composed of?

The approved scope statement, WBS, and WBS dictionary.

10
New cards

What is a WBS dictionary?

Details about WBS components, such as work descriptions, deliverables, and acceptance criteria.

11
New cards

What is a work package?

The lowest level of the WBS used to plan and control project work.

12
New cards

What is the 100% rule for a WBS?

The WBS includes all approved project scope and excludes work outside it.

13
New cards

Which document grants the PM formal authority to use resources?

Project charter.

14
New cards

Which document lists work explicitly excluded from the project?

Project scope statement.

15
New cards

Which document shows how the project will be managed?

Project management plan.

16
New cards

Which document provides the approved reference for scope control?

Scope baseline.

17
New cards

What happens during project initiation?

The project is authorized and key stakeholders are identified.

18
New cards

After charter approval, what is an important next step?

Identify and analyze stakeholders before developing detailed plans.

19
New cards

When is the detailed WBS usually created?

During planning, after requirements are collected and scope is defined.

20
New cards

What is progressive elaboration?

Increasing detail in plans as more information becomes available.

21
New cards

What is rolling wave planning?

Plan near-term work in detail and future work at a higher level.

22
New cards

How does rolling wave planning relate to progressive elaboration?

Rolling wave planning is one technique that uses progressive elaboration.

23
New cards

What is iterative development?

Refining the product through repeated cycles.

24
New cards

What is incremental development?

Delivering functionality in successive usable portions.

25
New cards

What is scope creep?

Uncontrolled expansion of project scope without proper approval.

26
New cards

What is gold plating?

Deliberately adding features or work beyond agreed requirements.

27
New cards

Can gold plating contribute to scope creep?

Yes. Extra unapproved work can expand project scope.

28
New cards

What is integrated change control?

Evaluating, approving or rejecting, and managing changes to project baselines.

29
New cards

What should happen before implementing a change to a predictive scope baseline?

Document and evaluate the change, then obtain approval from the authorized decision maker.

30
New cards

What impacts should be assessed for a change request?

Scope, schedule, cost, quality, resources, risks, and relevant contracts.

31
New cards

Who may approve a formal change request?

A designated authority such as the CCB, sponsor, or PM within delegated limits.

32
New cards

Does sponsor satisfaction automatically approve unauthorized scope additions?

No. Follow the applicable formal change control and acceptance process.

33
New cards

What should the PM do when unauthorized changes are discovered?

Document them, assess impacts, and process them under project change governance.

34
New cards

What happens after a baseline change is approved?

Update relevant baselines and plans, communicate the decision, and implement.

35
New cards

What happens when a change request is rejected?

Record the decision and continue with the approved scope.

36
New cards

What is a change control board (CCB)?

A designated group authorized to review and decide on certain changes.

37
New cards

How are new features typically handled in Agile?

Add them to the product backlog for product owner prioritization.

38
New cards

Does Agile mean any change can be implemented immediately?

No. Respect sprint goals, contracts, budgets, and required approvals.

39
New cards

Who orders the product backlog in Scrum?

The product owner.

40
New cards

What is the product backlog?

An ordered list of work needed to improve the product.

41
New cards

What is the sprint backlog?

The sprint goal, selected product backlog items, and delivery plan.

42
New cards

Which is usually preferred for new scope in predictive projects?

Approved change control, rather than informal additions.

43
New cards

What is scope validation?

Formal acceptance of completed deliverables by the customer or sponsor.

44
New cards

How does validate scope differ from control quality?

Validate scope seeks acceptance; control quality checks correctness and conformance.

45
New cards

What is requirements traceability?

Linking requirements to their sources, deliverables, and verification.

46
New cards

A PM lacks formal project authorization. What should happen?

Work with the sponsor to establish a project charter.

47
New cards

A team keeps adding unapproved HMI features. What is the overall issue?

Scope creep; individual extras may also be gold plating.

48
New cards

Future phases are vague but next month is detailed. Which planning technique?

Rolling wave planning.

49
New cards

A deliverable is broken into modules and tasks. Which technique?

Decomposition.

50
New cards

Stakeholders disagree on approved deliverables. What baseline helps?

The scope baseline, including the scope statement and WBS.