What type of contracts have revenue recognition before delivery
Accounting for long-term construction contracts
Two ways to do Accounting for long-term construction contracts
Percentage-of-completion method
Completed contract method
Are JE during the period diff under both methods?
nah, JE are same under both methods
Are AJE during the period diff under both methods?
yes, end of period adjusting journal entry for recognizing revenues and expenses will differ depending on the method of accounting for the long term contract
1st event to account for long term contracts generally are
Incur costs during the period related to direct materials, direct labor and overhead
1st event JE for LT Contract during period
DR CIP Inv
CR Cash (or payables)
2nd event to account for long term contracts generally are
bill the customer
2nd event JE for LT Contract during period
DR A/R
CR Billings on contract
3rd event to account for long term contracts generally are
collect on billings
3rd event JE for LT Contract during period
DR Cash
CR A/R
What is Construction in Process (CIP) Inv?
asset account, costs of construction are held in inventory
How is CIP inv calcuated differently for % complete method
CIP inventory is carried at cost + realized gross profit
What is billings on contract
contra-asset account
What is billings on contract a contra account to?
CIP Inv
Why is billings on contract a XA account to CIP Inv?
to avoid overstating the contractor’s interest in the project
B/S reporting if CIP > Billings
Reported as Current Asset
B/S reporting if CIP < Billings
Current liability
What type of account is revenue from LT Contracts
Revenue account
Where does Rev from LT contracts close to?
Retained Earnings
What type of account is Construction Expenses (or Costs of Construction)
Expense account
Where does Construction Expenses close to?
Retained earnings
When is percentage of completion method appropriate
Contract specifies the amount of consideration to be exchanged and the terms of settlement.
Buyer is expected to satisfy the obligation.
Contractor can perform according to the terms of the contract.
when to use % complete formula
End of period AJE
% completion formula
Total costs incurred to date / most recent estimate of TOTAL project costs
when to use current period rev recognised
end of period AJE
Current period rev recog’ed formula
(% complete * total revenue from contract) — total rev recog’ed in prior periods
AJE at the end of each period under percentage of completion method for an overall profitable contract is
dr. Construction Expenses XX
dr. CIP Inventory XX
cr. Revenue on Long term Contract* XX
Important note for CR Revenue on Long term Contract for AJE
Where the amount of Revenue recognized is based on the percent complete in the period. On a profitable contract, the amount of construction expense is the amount incurred in the period. The entry to CIP Inventory records the difference between revenues and expenses recognized (can be a debit [increase] or credit [decrease] entry).
JE to record completion of contract [% complete method]
DR Billings on contract
CR CIP inv
Are there are any AJE for completed contract method?
No, no AJE for revenue and expense recognition under the completed contract until the contract is complete (as long as the contract is overall profitable).
AJE in year contract is completed [completed contract method]
DR Construction expenses, CR CIP Inventory
DR Billings on Contract , CR Revenue on Long term contract