Materiel Joint Capabilities (MIDS)
Pre-Pathway (Left of MDD); Identification of capability gap.
Materiel Development Decision (MDD)
Entry point into acquisition process.
Materiel Solution Analysis (MSA)
Focused on assessing alternative materiel solutions to meet the validated gap.
Milestone A
Decision Point. MDA approves the preferred materiel concept & authorizes entry into TMRR.
Technology Maturation & Risk Reduction (TMRR)
Dedicated to reducing technology, manufacturing & integration risks.
Milestone B
Decision Point. Initiation of an acquisition program. Authorization to enter EMD.
Engineering & Manufacturing Development (EMD)
System is designed, built, integrated, tested, & prepared for production.
Milestone C
Decision Point. MDA authorizes entry into low-rate production (LRIP) or limited fielding.
Production & Deployment
Post-MS C to FRPDR. Achieve an operational capability & deliver systems to user units.
Full-Rate Production Decision Review (FRPDR)
Decision Point. Within P&D. MDA review to authorize proceeding past LRIP to full-rate production.
Operations & Support
Post-FRPDR to Disposal. Longest & most expensive phase. Executes the product support strategy & disposal.
Initial Capabilities Document (ICD)
Validated before MDD. Guides MSA. Identifies capability gap. NEVER contains specific systems solution.
Capability Development Document (CDD)
Drafted in TMRR. Validated prior to Milestone B. Defines measurable, testable performance parameters (KPPs/KSAs) for the EMD design
Capability Production Document (CPD)
Drafted in EMD. Validated prior to Milestone C. Finalizes production-specific performance values.
Analysis of Alternatives (AoA)
Conducted during MSA. Analytical comparison of the operational effectiveness, suitability & life-cycle cost of alternative solutions.
Technology Development Strategy (TDS)
Developed for Milestone A review. Outlines the strategy for maturing critical technologies during the TMRR phase.
Acquisition Strategy (AS)
Drafted for Milestone B. Updated at Milestone C & FRPDR. PM’s master business & technical roadmap for managing program execution.
Acquisition Program Baseline (APB)
Established at Milestone B. Updated at Milestone C. Agreement between the PM & MDA. Establishing cost, schedule & performance boundaries.
System Requirement Review (SRR)
Early TMRR. Verifies the system requirements are consistent with the preferred concept & validated CDD.
System Functional Review (SFR)
Mid TMRR. Establishes the Functional Baseline. Ensures funtional specs are ready for preliminary design.
Preliminary Design Review (PDR)
Late TMRR or early EMD. Establishes the Allocated Baseline. Determines if the system is ready to proceed to detailed design. (Must complete prior to Milestone B for major programs.
Critical Design Review (CDR)
Mid EMD. Establishes Product Baseline. Verifies the detailed design is stable & ready to Begin fabrication/coding.
Test Readiness Review (TRR)
Late EMD. Ensures the test subsystem, test software, facilities, & personnel are ready are ready to begin formal testing.
Production Readiness Review (PRR)
End of EMD. Evaluates weather the contractor’s manufacturing design & processes are ready to enter production.
Functional Configuration Audit (FCA)
Late EMD. Verifies that the actual performance of the physical system matches its functional specifications (tested performance vs spec)
Physical Configuration Audit (PCA)
Late EMD/LRIP. Verifies that the physical design matches the “as-built” technical documentation (drawings vs. actual build).
Test & Evaluation Master Plan (TEMP)
Drafted at MS A. Updated at MS B, MDC & FRPDR. Document detailing the programs developmental, operational & live-fire test strategies.
Developmental Test & Evaluation (DT&E)
Dominates EMD. Controlled engineering test to VERIFY that the design meets technical specifications.
Initial Operational Test & Evaluation (IOT&E)
Late EMD/LRIP. Independent testing in realistic operational conditions to evaluate effectiveness & suitability.
Life Cycle Sustainment Plan (LCSP)
Drafted at MS A. Updated at MSB, MSC & FRPDR. PMs program management plan for the integration of supportability into the system design & the fielding of the sustainment package.
Performance-Based Logistics (PBL)
Formulated in EMD. Executed in O&S.A sustainment strategy that lurches performance outcomes (system availability) rather than transactions (space parts).
Planning, Programming, Budgeting & Execution (PPBE)
Annual process where DoD allocates financial resources to acquisition programs.
Acquisition Category (ACAT)
Determined at MDD & monitored throughout. Classifies programs based on RDT&E/Procurement dollar thresholds or special interest, defining the level of oversight.
Milestone Decision Authority (MDA)
Presides over MDD, MS A, MS B, MS C, & FRPDR. Responsible for a program, including authority to approve phase progression.
Integrated Product Team (IPT)
Formed pre-MDD. Active through O&S. Multidisciplinary team collaborating to execute the programs.
Cost Analysis Requirements Description (CARD)
Submitted prior to Milestones B & C & FRPDR. Technical & programmatic “baseline description” of the program used to build Cost Estimates (POE & ICE)
Earned Value Management (EVM)
Executed during EMD & P&D. Management technique that integrates program scope, schedule & cost metrics to measure progress & predicts final costs.
Integrated Baseline Review (IBR)
Conducted within 180 days of contract award. Typically EMD. A joint PM/ Contractor review to establish a mutual understanding of the Performance Measurement Baseline (PMB) risks.
Joint Capabilities Integration & Development System (JCIDS)
Requirements generation process managed by the Joint Oversight Council (JROC); Produces ICD, CDD, CPD.
Key Performance Parameters (KPP)
Mandatory; has Threshold & Objective values.
Modular Open Systems Approach (MOSA)
Open standards & well-defined interfaces. Enables competition for future upgrades, mitigates vendor lock & reduces lifecycle sustainment costs.
TRL 6
System prototype demonstrated in a relevant environment. Requirement for Milestone B. CANNOT enter EMD without it.
TRL 7
Prototype demonstrated in an operational environment. Late EMD/Early P&D. (flight or combat vehicle test)
Cybersecurity
Tested as a system survivability requirement & supply chain risk (SCRM).
Point of Total Assumption (PTA)
On Fixed Plus Incentive (FPI) contracts where the contractor assumes 100% of cost overruns up to the ceiling price.
Cost-Reimbursement (CPFF/CPIF)
High technical risk to the Government (TMRR/EMD). Better for Contractor.
Fixed-Price Incentive Firm (FPI)
Mature design/early production (LRIP). Better for Governement.
Firm-Fixed-Price (FFP)
Stable/Commercial. Better for Government.
Lowest Price Technically Acceptable (LPTA)
Use when requirements are we;;-defined & there is no value in exceeding thresholds.
Best Value Tradeoff
Use when performance above threshold warrants paying a higher price.
Source Selection Authority (SSA)
Makes the final decision. Informed by the SSAC.
Source Selection Advisory Council (SSAC)
Takes SSEB’s findings. Performs high level strategic & comaprtive analysis & prepares award recommendations.
Source Selection Evaluation Board (SSEB)
Evaluates proposals against Section M criteria. (Never compares proposals against each other)
Adaptive Acquisition Framework (AAF)
DoD’s set of six acquisition pathways designed to tailor acquisition strategies to capability characteristics. (MCA, MTA, Urgent, Software, DBS, & Services).
Acquisition Decision Memorandum (ADM)
The official document signed by the MDA recording decisions, exit criteria & directed actions at a Milestone or Decision Point.
Major Defense Acquisition Program (MDAP)
ACAT I program exceeding RDT&E ($525M) or Procurement ($3.06 B) thresholds.
Low-Rate Initial Production (LRIP)
The initial production quantity after Milestone C used to establish an initial production base, supports IOT&E & permit an orderly ramp-up to FRP.
Full-Rate Production (FRP)
Decision point authorizing economic-rate production & widespread deployment following successful IOT&E & manufacturing verification.
Initial Operational Capability (IOC)
When the first operational units are equipped, trained & capable of conducting mission operations.
Full Operational Capability (FOC)
When all programmed units are fully equipped & sustained.
Independent Cost Estimate (ICE)
Independent life-cycle cost estimate prepared by CAPE required prior to Milestones A,B,C & FRP for MDAPs.
Independent Technical Risk Assessment (ITRA)
Independent review of technical maturity & engineering risks required by statute prior to Milestones A, B & C for MDAPs.
Program Protection Plan (PPP)
The cybersecurity, supply chain risk management (SCRM), & anti-tamper plan designed to protect Critical Program Information (CPI) & Critical Functions.
Systems Engineering Plan (SEP)
The blueprint for the technical management, architecture design, technical reviews & risk management of the program across all phases.
Validated Online LifecycleThreat (VOLT)
DIA or Service Intelligence Center threat report that establishes the baseline threat environment for the system.
Live-Fire Test & Evaluation (LFT&E)
Realistic survive ability & lethality testing for covered systems before entering full-fate production.
Technology Readiness Level (TRL)
Metrics used to measure the maturity of Critical Technology Elements (TRL,1–9)
Manufacturing Readiness Level (MRL)
Metrics used to measure the maturity of the manufacturing processes (MRL, 1–10)
Supply Chain Risk Management (SCRM)
Ensures hardware, software, microelectronics & assemblies used in DoD systems are not compromised by adversaries through sabotage.
MRL 6
Identifies manufacturing processes & materials that are critical to the design. Production revenant environment. PDR/Milestone B.
MRL 7
Verifies the detailed is compatible with the planned manufacturing processes. Production representative environment. CDR.
MRL 8
Confirming that manufacturing processes are in control & ready to start LRIP. PRR/Milestone C.
Functional Baseline (FBL)
What the system must do. Top-level performance, operational capabilities & system-level requirements. (The Wishlist)
Allocated Baseline (ABL)
How the system is split up. Distributes (allocates) the top-level requirements down to specific subsystems or components. (The Blueprint)
Product Baseline (PBL)
Exactly how to build it. The complete “as-built” technical data package. (The Spec Sheet & Materials)
Maintenance Baseline (MBL)
How to support & update it once deployed. (Homeowner’s Manual)