Vocabulary flashcards covering unit measurements for works and materials, painting coefficients as per IS: 1200 - Parris, daily labour out-turn rates, measurement degrees of accuracy, and steel reinforcement thumb rules.
Ornamental Cornice and Bore Wells Measurement Unit
Measured in Running meter (R.M).
Glazing Panels Unit of Measurement
Measured in square meters (m2).
Electrical Fittings Unit of Measurement
Measured in numbers (NO’S).
All Electrical Works Unit
Measured in Points (PKS).
Bitumen Unit of Measurement
Measured in Tonne.
Shutters for Doors and Windows Unit
Measured in square meters (m2).
Brick Metric System Dimensions Unit
For brick size 19×9×9cm, it is measured in cm.
Aggregate Metric System Unit
For sizes such as 20mm and 40mm, it is measured in mm.
Earthwork Excavation, Backfilling, and Sand filling Unit
Measured in cubic meters (m3).
Excavation in Holes in Rocks Unit
Measured in numbers (NO’S).
Blasting Explosive Unit
Measured in kilograms (kg’s).
Cable Pulling Excavation Unit
Measured in Running meter (R.M).
PCC, RCC, Precast Unit, and Sunshade [chajja] Unit Measurement
Measured in cubic meters (m3).
Precast RCC Jolly Work Unit
Measured in square meters (m2).
Damp Proofing Course (D.P.C) Unit
Measured in square meters (m2).
Brickwork Wall Thickness Measurement Standards
Half brick wall corresponds to 10cm (0.1m), one brick wall to 20cm (0.2m), and one and a half brick wall to 30cm (0.3m).
All Brickwork and Stone Masonry Unit
Measured in cubic meters (m3).
Cornice Brickwork and Stonework Unit
Measured in Running metre (R.M).
Wood Work in Frame Unit
Measured in cubic meters (m3).
Wood Work in Shutter Unit
Measured in square meters (m2).
Reinforcement Steel Unit of Measurement
Measured in Tonne, Quintal, or kg’s.
Bar Bending Wire Fencing Unit
Measured in Running meter.
Hold Fast Quantity Standards
Measured in NO’S or kg’s, with 6 NO’S (3 pairs) for doors and 4 NO’S (2 pairs) for windows.
Painting Area Formula
Calculated as Painting area=Opening area×Painting Coefficient as per IS: 1200 - Parris.
Fully Pannelled Doors and Windows Painting Coefficient
Equal to 2.25 (or) 2.60.
Fully Glazed Doors and Windows Painting Coefficient
Equal to 1.00 (or) 1.60.
Partially Pannelled and Partly Glazed Doors Painting Coefficient
Equal to 2.00.
Flush Doors and Windows Painting Coefficient
Equal to 2.040.
Collapsible Gate Painting Coefficient
Equal to 3.00.
Steel Rolling Shutters Painting Coefficient
Equal to 2.20 (or) 2.50.
Plain Steel Sheet Doors and Windows Painting Coefficient
Equal to 2.20.
Iron Grilled Doors and Windows Painting Coefficient
Equal to 1.00.
Corrugated Iron Sheet Painting Coefficient
Equal to 1.14 (14% extra).
Corrugated Asbestos Cement Sheet Painting Coefficient
Equal to 1.20 (20% extra).
Semi-Corrugated Iron Sheet Painting Coefficient
Equal to 1.10 (10% extra).
Corrugated Sheet Dimensions Standard
Consists of 7 to 10 corrugations with a width of 1.05m.
Task Work Sand Filling
4m3 within an 8-hour day.
Task Work Excavation in Ordinary Soil
3m3 within an 8-hour day.
Task Work Excavation in Hard Soil
2m3 within an 8-hour day.
Task Work Excavation in Rocks
1m3 within an 8-hour day.
Task Work Disposal of Surplus Earth
2.83 (or) 3m3 within an 8-hour day.
Task Work Reinforced Cement Concrete
3m3 within an 8-hour day.
Task Work Brickwork in Footing (C.M and L.M)
1.25m3 within an 8-hour day.
Task Work Brickwork in Footing (Mud Mortar)
1.50m3 within an 8-hour day.
Task Work 2.5 cm Thick C.C Floor
7.5m2 (Sq.m) within an 8-hour day.
Task Work Brickwork Using L.M and C.M
1m3 within an 8-hour day.
Task Work Brickwork Using Mud/Clay Mortar
1.25m3 within an 8-hour day.
Task Work Brickwork in Arches Using C.M, L.M
0.55m3 within an 8-hour day.
Task Work Half Brick Wall Partition
5m2 (Sq.m) within an 8-hour day.
Standard Lead and Standard Lift
Standard Lead is 30m and Standard Lift is 1.5m.
Task Work Random Rubble Masonry (C.M, L.M)
1m3 within an 8-hour day.
Task Work Coarse Rubble Masonry (C.M, L.M)
0.8m3 within an 8-hour day.
Task Work Stone Masonry in Arches
0.44m3 within an 8-hour day.
Task Work Ashlar Rubble Masonry
0.4m3 within an 8-hour day.
Task Work Lime Concrete in Foundation and Floor
8.5m3 within an 8-hour day.
Task Work Lime Concrete in Roof
6m3 within an 8-hour day.
Task Work Plain Cement Concrete
5m3 within an 8-hour day.
Task Work Plastering Work
8m2 within an 8-hour day.
Task Work Painting Work
10m2 within an 8-hour day.
Task Work Painting and Varnishing Doors and Windows
25m2 within an 8-hour day.
Task Work Distempering (1 Coat)
35m2 within an 8-hour day.
Task Work White Washing (3 Coats)
70m2 within an 8-hour day.
Task Work White Washing (1 Coat)
200m2 within an 8-hour day.
Dimension Accuracy for Length, Breadth, or Depth
Measured to the nearest 0.01m.
Dimension Accuracy for Area of Work
Measured to the nearest 0.01m2.
Dimension Accuracy for Volume of Work
Measured to the nearest 0.01m3.
Wood Work Area Measurement Accuracy
Measured to the nearest 0.002m2.
Wood Work Volume Measurement Accuracy
Measured to the nearest 0.001m3.
Slab Thickness Measurement Accuracy
Measured to the nearest 0.005m.
Steel Work Dimension Measurement Accuracy
Measured to the nearest 0.001m.
Steel Work Weight Measurement Accuracy
Measured to the nearest 1kg.
Steel Reinforcement Thumb Rule for Lintel / Slab
Required steel ratio is 0.721%.
Steel Reinforcement Thumb Rule for Beam
Required steel ratio is 1%−2%.
Steel Reinforcement Thumb Rule for Column
Required steel ratio is 1%−5%.
Steel Reinforcement Thumb Rule for Foundation / Raft Footing
Required steel ratio is 0.5% to 8%.
Steel Reinforcement Thumb Rule for RCC Work Volume
Required volume of steel is 0.6% to 1%.