It is a predetermined benchmark established against which actual performance can be measured.
Standard cost
It is a predetermined cost established for a unit of product, service, or activity based on specified expectations regarding the quantity and price of resources required.
Ideal standards
This represent performance under conditions in which operations proceed perfectly or with virtually no inefficiency.
Can serve as aspirational benchmarks but less appropriate as the sole basis.
Practical or attainable standards
This represent efficient levels of performance that can reasonably be achieved under normal operating conditions.
More useful because they provide employees and managers with a realist performance benchmark.
Standard costing system
It is a managerial accounting system that establishes predetermined cost and operating standards, measures actual performance, compares actual results with standards, and analyzes significant differences to support management decision-making.
Establish the standard
Management determines the expected cost of a product or service under specifies operating conditions.
Measure actual performance
Record the actual resources consumed and costs incurred.
Compare actual results with standards
Compare actual performance with the applicable standards.
Identify variances
Determine the differences between actual and standard results.
Investigate significant variances
Identify the causes of significant deviations from standards.
Take corrective action
Address the causes of significant variances and implement measures to improve performance.
Management by exception
A management approach in which attention is focused primarily on significant deviations from expected performance.
Variance analysis
It is the systematic process of comparing actual costs and operating results with standard or budgeted amounts and analyzing the differences to identify their causes and managerial implications.
Standard price or rate
Standard quantity or hours
Two fundamental components used throughout variance analysis
Standard price or rate
It is the amount that the organization expects to pay for one unit of an output.
Standard quantity or hours
It is the amount of an input that should be used to produce the actual output achieved under the established operating standard.
General Model of Standard Cost Variance Analysis
It separates the total cost variance into price or rate variance and quantity or usage variance.
Price or rate variance
It compares the actual cost with the adjusted cost to identify the effect of paying a price or rate different from the standard.
Quantity or usage variance
It compares the adjusted cost with the standard cost to identify the effect of using a quantity different from the standard allowed.
Favorable variance (F)
A variance when actual cost is lower than the standard cost allowed for the actual output.
Unfavorable variance (U)
A variance when actual cost is higher than the standard cost allowed for the actual output.
Lower-quality materials
Lower-skilled labors
It may result in favorable price variance but an unfavorable quantity/usage variance because it requires more.
Material price variance (MPV)
It measures the difference between the actual price paid for materials and the standard price that should have been paid, based on the actual quantity purchased or used.
Material quantity variance (MQV)
It measures the difference between the actual quantity of material used and the standard quantity allowed for the actual output produced.
Labor rate variance (LRV)
It measures the difference between the actual wage rate paid and the standard wage rate for the actual hours worked.
Labor efficiency variance (LEV)
It measures the effect of using more or fewer labor hours than the standard hours allowed for actual output.
Variable overhead rate/Spending variance
It measures the difference between actual variable overhead and standard variable overhead for actual activity.
Variable overhead efficiency variance
It measures the effect of using more or fewer activity hours than the standards hours allowed for actual production.
FOH spending variance
It measures the difference between actual fixed MOH incurred and the budgeted fixed MOH.
FOH volume variance
It measures the effect of producing at a level different from the level of activity used to established the FOH application rate.