CIVL-4420 Exam 1 (Module 1, 2, and 3)

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/52

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 12:19 PM on 9/29/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

53 Terms

1
New cards

*How many levels are in a Work Breakdown Structure?

Depends on the project

2
New cards

*What is the 100% rule for a WBS?

A WBS must cover 100% of the work to be performed under the project and all project deliverables.

3
New cards

*What is the difference between a general and a supplementary condition?

General: Standard condition Supplementary: Modified or non-standard condition ("…deleted and changed to…")

ON EXAM: "Is this a general or supplementary condition?"

4
New cards

*What is the difference between prescriptive and performance specifications?

Prescriptive: dictates the exact materials, equipment, and installation methods

Performance: defines the desired end results, operational functions, and compliance criteria without dictating the exact methods or materials used to achieve them

ON EXAM: "Is this a prescriptive or a performance specification?"

5
New cards

*What is wrong with Payback Period?

Doesn't take into account the time value of money.

6
New cards

*When comparing multiple projects, why do you assume inflation equals zero?

All projects experience the same inflation.

7
New cards

*What do the following NPV values mean? NPV = +$10k NPV = 0 NPV = -$10k

NPV = +$10k: Making $10k more than the required rate of return. Project is feasible.

NPV = $0: You're making exactly the required rate of return (k) after the investment

NPV = -$10k: Project isn't acceptable

8
New cards

*Can you use NPV, IRR, and PI to compare projects with different durations?

NO! you can only use NPV, IRR, and PI for projects that have the SAME duration. For projects with different durations you use EAA.

ON EXAM: you will be given projects with different durations and will be asked to compare them. USE EAA!!!

9
New cards

What is a project?

A temporary endeavor undertaken to create a unique product

10
New cards

What are the 5 project characteristics?

  1. Defined goals or objective
  2. Composed of specific tasks not routinely performed
  3. Defined beginning and end
  4. Defined deliverables
  5. Consumes resources
11
New cards

What is the project life cycle for the owner/client?

Initiation, Planning, Bidding, Execution, Closure

12
New cards

is the Operation and Maintenance part of a project life cycle?

NO!

13
New cards

What is the project life cycle for a contractor and where does it start in relation to the project life cycle for a owner/client?

Initiation, Planning, Execution, Closure.

Starts after Planning and before Bidding in a owner/client project life cycle.

14
New cards

When does the bidding submission and contractor selection happen in both owner and contractor project life cycles?

owner: Bidding

contractor: Planning

15
New cards

What is project management?

The application of knowledge, skills, tools, and techniques to meet specific project objectives.

16
New cards

What is a project manager?

A trained professional who leads the project team through all project phases and within identified project constraints.

17
New cards

What are the responsibilities of a project manager?

Main: successful accomplishment of project objectives

Facilitate communication among stakeholders

Address stakeholders needs

18
New cards

What are the project constarints

Scope Cost Schedule Quality Risk Resources

19
New cards

What are the six dimensions of effective leadership?

1) Ethics and Integrity 2) Problem solving and decision making skills 3) Negotiation and conflict management skills 4) Technical skills 5) Planning and execution skills 6) Team management and interpersonal skills

20
New cards

What is the definition of ethics?

Set of moral principles that govern a persons behavior.

21
New cards

What is the definition of integrity?

Quality of consistently acting in an ethical manner.

22
New cards

Why is ethics important?

It is easier to assist workers with strong ethical principles in learning and developing the other necessary skills then to try to make a unethical worker honest and reliable

23
New cards

What are the 5 stakeholder groups that ethical responsibilities are divided up into?

1) Society 2) Natural and Built Environment 3) Profession 4) Clients and Employees 5) Peers

24
New cards

what are the four set priorities for effective decision making?

By priority: 1) Ethical concerns 2) Legal concerns 3) Project objectives 4) Stakeholders' objectives

25
New cards

What two things are essential for before a negotiation

Knowledge and preparedness

26
New cards

What are the main risks that may trigger a legal team intervention?

Poorly written contracts or ambiguous contract language Contract formation issues Design errors or omissions Unfair or unreasonable contract provisions

27
New cards

What's the most important risk mitigation and control practices that a project manager could use?

Effective document management practices

28
New cards

What are the requirements to form a contract?

Offer Acceptance Meeting of Minds Consideration Legal Basis Competent Parties

29
New cards

What type of people are not permitted to enter into a bidding contract?

Minors and people who are determined to be insane.

30
New cards

What is the most common type of contract in construction?

Express contract

31
New cards

What is a quasi contract?

Exception in court where the situation isn't fair for one party so the court creates a contract.

32
New cards

What are industry standard forms?

Contract document standards that were tested in court.

33
New cards

What documents are included in the Invitation for Bids?

Instruction to bidders General and Supplementary conditions Technical Specifications Plans and drawings

34
New cards

How does a surety bond work?

Owner makes a claim to the insurance company. Insurance company pays owner. Contractor reimburses the insurance company.

35
New cards

What is a bid bond?

Protects owner if winning bid is not honored by contractor

36
New cards

What is a performance bond?

Protects owner if contractors default or have poor performance

37
New cards

What is a payment bond?

Guarantees that all contractors' subcontractors and suppliers will be paid.

38
New cards

What is a type 1 differing site condition?

Conditions materially different from contract documents

39
New cards

What is a type 2 differing site condition?

Conditions materially different from those that an ordinary contractor would expect to encounter

40
New cards

What is the definition of Liquidated Damages?

The sum of money that the aggravated party in a contract should get as total compensation if the other party breaches a specific part of the contract.

41
New cards

Why wouldn't liquidated damages be charged to a contractor?

delays that occur due to unforeseeable causes beyond control.

42
New cards

What does a time extension provision describe?

Describes conditions where the owner is obliged to extend the time that a contractor has to complete a contract.

43
New cards

What does a price adjustment provision describe?

Clauses that allow for changes in contract prices for fluctuations in prices for materials

44
New cards

What is the most common provision used in a multi-year contract?

Price adjustment provision

45
New cards

What is the most common cause for construction disputes?

Errors and omissions in contract documents.

46
New cards

What is a Tort claim?

Breach in performance of duties that the law says people have to owe another regardless of the existence of any type of contract

47
New cards

When someone makes a Tort Claim is there a contract already in place?

NO

48
New cards

What are the types of tort damages?

Personal injury property damages economic loss (only if you have a contractual claim)

49
New cards

What is the economic loss rule for tort claims?

Can only claim economic loss if you have a contractual claim

50
New cards

What are the types of Tort claims and what are some examples?

Intentional: Battery

Negligent: not intentional

51
New cards

What is mediation?

A voluntary process of formal discussion with a neutral third party to resolve disputes Not enforceable by law

52
New cards

What is a Arbitration?

A more formal dispute resolution process where a arbitrator is selected to make the final decision on a dispute. Enforceable by law Private

53
New cards

What is a Litigation?

Disputes are resolved in a public court system. Usually both parties are represented by legal counsel. Most expensive