Design for serviceability - preliminary design

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/14

encourage image

There's no tags or description

Looks like no tags are added yet.

15 Terms

1
New cards

what is the first objective of preliminary design for serviceability?

approximation to cross-sectional dimensions and effective prestress

2
New cards

how do we approximate depth of a beam if span < 36m

h(m) = span/25 + 0.1

3
New cards

how do we approximate depth of a beam if span >36m?

h(m) = span/20

4
New cards

what 2 assumptions are made when approximating effective prestress at midspan?

  • usually lever arm is between 0.5h and 0.8h → a=0.6h

  • if self-weight represents 50-60% of Mserv then Msw = 0.5Mserv


5
New cards

based on assumptions how can effective prestress be approximated?

Pe 0.6 h = Mserv

6
New cards

what is Pe approximately for a rectangular section?

1700 h3 kN

7
New cards

how is minimum cross-sectional area determined?

assume average compressive stress in service at 20% of concrete compressive strength,

C=0.2fcdAc, T=Pe

Pe=0.2fcdAc=0.2(fck/1.5)Ac

Ac=Pe/(0.13fck)

8
New cards

if approximate effective stress at midspan is 1700h3kN, what is minimum cross-sectional area?

Ac,min = (1.7×106 h3)/0.13fck= 1.3 × 107 h3/fck

9
New cards

when can you use the effective prestress and minimum area approximations?

only for first estimates

10
New cards

how is initial prestressing force at transfer calculated?

P0=Pjack - ΔPi = 0.8-0.95Pjack

11
New cards

what actions are included when calculating prestressing force at transfer

self-weight only with partial safety factor

12
New cards

what are the allowable stresses in the concrete at transfer?

  • top fibre - no tension allowed

  • bottom fibre - compression limited to 60% of characteristic strength at age of transfer


13
New cards

how is effective prestressing force in service calculated?

P = Pjack - ΔPi - ΔPc+s+r

14
New cards

what combination of actions are included when calculating effective prestressing force in service?

self-weight + dead loads + live loads

15
New cards

what are the allowable stresses in the concrete when in service?

  • in compression - limited to 45% of the characteristic compressive concrete strength

  • in tension - not allowed