what is the first objective of preliminary design for serviceability?
approximation to cross-sectional dimensions and effective prestress
how do we approximate depth of a beam if span < 36m
h(m) = span/25 + 0.1
how do we approximate depth of a beam if span >36m?
h(m) = span/20
what 2 assumptions are made when approximating effective prestress at midspan?
usually lever arm is between 0.5h and 0.8h → a=0.6h
if self-weight represents 50-60% of Mserv then Msw = 0.5Mserv
based on assumptions how can effective prestress be approximated?
Pe 0.6 h = Mserv
what is Pe approximately for a rectangular section?
1700 h3 kN
how is minimum cross-sectional area determined?
assume average compressive stress in service at 20% of concrete compressive strength,
C=0.2fcdAc, T=Pe
Pe=0.2fcdAc=0.2(fck/1.5)Ac
Ac=Pe/(0.13fck)
if approximate effective stress at midspan is 1700h3kN, what is minimum cross-sectional area?
Ac,min = (1.7×106 h3)/0.13fck= 1.3 × 107 h3/fck
when can you use the effective prestress and minimum area approximations?
only for first estimates
how is initial prestressing force at transfer calculated?
P0=Pjack - ΔPi = 0.8-0.95Pjack
what actions are included when calculating prestressing force at transfer
self-weight only with partial safety factor
what are the allowable stresses in the concrete at transfer?
top fibre - no tension allowed
bottom fibre - compression limited to 60% of characteristic strength at age of transfer
how is effective prestressing force in service calculated?
P = Pjack - ΔPi - ΔPc+s+r
what combination of actions are included when calculating effective prestressing force in service?
self-weight + dead loads + live loads
what are the allowable stresses in the concrete when in service?
in compression - limited to 45% of the characteristic compressive concrete strength
in tension - not allowed