21 Terms

1
New cards

Diffusers

Generally in a general duct work system, the duct work is constructed from galvanized steel. However, flexible duct in short segments is preferred for ease of construction to connect...

2
New cards

30%

Ductwork construction is approximately _____ of the cost of an HVAC air-based system

3
New cards

Duct mastic

For sealing ducts at connection points to air handling units, the recommended material is _______

4
New cards

2

The problem with utilizing flexible duct for an entire ductwork system is that flex duct has ____ times the friction or resistance to air flow compared to galvanized steel ductwork

5
New cards

1:1

Concerning ductwork fabrication and construction , the preferred aspect ratio would be ______

6
New cards

Centrifugal ; axial

Concerning air-handling fans, the two most common fan designs are _____ and ____________

7
New cards

Higher cost

In a filter for an HVAC system, the key problem with a pleated-type filter compared to a flat filter is _____.

8
New cards

Ceiling height

Comparing the selection of galvanized steel ductwork, round duct is use less than rectangular because of ________ issues

9
New cards

Damper Control

A feature in an HVAC system for a relief air scheme can be accomplished at the lowest cost by ________.

10
New cards

Natural gas: 5x10^-6 $/BTU, No. 2: 7.14x10^-6 $/Btu cost per Btu is less for natural gas

If gas is available at $0.50 therm and No. 2 oil is available at $1 per gallon, which will be the more economical fuel source based on the cost per Btu?

11
New cards

$6.25

If the gas is available at $0.50 per therm and the efficiency of the utilization is 80 perfect, what is the net cost of heating energy in dollars per million Btu?

12
New cards

1. Where it will minimize the amount of piping required

2. Where noise is generated from the machine wont be heard and disturb occupants

3. Where it has good access to combustible air and a fuel supply

Select all that apply. Which factors should be considered in deciding where to put a central boiler plant for a large building.

13
New cards

Annual Fuel Utilization Efficiency

AFUE

14
New cards

92-95%

What is the nominal AFUE of impulse-type furnaces

15
New cards

blow-down

Boiler _____is a process of removing impurities

16
New cards

5.86

A vapor compression refrigeration machine uses 30kW of electrical power to produce 50 tons of cooling. What is its COP?

17
New cards

Either helical or centrifugal compressors

Chilled water systems use water cooled condensers with what types of compressors installed?

18
New cards

R-410A

What has the refrigerant R-22 been replaced with?

19
New cards

1. Because it is extremely toxic

2. Because it is flammable

Ammonia is an environmentally friendly refrigerant with high performance that is cheap compared to other refrigerants. if it is so great, why is it not used in most applications?

20
New cards

1,500,000 gal

Approximately how much chilled water storage would be required to reduce chiller load by 250 tons for a period of 6 hours

21
New cards

3,000 gal

(1,500,000/10)

Approximately 1,500,00 gal of chilled water storage would be required to reduce chiller load by 250 tons for a period of 6 hours. How much ice storage is required?