gantt chart
scheduling low-volume operations with no fixed routing → visualizes a time schedule
work loading : infinite loading
ignores capacity retsraints
uses a schedule as input
identifies bottlenecks in the schedule
work loading: finite loading
considers capacity constraints
uses a prioritized list of jobs as input
input-output control
capacity control technique to monitor the workflow in a work center
work scheduling : foreward scheduling
start processing a job when it is received regardless of its due date
work scheduling : backward scheduling
begin by scheduling the last activity such that the job is finished on its due date
operation or job sequencing =
short term planning of jobs based on available capacity and priorities → determines the sequence of jobs, start and end times, expected queues
job sequencing : priority rules
decide on the relative priority (sequence) when multiple jobs are waiting at a work center
local priority rules consider only the jobs waiting at the work center
gloval priority rules : also consider workload in remaining work centers
job sequencing : local priority rules
consider only the jobs waiting at the work center
job sequencing : global priority rules
also consider workload in remaining work centers
common priority rules : First come first served
the job that arrived first in the work center
common priority rules : last come first served
the job that arrived last in the work center
common priority rules : earliest due date
the job with the earliest due date, minimizes job tardiness
common priority rules : shortest processing time
the job with the smallest processing time → minimizes mean hob lateness, mean job flow time and numer of jobs in the system
common priority rules : longest processing time
the job with the longest processing time
common priority rules : critical ratio
the job with the smallest ratio of time remaining until due date to its processing time remaining
common priority rules : slack per remaining operation
the job with the smallest ratio slack per remaining operation
measure scheduling effectiveness : job flow time
completion time - time job was first available → measures total time that a job spends in the shop before it is ready (responsiveness)
measure scheduling effectiveness : makespan
completion time of the last job - starting time of the first job → measures the total time to finish a batch of jobs (efficiency)
measure scheduling effectiveness : average number of jobs in the system
sum of individual job flow times / makespan → relates to the size of the queues, work in process inventory ext
measure scheduling effectiveness : job lateness
completion time - due date
measures wheter a job is completed early, on time or too late
→ potentially hides large differences between very early and very late jobs
measure scheduling effectiveness : job tardiness
max(0, completion time- due date)
→ measures how many days after the deadline a job is completed (due date performance)
→ assumes that there is no benefit in finishing a job early
job sequencing : johnson’s rule
sequencing jobs through two subsequent work centers
all jobs go through two successive operations, but have different durations
objective : minimize makespan
optimized production technology OPT (by eli goldratt)
bottleneck activities determine the throughput of the system
bottleneck resources must be used to their full capacity
non-bottleneck resources must be scheduled to suppot bottleneck resources
scheduling in services : managing demand
appointments or reservations
posted schedules
delayed services (backlogs)
scheduling in services : scheduling employees
staffing for peak demand,
floating employees or employees on call
temporary seasonal, or part time employees