Reed Documents that the NRC must approve any changes made:
License, Technical Specifications, Safety Analysis Report(SAR)
Purpose of License?
The NRC issued Reed College a license to have a reactor. It is short and general. The Technical Specifications are an appendix to the license.
Purpose of Technical Specifications
Contains limitations on the operations of the reactor to ensure public safety.
Purpose of SAR?
The analysis that proves that operation of our reactor will not hurt anyone and will ensure public safety. This analyzes all sorts of accidents and radiation events.
Reed Documents that can be changed under 10 CFR 50.54 without NRC approval, provided any changes made do not decrease effectiveness and appropriate records of any changes made are kept:
Requalification plan, Emergency plan, Security plan
Purpose of Emergency Plan?
A general description of how we plan for, and manage, accidents. It does not describe specific actions to take in specific emergencies.
Purpose of Requalification Plan?
A description of how we ensure that operators maintain their competency to operate. SOP 63 implements the requirements of the Requal Plan.
Purpose of Security Plan
A description of how we ensure the security of the reactor and its fuel. Access to this document is restricted. SOP 65 implements the requirements of the Security Plan.
Reed Documents that the NRC does not need to approve at all:
SOPs, EIPs, Administrative Procedures, PCNs, FRM
Purpose of SOPs
The Standard Operating Procedures describe how we perform the operation and maintenance of the reactor.
Purpose of EIPs?
The Emergency Implementation Procedures describe step-by-step how to handle specific emergency scenarios.
Purpose of Administrative Procedures?
This describes the organization and administration of the reactor, such as hierarchy of staff, their duties, required committees and their duties, and how changes are approved.
PCNs
The Procedure Change Notifications are important changes to the facility or its procedures. Operators must review and sign each one issued while they are licensed before operating.
FRM
The Facility Reference Manual includes design features of all major reactor systems and components.
Reed Documents maintained by Environmental Health and Safety:
RAM P&P Manual
RAM P&P Manual
The Radioactive Materials Policy and Procedures Manual details the procedures for receiving, shipping, handling, and disposing of radioactive materials at Reed College.
SOP Decades:
01-09 Operations
10-19 Irradiations
20-29 Checklists
30-39 Systems and Components
40-49 Radiation Monitors
50-59 Health Physics
60-69 Administrative
70-79 Director and ROM Use Only