What are the different project time management processes?

  • Planning Schedule Management

  • Defining Activities

  • Sequencing Activities

  • Estimating activity resources

  • Estimating activity duration

  • Developing the schedule

  • Controlling the schedule



2
New cards

Defining activities involves the specific actions that will produce the project deliverables in enough _ to determine resources and schedule estimates.

identifying, details

3
New cards

Activity list

a tabulation of activities to be included on a project schedule

4
New cards

Milestone

a significant event that usually has no duration

5
New cards

Sequencing activities involves _ the reasons for dependencies and the different types of dependencies.

evaluating

6
New cards

A dependency or a relationship is the sequencing of …

project activities or tasksMa

7
New cards

Mandatory dependencies

inherent in the nature of the work being performed on a project

8
New cards

Discretionary dependencies

defined by the project team, sometimes called soft logic.

9
New cards

External dependencies

involves relationships between project and non-project activities

10
New cards

_ are the preferred technique for showing activity sequencing.

Network diagrams

11
New cards

What do boxes represent in a Precedence diagramming method?

activities

12
New cards

What are the difference types of dependencies between activites in a PDM?

  • finish-to-start

  • start-to-start

  • finish-to-finish

    • start-to-finish


13
New cards

What does duration include?

actual amount of time worked plus elapsed time

14
New cards

Effort is…

the number of work days or hours required to complete a task and does not represent duration.

15
New cards

A three-point estimate is an estimate that includes an…

optimistic, most likely, and pessimistic estimate.

16
New cards

Critical Path Method

Network diagramming technique used to predict total project duration.

17
New cards

critical path

series o factivites that determine the earliest time which the project can be completed.

18
New cards

What is the first step to calculating the critical path?

developing a good network diagram and add the duration estimates for all activities.

19
New cards

How do you calculate the critical path?

The longest path in a network diagram is the critical path.

20
New cards

Free slack or free float

amount of time the activity can be delayed without delaying the early start of any immediately following activities.

21
New cards

Total slack or total float

amount of time an activity may be delayed from its early start without delaying the planned project finish date.

22
New cards

Forward pass determines…

the early start and finish dates

23
New cards

Backward pass determines…

the late start and finish dates

24
New cards

Critical Chain Scheduling considers _ when creating a project schedule and includes buffers to protect the project completion date.

limited resources

25
New cards

Theory of Constraints (TOC): attempts to _ multitasking when resource works on more than one task at a time

minimize

26
New cards

buffer

additional time to complete a taskM

27
New cards

Murphy’s law

if something can go wrong, it will

28
New cards

Parkinsons’s law

work expands to fill the time allowed

29
New cards

Feeding buffer

additional time added before tasks on the critical path

30
New cards

Performance Evaluation and Review Technique (PERT)

network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.