Vocabulary flashcards covering core project scheduling fundamentals and project estimation techniques.

Last updated 10:39 PM on 10/12/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

16 Terms

1
New cards

Project Scheduling

The process of determining when project activities will be performed, the sequence in which they will occur, and the time required to complete them (Project Management Institute [PMI], 2021).

2
New cards

Milestone

A significant point or event in a project that indicates the achievement of an important objective, deliverable, or stage; it represents an achievement rather than work and normally has zero duration.

3
New cards

Activity

A unit of project work that consumes resources and has a measurable duration, distinguished from a milestone which merely marks an achievement.

4
New cards

Project Dependency

A relationship between two activities in which the timing or completion of one activity affects another activity, showing which activities must occur before, after, or alongside others.

5
New cards

Finish-to-Start (FS)

The most common dependency relationship, where one activity must finish before another activity can start.

6
New cards

Start-to-Start (SS)

A dependency relationship where one activity must start before another activity can start, allowing activities to continue at the same time.

7
New cards

Finish-to-Finish (FF)

A dependency relationship where one activity must finish before another activity can finish.

8
New cards

Start-to-Finish (SF)

A less common dependency relationship where one activity must start before another activity can finish.

9
New cards

Critical Path

The longest sequence of dependent activities in a project network that determines the shortest possible time in which the project can be completed.

10
New cards

Float (or Slack)

The amount of time an activity can be delayed without delaying the overall project completion date.

11
New cards

Zero Float

The characteristic condition of activities located on the critical path, meaning any delay to these activities will delay the entire project.

12
New cards

Project Estimation

The process of predicting the time, cost, resources, or effort required to complete a project or its activities.

13
New cards

Top-Down Estimating

An estimating approach that begins with an estimate for the entire project and then divides or allocates it among the project's components (Whole → Parts).

14
New cards

Bottom-Up Estimating

An estimating approach that involves estimating each individual activity or work package and then adding them together to determine the total project estimate (Parts → Whole).

15
New cards

Parametric Estimating

An estimating technique that calculates costs or durations by multiplying a measurable unit quantity by a known unit rate derived from historical information.

16
New cards

Parametric Estimating Formula

Estimate=Quantity×Unit Rate\text{Estimate} = \text{Quantity} \times \text{Unit Rate}