Construction activities
— are not independent.
An activity may depend on:
completion of another activity;
availability of a work area;
availability of materials;
availability of labor;
availability of equipment;
inspection or approval.
An activity may depend on:
completion of another activity;
availability of a work area;
availability of materials;
availability of labor;
availability of equipment;
inspection or approval.
Activity sequencing
— is a logical representation of how construction work can or must occur.
Predecessor
An activity that occurs before another activity.
Successor
An activity that follows another activity.
Sequential activities
— occur one after another because the successor depends on the predecessor.
Parallel activities
— can reduce total project duration.
Parallel activities
— can occur at the same time, provided that their required conditions are satisfied.
Parallel activities
may proceed simultaneously if sufficient:
workers;
materials;
equipment; and
work areas
are available.
Physical Completion
Resource Availability
Material Availability
Approval / Inspection
Work Area Availability
An activity may depend on:
Physical Completion
Example: Walls must be constructed before painting.
Resource Availability
Example: Concrete placement requires an available concrete pump.
Material Availability
Example: Window installation requires delivery of the window units.
Approval / Inspection
Example: Concrete placement may require required inspection or approval before proceeding, depending on project procedures.
Work Area Availability
Example: Floor finishing requires the area to be sufficiently ready and accessible.