Activity list

Master record of each unit of work: ID, verb-noun description, predecessors/successors, resources, and assumptions/constraints; each activity is sized at roughly 8–80 hours of effort

2
New cards

Work package vs. activity

Lowest WBS level describing what is delivered vs. the decomposed unit describing how the work gets done

3
New cards

Finish-to-Start (FS)

B can't begin until A ends; the most common dependency (e.g., testing after coding)

4
New cards

Start-to-Start (SS)

B can't begin until A begins (e.g., documentation once drafting begins)

5
New cards

Finish-to-Finish (FF)

B can't end until A ends (e.g., quality review closes after inspections)

6
New cards

Start-to-Finish (SF)

B can't end until A begins; rare (e.g., night shift ends when day shift starts)

7
New cards

Mandatory dependency

Hard logic; cannot be changed

8
New cards

Discretionary dependency

Soft logic based on best practice; can be changed, and is the only kind that allows overlapping activities

9
New cards

External dependency

Relationship driven by something outside the team's control (e.g., permits); carries risk

10
New cards

Precedence Diagramming Method (PDM)

Network diagram format where activities are nodes; each node shows duration, ES, EF, LS, LF, and float

11
New cards

Analogous duration estimate

Based on similar past projects; fast and cheap but least accurate, so suited to early stages

12
New cards

Parametric duration estimate

Statistical rate applied to quantity (e.g., 100 m of cable = 2 days, so 500 m = 10 days)

13
New cards

Three-point (PERT) estimate

Expected time = (O + 4M + P) ÷ 6; standard deviation = (P − O) ÷ 6

14
New cards

Duration estimate: expert judgment

Use experienced people to validate other estimates or when the work is new

15
New cards

Forward pass

Left-to-right calculation (EF = ES + duration) that yields the earliest project finish

16
New cards

Backward pass

Right-to-left calculation (LS = LF − duration) that yields the latest dates that don't delay the project

17
New cards

Total float

LS − ES (or LF − EF); slack shared along an entire path

18
New cards

Free float

ES of the successor − EF of the activity; slack belonging to one activity alone

19
New cards

Critical path

Longest path through the network; zero slack, so any delay pushes the end date

20
New cards

Crashing

Compressing the schedule by adding resources or overtime; always raises cost; main risk is diminishing returns; do the cheapest cost-per-day first

21
New cards

Fast-tracking

Compressing the schedule by overlapping activities planned in sequence; no direct cost increase; main risk is rework

22
New cards

Which activities get schedule compression?

Critical-path activities only

23
New cards

Milestone

Zero-duration event marking a point in the project (e.g., "Go-Live")

24
New cards

Gantt chart

Most common schedule format; bars plotted on a timeline

25
New cards

Schedule baseline

Approved schedule; altered only via formal change control; basis for SV and SPI

26
New cards

Cost estimate: analogous

Uses similar past projects; used at initiation; accuracy −25% to +75%

27
New cards

Cost estimate: parametric

Uses a statistical rate such as $/sq ft; used in planning; accuracy −10% to +25%

28
New cards

Cost estimate: bottom-up

Estimate each work package, then roll up; detailed planning; accuracy −5% to +10%

29
New cards

Contingency reserve

Covers known unknowns (identified risks); controlled by the PM; included in the cost baseline

30
New cards

Management reserve

Covers unknown unknowns; controlled by senior management/sponsor; excluded from cost baseline but included in total project budget

31
New cards

Cost aggregation sequence

Work package estimates → control accounts → project estimate → + contingency = cost baseline → + management reserve = total project budget

32
New cards

Funding-limit reconciliation

Rescheduling work so planned spending fits within the tranches in which funds are released

33
New cards

PV (BCWS)

Budget for work scheduled to be done by now ("what should be done?")

34
New cards

EV (BCWP)

Budget for work actually completed ("what was done?")

35
New cards

AC (ACWP)

Actual cost of the work completed

36
New cards

Reading EVM variances and indices

Variances (CV, SV) negative = bad; indices (CPI, SPI) below 1.0 = bad; SV is in dollars, not days

37
New cards

Quality vs. grade

Meeting requirements (low is always a problem) vs. a category of features (low can be fine; a budget hotel can be high on the first)

38
New cards

Prevention costs

Training, quality planning, design reviews; usually the best return

39
New cards

Appraisal costs

Testing, inspections, audits; finds defects but doesn't stop them from occurring

40
New cards

Internal failure costs

Rework and scrap found before delivery

41
New cards

External failure costs

Warranty claims and returns after delivery; the most expensive cost-of-quality category

42
New cards

Plan Quality

Sets standards and metrics; outputs are the management plan for meeting requirements and the measures used to judge it

43
New cards

Manage Quality

Process-focused and proactive; audits how work is done

44
New cards

Control Quality

Product-focused and reactive; inspects deliverables; output feeds Validate Scope

45
New cards

Fishbone (Ishikawa) diagram

Root-cause tool organized by Man, Machine, Method, Material, Measurement, Mother Nature

46
New cards

Quality checklist

Standardizes required steps using lessons learned

47
New cards

Control chart

Plots process data against limits set at ±3σ from the mean

48
New cards

Rule of seven

7+ consecutive points on one side of the mean signal an assignable cause to investigate

49
New cards

Control limits vs. specification limits

Process behavior vs. customer requirements

50
New cards

Pareto chart

Descending bars plus a cumulative % line; shows the vital few causes (80/20)

51
New cards

PDCA

Plan-Do-Check-Act cycle (Deming); the improvement method

52
New cards

Kaizen

"Change for the better"; small daily gains by everyone; the improvement mindset

53
New cards

Verification

Building the product right: internal check against specs

54
New cards

Validation

Building the right product: done with the customer (e.g., UAT)

55
New cards

Acceptance criteria

Measurable conditions agreed on during planning, before work begins

56
New cards

Risk vs. uncertainty

Specific event with estimable probability and impact (plan for it) vs. vague lack of knowledge with no probability (handle with buffers and adaptability)

57
New cards

Opportunity

Positive uncertain event; logged in the same register as threats

58
New cards

Risk management loop

Identify → Analyze → Plan Responses → Monitor → back to Identify; revisit at every milestone

59
New cards

Risk brainstorming

Most common identification technique; quantity first, judge later, with a facilitator

60
New cards

Risk checklist

Built from past projects; fast but misses new risks; a starting point only

61
New cards

Assumptions analysis

Asking "what if this assumption is wrong?"; unstable assumptions become risks

62
New cards

Best-practice order for identifying risks

Start with checklists, expand with brainstorming, pressure-test with assumptions analysis

63
New cards

Probability-impact matrix

Qualitative tool scoring each risk by likelihood and severity; scales defined up front; high-high needs action now, low-low can be accepted and monitored

64
New cards

Risk register

Living log of each item's description, probability, impact, response, one named owner, and status

65
New cards

Avoid (threat)

Change the plan so the risk can't occur

66
New cards

Transfer (threat)

Shift the impact to a third party (insurance, contracts)

67
New cards

Mitigate (threat)

Reduce probability and/or impact; the most common response

68
New cards

Accept (threat)

Take no proactive action; document and monitor

69
New cards

Exploit (opportunity)

Make sure the opportunity happens

70
New cards

Share (opportunity)

Partner with a third party better able to capture it

71
New cards

Enhance (opportunity)

Increase the opportunity's probability and/or impact

72
New cards

Accept (opportunity)

Don't pursue it, but still document it

73
New cards

Choosing a risk response

Compare response cost to expected loss; consider risk appetite; re-score what's left afterward

74
New cards

Residual risk

Exposure remaining after a response is applied

75
New cards

EMV

Probability × impact, summed across risks; one way to size contingency (others: 5–15% of budget, or expert judgment + historical data)

76
New cards

RAID log

Risks, Assumptions, Issues, Dependencies; each entry needs owner, due date, status; reviewed at kickoff, weekly, at milestones; archived at close

77
New cards

Risk vs. issue

Future and uncertain (plan for it) vs. present and certain (resolve it); a risk that occurs with no plan becomes the latter

78
New cards

Communications matrix

Answers who needs what information, when, in what format, from whom, and by which method

79
New cards

Interactive communication

Two-way, real time (meetings, calls); best for complex issues and decisions

80
New cards

Push communication

Sent to specific recipients (email, memos, reports); best for status updates

81
New cards

Pull communication

Recipients retrieve it when needed (portals, wikis, shared drives); best for large audiences

82
New cards

Communication channels formula

n(n − 1) ÷ 2; 10 people = 45, 20 people = 190

83
New cards

Status report

Where the project stands right now

84
New cards

Progress report

What was completed this period

85
New cards

Forecast report

Where the project is heading (EAC, ETC)

86
New cards

Variance report

Deviation from baseline plus root cause

87
New cards

Dashboard

Displays KPIs with red/yellow/green status

88
New cards

Information radiator

Large visible display (Kanban board, burndown chart); common in Agile

89
New cards

Make (vs. buy)

Choose when work is core, sensitive/proprietary, or you have idle capacity

90
New cards

Buy (vs. make)

Choose when you need special expertise, lack capacity, need speed, or the work is one-time

91
New cards

Procurement process

Plan (needs, SOW, selection criteria) → Conduct (solicit, evaluate, award) → Control (performance, changes, payments) → Close (acceptance, final payment, lessons learned)

92
New cards

Statement of Work (SOW)

Defines scope, location, period of performance, and acceptance criteria; vagueness here is the root cause of most disputes

93
New cards

Source selection criteria

Price, technical capability, past performance, management approach; set before bidding

94
New cards

RFI

Learn about the market; no commitment

95
New cards

RFP

For complex needs; asks vendors for both a technical and a cost proposal

96
New cards

RFQ

For a well-defined item; price is the main factor

97
New cards

IFB

Government sealed bidding; lowest responsive, responsible bidder wins

98
New cards

Fixed-price contract

Seller bears cost risk; best for well-defined scope; highest buyer cost certainty. Variants: FFP, FPIF (target + ceiling), FP-EPA (inflation adjustment)

99
New cards

Cost-reimbursable contract

Buyer bears cost risk; best for uncertain scope; lowest buyer cost certainty. Variants: CPFF (fixed fee), CPIF (fee tied to cost vs. target), CPAF (subjective award fee)

100
New cards

Time & materials contract

Hourly rate plus materials; cost risk mostly on buyer; limited certainty; best for low-to-medium scope clarity; capped by a not-to-exceed (NTE) limit