Construction Management and Engineering Examination Review

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/44

flashcard set

Earn XP

Description and Tags

Comprehensive vocabulary flashcards covering construction management, scheduling (CPM), building codes, OSHA regulations, cost accounting, estimating calculations, and structural components.

45 Terms

1
New cards

Retainage

The difference between the gross earned amount and the amount actually paid to the contractor, withheld to encourage the general contractor to complete the project per contract requirements.

2
New cards

Activity Duration Calculation

The estimating method used to calculate task duration by dividing the plan quantity by the daily production rate (Plan Quantity/Daily Production Rate\text{Plan Quantity} / \text{Daily Production Rate}).

3
New cards

Schedule of Values

A contractor's proposed itemized breakdown of the total project contract sum into individual pay items, utilized for evaluating progress payments.

4
New cards

Topographical Map

A site drawing showing contour lines and ground elevations.

5
New cards

Reinforcing Steel Location (Concrete)

The structural positioning of rebar placed specifically where concrete experiences tension forces.

6
New cards

Value Engineering

A systematic evaluation of a project design, during planning or bidding, to suggest alternative materials or methods that reduce costs without degrading quality.

7
New cards

OSHA Portable Ladder Extension Rule

The safety rule mandating that a portable ladder must extend at least 3 ft3\,\text{ft} above the upper landing surface being accessed.

8
New cards

Back Charge

A financial deduction made by a general contractor from a subcontractor's contract amount to recover costs for repairing faulty work or completing deficient tasks.

9
New cards

A-C Plywood

A grade stamp indicating a panel with an AA-grade smooth front veneer and a CC-grade back veneer.

10
New cards

OSHA Fall Protection Threshold

The maximum allowable height of 6 ft6\,\text{ft} on an open-sided floor before perimeter fall protection systems must be provided.

11
New cards

Tempered Glass

Treated safety glass that breaks safely into small, dull granular pieces rather than jagged shards upon fracture.

12
New cards

Expediting

The material control activity of tracking, verifying progress, and accelerating vendor deliveries to ensure materials arrive on the jobsite on schedule.

13
New cards

UniFormat

A standardized CSI classification system organized around building systems and assemblies, primarily used in conceptual estimating.

14
New cards

Finish to Start (FS)

A network scheduling precedence relationship in which the start of a successor activity depends on the completion of the preceding activity.

15
New cards

Differing Site Conditions (DSC) Clause

A contractual provision where a claimant seeking equitable adjustment must establish that the contractor performed a site visit and encountered concealed conditions differing from contract representations.

16
New cards

Psychrometric Chart

A thermodynamic graph used to determine dew point, relative humidity, and enthalpy across varying dry-bulb and wet-bulb temperatures.

17
New cards

Actual Size of a 2x8 Board

The dressed surfaced dimensions of a nominal 2×82 \times 8 piece of lumber, measuring 112 in1\frac{1}{2}\,\text{in} thick by 714 in7\frac{1}{4}\,\text{in} wide.

18
New cards

Davis-Bacon Act

Federal legislation mandating that contractors pay laborers and mechanics wages that are not less than the prevailing wage rates determined for the project locality.

19
New cards
<p>Elevated Slab Form System Components</p>

Elevated Slab Form System Components

The structural components of an elevated slab formwork assembly sequenced from the topmost layer downwards: Deck (or Sheathing), Joist, Stringer, and Shore.

20
New cards
<p>Simple Beam Maximum Shear</p>

Simple Beam Maximum Shear

The highest internal shear force developed in a simply supported beam; for a 20-ft20\text{-}\text{ft} span carrying a concentrated load P=40 kipsP = 40\,\text{kips} located 5-ft5\text{-}\text{ft} from the left end (reactions: 30 kips30\,\text{kips} left, 10 kips10\,\text{kips} right), the maximum shear is 30 kips30\,\text{kips}.

21
New cards
<p>Horizontal Distance (H Distance)</p>

Horizontal Distance (H Distance)

The horizontal projection calculated from a slope measurement using the cosine of the slope angle: for a slope distance of 200 ft200\,\text{ft} at a 15∘15^\circ angle, H=200 ft×cos⁡(15∘)=193.19 ftH = 200\,\text{ft} \times \cos(15^\circ) = 193.19\,\text{ft}.

22
New cards

Free Float

The duration an activity can be delayed without delaying the early start date of any immediately succeeding activity, calculated as: Earliest Start of Next Activity−Early Finish of Current Activity\text{Earliest Start of Next Activity} - \text{Early Finish of Current Activity}.

23
New cards

Air Entrainment

The intentional inclusion of microscopic air bubbles in a concrete mix to improve workability and enhance resistance to freeze-thaw degradation.

24
New cards

Control Joint

A planned groove or cut placed in concrete slabs to accommodate drying shrinkage and regulate where cracking occurs.

25
New cards

Unit Price Contract

A contract model specifying reimbursement based on fixed stated dollar rates multiplied by field-measured quantities installed.

26
New cards

Concrete Free-Fall Limit

The threshold of 4 ft4\,\text{ft}, beyond which unconfined dropping of fresh concrete leads to segregation of coarse aggregates from the cement-water paste.

27
New cards

Escalation

A contingency allowance budgeted into long-term construction contracts to account for future market inflation in labor and material prices.

28
New cards

Critical Path

The longest continuous chain of dependent tasks through a project schedule network having a total float value of zero, defining the minimum project duration.

29
New cards

Fast-Track Construction

A delivery approach where construction activities are initiated prior to the full completion of design drawings and specifications.

30
New cards

Request for Information (RFI)

A formal submission by a contractor requesting clarification, interpretation, or resolution of drawing discrepancies from the design professional.

31
New cards

Work Breakdown Structure (WBS)

A hierarchical framework dividing total project scope into manageable work packages, tasks, and sub-elements.

32
New cards

OSHA General Duty Clause

Section 5(a)(1) of the OSH Act obligating employers to provide each worker with an environment free from recognized hazards that cause or are likely to cause death or physical injury.

33
New cards

Forward Pass

The scheduling computational sequence moving left-to-right through a CPM network that calculates Early Start (ES\text{ES}) and Early Finish (EF\text{EF}) dates for all activities.

34
New cards

Straight-Line Depreciation

An accounting method determining annual asset wear: (Cost−Salvage Value)/Useful Life(\text{Cost} - \text{Salvage Value}) / \text{Useful Life}; for a $10,000\$10,000 asset with $1,000\$1,000 salvage value over 5 years5\,\text{years}, depreciation is $1,800 per year\$1,800\,\text{per year}.

35
New cards

Optimum Moisture Content

The soil water percentage that produces the greatest compaction density with the least mechanical compaction effort and reduced subsequent settlement.

36
New cards

Experience Modification Rate (EMR)

An insurance metric quantifying a contractor's worker safety history, where an EMR below 1.01.0 signifies a lower loss rate than the national average.

37
New cards

Crashing

The project schedule compression technique of adding labor or equipment resources to critical path activities to shorten duration at minimal cost.

38
New cards

Builders Risk Insurance

Property damage policy protecting a structure and in-place building materials against losses caused by physical perils (such as storm collapse or fire) during construction.

39
New cards

Sheepsfoot Roller

A compaction roller equipped with projecting tamping feet, ideally suited for compacting cohesive soils like clay.

40
New cards

Modified Proctor Test

A standardized geotechnical laboratory test determining the relationship between dry density and moisture content of compacted soil.

41
New cards

Cardinal Change

A directive issued by an owner that exceeds the contractor's original scope to such an extent that the contractor can legally refuse execution without breach.

42
New cards

Substantial Completion

The point determined by the architect when construction is sufficiently complete for the owner to legally and functionally occupy the building for its intended purpose.

43
New cards

Addendum

A written or graphic modification issued to bidders by the design team to revise or clarify contract documents prior to bid opening.

44
New cards

Proprietary Specification

A specification section that designates a single brand name, model number, manufacturer, or patented design to establish product standards.

45
New cards

Through-Wall Flashing

Continuous moisture barriers placed within masonry cavity walls to collect and redirect penetrating water to the outside via weep holes.