MN HP Piping Code Midterm Review

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/27

flashcard set

Earn XP

Description and Tags

Flashcards prepared from the Minnesota High Pressure Piping Code Midterm Exam covering piping requirements, safety valves, weld specifications, expansion, and support spacing.

Last updated 9:22 PM on 10/6/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

28 Terms

1
New cards

High pressure steam is defined as a pressure in excess of what value?

15 psig15\,\text{psig}

2
New cards

What is the pressure requirement for a hydrostatic test of a power piping system after erection?

1.5×MAWP1.5 \times \text{MAWP}

3
New cards

When are two blowoff valves required on a boiler and its appurtenances?

When the pressure exceeds 100 psig100\,\text{psig} (must have a slow opening valve).

4
New cards

What is the minimum internal diameter required for instrument tubing?

0.36 inch0.36\,\text{inch}

5
New cards

What is the maximum deviation above the S value allowed on power piping systems?

20%20\%

6
New cards

What is an example of an essential variable in a Welding Procedure Specification (WPS)?

Type of filler material

7
New cards

In order for a certified welder to qualify to a new Welding Procedure Specification wherein one or more essential variables are changed, what test must be performed?

A new WPQ (Welder Performance Qualification)

8
New cards

For high pressure boilers and piping, safety valves must discharge at a point of safety not less than what distance from running boards, platforms, or adjacent areas?

Not less than 7 feet7\,\text{feet}

9
New cards

What is the safe maximum load at 650 ∘F650\,^\circ\text{F} of a 5/8 inch5/8\,\text{inch} ASTM A36 threaded rod?

2,160 lb2,160\,\text{lb}

10
New cards

What is the maximum span between supports without concentrated loads for a 12 inch12\,\text{inch} standard steam branch line?

30 feet30\,\text{feet}

11
New cards

What are the two requirements concerning water discharge from a blowdown tank before entering a drain?

  1. Pressure must be less than 5 psig5\,\text{psig} 2. Temperature must be less than 140 ∘F140\,^\circ\text{F}
12
New cards

List the three types of guided bend test specimens.

  1. Side bend 2. Face bend 3. Root bend
13
New cards

Heating media piping systems are understood to include fluids used for heating when pressure and temperature exceed what limits?

Pressure exceeds 30 psig30\,\text{psig} and temperature exceeds 250 ∘F250\,^\circ\text{F}

14
New cards

According to the notes, a qualification test for a Weld Procedure Specification shall be in accordance with which code section?

ASME Section II

15
New cards

Welding on piping directly attached to an ASME Section I boiler up to a functional boundary valve requires what stamp?

PP Stamp

16
New cards

What is the allowable percent increase of stress on hangers for short time overloading conditions?

20%20\%

17
New cards

How much will a 2 inch2\,\text{inch} copper line expand given an installation temperature of 65 ∘F65\,^\circ\text{F}, operating temperature of 378 ∘F378\,^\circ\text{F}, and length of 80 feet80\,\text{feet}?

278 inch2\frac{7}{8}\,\text{inch} (or 2.854 inch2.854\,\text{inch})

18
New cards

What is the definition of stress relieving?

Pipe is brought to required temperature, held at that temperature for a period of time, and then cooled slowly.

19
New cards

Are economizers, heaters, tanks, and other pressure vessels inside or outside the scope of the code?

They are outside the scope of the code, but connecting piping shall conform to the requirements.

20
New cards

What does the acronym OS&Y stand for?

Outside Screw and Yoke

21
New cards

Up to what temperature limit may copper pipe or tubing be used on steam systems?

Provided the temperature is not above 406 ∘F406\,^\circ\text{F}

22
New cards

What percent of total calculated expansion would you cut the pipe short when constructing and installing an expansion loop?

50%50\%

23
New cards

What is the outer diameter (OD) of a 10 inch10\,\text{inch} Class 300 weldneck flange?

1712 inch17\frac{1}{2}\,\text{inch}

24
New cards

What is the maximum span between supports without concentrated loads for a 4 inch4\,\text{inch} extra heavy wall steam branch line?

15 feet15\,\text{feet}

25
New cards

By what methods shall thermal expansion of piping be compensated?

Pipe bends, offsets, expansion loops, and changes in direction

26
New cards

How many safety valves are required for each boiler with over 500 square feet500\,\text{square feet} of water heating surface?

Two or more safety valves

27
New cards

When boilers are connected to a common steam main, what shall the steam connection from each boiler having a manhole opening be fitted with?

Fitted with 2 stop valves and a free blow drain between them

28
New cards

What is the requirement regarding two means of feeding water to a boiler fired by solid fuel?