Vocabulary practice flashcards covering steam boiler principles, firetube and watertube designs, fittings, safety valves, blowdown equipment, and operational standards.

37 Terms

1
New cards

Low Pressure Steam Boiler

A steam boiler having a maximum allowable working pressure (MAWP) of up to 15 psi15\,\text{psi}.

2
New cards

Boiler Horsepower

The evaporation of 34.5 lb34.5\,\text{lb} of water per hour from and at a feedwater temperature of 212∘F212^\circ\text{F}.

3
New cards

Firetube Boiler

A boiler in which heat and gases of combustion pass through the tubes surrounded by water, characterized by a large volume of water relative to horsepower size.

4
New cards

Horizontal Return Tubular (HRT) Boiler

A specific design of firetube boiler.

5
New cards

Heating Surface

The part of a boiler that has heat and gases of combustion on one side and water on the other side.

6
New cards

Thermal Efficiency

The ratio or comparison of heat supplied in fuel to heat absorbed by boiler water.

7
New cards

Baffles

Partitions designed to direct combustion gases into close contact with the boiler heating surface.

8
New cards

Dished Heads

Concave steam and water drum ends that eliminate the need for stays.

9
New cards

Waterwalls

Tubes arranged along furnace walls in watertube boilers to increase the service life of furnace refractory.

10
New cards

Tensile Stress

The type of mechanical stress to which boiler plates and staybolts are subjected when the boiler is pressurized.

11
New cards

Safety Valve

The most important boiler fitting, designed to pop open to prevent internal pressure from exceeding the MAWP.

12
New cards

Superheater Safety Valve

A safety valve set to open before the main steam safety valves open to maintain steam flow and protect the superheater tubes from burning out.

13
New cards

Accumulation Test

A test conducted on a boiler to determine and verify the relieving capacity of its safety valve.

14
New cards

Relieving Capacity

The measure of a safety valve's discharge rate, expressed in pounds of steam per hour capable of discharging under a specified pressure.

15
New cards

Water Column

A vessel whose primary purpose is to reduce turbulence in the gauge glass to provide an accurate reading of the water level.

16
New cards

Try Cocks

Valves installed on the water column providing a secondary means of determining boiler water level.

17
New cards

Whistle Valve

An audible warning valve on the water column that alerts the operator to a high or low water condition.

18
New cards

Steam Siphon

A bent loop of pipe that traps water to protect the steam pressure gauge from direct contact with high-temperature steam.

19
New cards

Hydrostatic Head of Water

The pressure exerted at the base of a vertical column of water, equal to 0.433 psi0.433\,\text{psi} per vertical foot.

20
New cards

Boiler Vent

A fitting at the highest part of the steam side of the boiler, left open during warm-up until internal pressure reaches 10 psi10\,\text{psi} to 15 psi15\,\text{psi}.

21
New cards

Steam Separator

A device designed to separate water from steam by abruptly changing the direction of steam flow.

22
New cards

Dry Pipe

A separator device installed in the upper part of the steam and water drum.

23
New cards

Cyclone Separator

A drum internal used in boilers equipped with superheaters to remove moisture from steam using centrifugal force.

24
New cards

Saturated Steam

Steam that exists at its corresponding saturation temperature and pressure.

25
New cards

Superheated Steam

Steam whose temperature has been increased without an increase in pressure.

26
New cards

Soot Blower Supply Line

A steam piping line connected to the superheater outlet header to supply moisture-free steam to the soot blowers.

27
New cards

OS&Y Gate Valve

An outside screw and yoke gate valve required as a main boiler stop valve because it offers no restriction to the flow of steam.

28
New cards

Automatic Nonreturn Valve

A main stop valve approved by the ASME code that must be installed as close to the boiler shell as practical on the main steam line.

29
New cards

Free-Blowing Drain

A drain opened during boiler warm-up to remove condensate trapped between the two main steam stop valves.

30
New cards

Expansion Bends

Loop-shaped pipe arrangements that allow the boiler main steam line to expand and contract freely during normal usage.

31
New cards

Bottom Blowdown Valves (High Pressure)

Two bottom blowdown valves required by ASME code on boilers operating at 100 psi100\,\text{psi} or higher.

32
New cards

Quick-Opening Blowdown Valve

A bottom blowdown valve positioned between the boiler shell and the slow-opening valve that is opened first and closed last during blowdown.

33
New cards

Maximum Blowdown Line Size

The maximum permissible pipe diameter for bottom and surface blowdown lines, established at 212 in.2\frac{1}{2}\text{ in.}.

34
New cards

Mud Drum

The lowest water-side component of a watertube boiler where bottom blowdown lines are connected.

35
New cards

Boiler Water Analysis

The chemical assessment used as the most accurate means of establishing boiler blowdown frequency.

36
New cards

Surface Tension (Boiler)

The tension of the water surface in the steam and water drum, which is increased by impurities floating on the water.

37
New cards

Blowdown Tank

A holding vessel designed to lower temperature and pressure from boiler blowdown lines before discharge to sewer lines.