1/112
Comprehensive vocabulary flashcards for MGSC 495 covering Production Activity Control (PAC), Scheduling, Theory of Constraints, Capacity Planning, Inventory Planning, Costing, Lot Sizing, and Warehouse Inventory Control.
Production Activity Control (PAC)
The function of routing and dispatching work to be accomplished through the production facility and performing supplier control, encompassing principles to schedule, control, measure, and evaluate operations.
Planning (PAC Aspect)
The phase of PAC that ensures required material, tooling, labor, and information are available to manufacture components when needed, initiates scheduling, and verifies scheduled completion dates can be met.
Implementation (PAC Aspect)
The phase of PAC that puts plans into action by gathering required shop floor information and dispatching authorized orders according to the requirements plan.
Control (PAC Aspect)
The phase of PAC that monitors what is actually happening on the shop floor, compares actual results to the plan to decide if corrective action is needed, and ranks open orders in priority sequence.
Supplier Management in PAC
A collaborative approach that manages outside suppliers by treating them with the same visibility, scheduling coordination, and communication as an internal production department.
Six Inputs to PAC
The essential planning inputs required by PAC: Master Production Scheduling (MPS) / Planned Orders, Item Master file, Bill of Materials (BOM), Routing Files, Work Center Files, and Shop Order Files.
Manufacturing Lead Time
The total span of time required to perform a series of operations, composed of five distinct components: queue time, setup time, run time, wait time, and move time.
Operational Time
The portion of total manufacturing lead time during which work is actively performed on a workstation, mathematically defined as: Operational Time=Setup Time+Run Time.
Internal Setup Time
The time associated with elements of a machine setup procedure that can only be performed while the process or machine is stopped or shut down.
External Setup Time
The time associated with elements of a machine setup procedure that can be performed while the machine or process is actively running.
Operation Setback Chart
A visual timeline chart that shows the backward sequencing of operations from a finished item's due date to determine the required start time for each component and subassembly.

Volume-Variety Matrix
A strategic framework matching product variety and production volume to appropriate manufacturing process types (Project, Work Center, Batch, Line, Continuous) and manufacturing environments (ETO, MTO, ATO, MTS).
Takt Time
The pace of production required to match the rate of customer demand, calculated as: Takt Time=Customer Demand per ShiftAvailable Production Time per Shift.
Cycle Time
The actual average elapsed time spent completing a single unit of product or service from start to finish.
One-Piece Flow vs. Batch Processing
One-piece flow moves single units sequentially between operations to minimize queue and overall throughput time, whereas batch processing runs groups of items, lowering unit setups but dramatically increasing WIP and wait time.
Priority Control
The process of communicating start and completion dates to manufacturing departments via dispatch lists to ensure execution of open shop orders according to relative urgency.
Dispatching
The selecting and sequencing of available jobs to be run at individual workstations and assigning those jobs to specific workers.
Shortest Processing Time (SPT)
A dispatching rule that sequences jobs with the smallest process time first, maximizing the total number of jobs completed while risking delays on long jobs.
Earliest Due Date (EDD)
A dispatching rule that prioritizes jobs based on earliest order due date, aligning with standard MRP outputs to minimize maximum tardiness.
Critical Ratio (CR)
A priority dispatching index calculated as: CR=Shop Time RemainingTime Remaining to Due Date, where values below 1.0 indicate an order is running behind schedule.
Slack Time
A sequencing rule calculated as remaining time until due date minus remaining processing time; jobs with the lowest slack time receive highest priority.
Slack per Remaining Operation (S/RO)
A sequencing metric calculated as: S/RO=Number of Operations RemainingTime Remaining to Due Date−Shop Time Remaining, where the lowest ratio receives the highest priority.
Forward Scheduling
A scheduling technique that starts from a known release or start date and schedules each successive operation forward to compute the earliest possible completion date.
Backward Scheduling
A scheduling technique that starts from an order's required due date and works backward through lead times to determine the latest permissible start date for each operation.
Infinite Loading
A capacity planning method that loads work into work centers in the periods required by due dates, without regard to actual capacity limits.
Finite Loading
A scheduling technique that assigns no more work to a work center than its actual available capacity limit in a given time period, leveling the schedule sequentially.
Overlapped Schedule
A schedule technique where a portion of an order (a transfer batch) is sent to a succeeding work center before the entire batch finishes processing at the current operation.
Transfer Batch
The quantity of an item moved between sequential work centers during production, which may be smaller than the total production batch size to reduce lead time.
Capacity Cushion
The planned reserve margin by which maximum productive capacity exceeds average expected utilization to accommodate unexpected surges in demand or disruptions.
Gantt Chart
A project management bar chart showing activity schedules across time, used to visualize dependencies and identify the critical path of tasks that determine project duration.
Just-In-Time (JIT)
A lean philosophy based on continuous waste elimination and productivity improvement by providing only the required materials, in the required quantity, exactly when needed.
River System Concept (Taiichi Ohno)
The principle formulated by Toyota's Taiichi Ohno stating that the primary goal of lean is connecting all processes into an uninterrupted, even flow from start to finish, treating time as the primary metric.
Theory of Constraints (TOC)
A holistic management philosophy created by Dr. Eliyahu Goldratt stating that any manageable system is limited in achieving higher goal performance by a very small number of constraints.
Five Focusing Steps
The TOC improvement cycle: 1) Identify the constraint, 2) Exploit the constraint, 3) Subordinate everything else, 4) Elevate the constraint, and 5) Repeat by identifying the new constraint.
Bottleneck
A facility, function, department, or resource whose capacity is less than the demand placed upon it, setting the throughput pace for the entire production system.
Capacity-Constrained Resource (CCR)
A resource that is not an immediate bottleneck but operates near full capacity and will become a constraint if its schedule is not carefully managed.

Drum-Buffer-Rope (DBR)
The TOC scheduling method where the Drum sets the pace, the Buffer provides inventory/time protection, and the Rope dictates material release to prevent excess WIP.
Time Buffer (TOC)
A strategic amount of inventory or lead time maintained ahead of a constraint to prevent the bottleneck from starving due to upstream delays.
Input/Output Control (I/O Control)
A capacity control technique that monitors planned versus actual input and output for work centers to detect capacity variances, queue buildups, or lack of work.

Capacity Bathtub Model
An analogy illustrating work center loading: incoming water represents planned input rate, water inside the tub represents backlog/WIP, and drain flow represents rated output capacity.
Backflush
An automated inventory deduction method where component records are reduced only after the finished parent item is recorded as complete, using the bill of materials.
Two-Bin Inventory System
A visual replenishment system where items are drawn from a primary bin; when depleted, a reorder is triggered while demand is met from a secondary buffer bin.
Kanban
A lean pull signaling mechanism (card, electronic flag, or container) that authorizes work centers to produce or withdraw a standard container of parts.

VATI Analysis
A TOC classification system characterizing the logical product and material flow structures through a plant into V, A, T, or I layouts.
V-Plant
A plant structure characterized by divergent flow (one-to-many), where a few basic raw materials diverge into many distinct finished products, such as an oil refinery or sawmill.
A-Plant
A plant structure characterized by convergent flow (many-to-one), where numerous raw materials and subcomponents combine into a single complex finished product.
T-Plant
A plant structure where standardized components are manufactured in linear flow and then assembled into multiple end items in final configuration (many-to-many / assemble-to-order).
I-Plant
A linear, sequential plant structure (one-to-one) where materials move along a common, unchanging series of operations, common in continuous processing.
Pacemaker
In lean manufacturing, the specific resource scheduled directly by customer demand that dictates the pace and rhythm of material flow through an entire value stream.
Heijunka
The lean practice of production leveling by volume and product mix over a specific time horizon to avoid demand fluctuations and minimize inventory buildup.
Available Time
The total theoretical hours a work center is open for production, calculated as: Available Time=Machines×Workers×Hours of Operation.
Utilization
A percentage metric measuring how intensively a resource is actually active compared to total available hours: Utilization=Available HoursHours Actually Worked×100%.
Efficiency
A percentage metric comparing actual output in standard hours against hours actually worked: Efficiency=Hours Actually WorkedStandard Hours of Work×100%.
Rated Capacity
The expected standard output capability of a work center, calculated as: Rated Capacity=Available Time×Utilization×Efficiency.
Demonstrated Capacity
Historical proven capacity computed directly from the average actual output produced by a work center over past time periods.
Productivity
An overall economic measure of production output relative to resource inputs: Productivity=InputOutput.
Ford's $5 Day Policy
Henry Ford's 1914 compensation strategy doubling worker pay to reduce crippling plant turnover (370% in 1913) and absenteeism (10%), resulting in doubled profits.
Vertical Integration
A business strategy where a manufacturer acquires control over multiple upstream supply and downstream distribution stages to guarantee reliable material delivery.
First Time Yield (FTY)
The percentage of units that pass an inspection process without requiring any rework, calculated as: FTY=Total Number of Parts ProcessedNumber of Parts Passing With No Failures.
Final Yield
The proportion of total acceptable units produced after all rework, calculated as: Final Yield=Total Number of Parts ProcessedTotal Number of Parts That Passed.
Overall Equipment Effectiveness (OEE)
A comprehensive operational metric measuring total equipment performance based on availability, performance rate, and quality yield.
Decoupling Inventory
Inventory placed between sequential stages in a manufacturing or distribution network to create operational independence between processes.

Order Decoupling Point (ODP)
The specific boundary in a value stream separating forecast-driven push processes from customer-order-driven pull operations.
Direct Inventories
Inventories that directly enter the production of goods, encompassing raw materials, work in process (WIP), finished goods, and MRO supplies.
Indirect Inventories
Inventories used to support operations or hedge uncertainties without being immediately transformed into product, including transit, buffer, seasonal, and anticipation stocks.
MRO Supplies
Maintenance, Repair, and Operating materials consumed during manufacturing and facility support operations that do not become part of the final product.
Service Parts
Modules, components, and elements retained in inventory specifically for post-sale replacement and equipment repair.
Fluctuation Inventory (Safety Stock)
A permanent inventory cushion held to protect against unpredictable variations in customer demand or replenishment lead times.
Anticipation Inventory
Inventory built up in advance of planned future events, such as marketing campaigns, plant shutdowns, or known demand surges.
Seasonal Inventory
A form of anticipation stock accumulated during slack demand periods to smooth production capacity ahead of predictable seasonal peaks.
Lot-Size Inventory
Inventory accumulated when items are produced or ordered in quantities exceeding immediate demand to exploit price discounts or setup efficiencies.
Cycle Stock
The active component of inventory depleted through regular customer sales and replenished cyclically when batch orders arrive.
Hedge Inventory
A speculative inventory buildup established to buffer against prospective supply risks such as labor strikes, currency shifts, or raw material price increases.
Pipeline Stock (In-Transit Inventory)
Inventory currently in transit between supply chain nodes, owned and financed by one of the trading partners throughout shipment.
ABC Classification
An inventory categorization method based on annual dollar usage: Class A comprises 10–20% of items generating 50–70% of spend; Class B comprises 20% of items and 20% of spend; Class C comprises 60–70% of items generating 10–30% of spend.
Pareto's Law (80/20 Rule)
The management principle stating that roughly 80% of total effects or monetary value arise from 20% of the causes or items.
Inventory Carrying Costs
The cumulative expense of holding inventory over time (typically 10–35% annually), comprising capital cost, storage/warehouse expense, risk/spoilage, and taxes/insurance.
Capital Cost (Cost of Capital)
The opportunity cost of capital invested in inventory, representing interest on borrowed capital or the forgone return on alternative company investments.
Ordering Costs
Fixed costs incurred each time a purchase or production order is placed, including clerical processing, receiving, setup teardown, and invoice payment.
Stockout Costs
The economic impact of inventory depletion, encompassing lost current sales, expediting fees, customer dissatisfaction, and potential loss of future business.
Risk Pooling
A supply chain strategy aggregating demand across multiple channels or locations into a central buffer stock to reduce overall inventory requirements.
Average Inventory
The mean level of inventory on hand over time, calculated for uniform cycles as: Average Inventory=2Q+Safety Stock.
Inventory Turnover
A financial efficiency ratio measuring how frequently inventory is sold and replaced per year: Inventory Turnover=Average Inventory in DollarsAnnual Cost of Goods Sold (COGS).
Days of Supply
A measure of inventory coverage indicating how many days on-hand inventory will sustain demand: Days of Supply=Average Daily Usage in DollarsAverage Inventory on Hand in Dollars.
FIFO (First In, First Out)
An inventory valuation method assuming the earliest acquired inventory units are sold first, leaving ending inventory valued at recent acquisition costs.
LIFO (Last In, First Out)
An inventory valuation method assuming the most recently purchased inventory units are sold first, leaving older costs in ending inventory balance.
Job Costing
A cost accounting method where production costs are accumulated and tracked for each specific, unique job or custom order.
Process Costing
A cost accounting method that averages production expenses across massive runs of homogeneous, standardized products.
Perpetual Inventory System
An inventory recordkeeping system that continuously and automatically records additions and deductions in real time as transactions occur.

Inventory Decision Matrix
A 2×2 framework defining replenishment rules based on order quantity (Fixed Q vs. Variable S) and order frequency (Variable R vs. Fixed T).
Min-Max System
An order point inventory system where the minimum level (Min) triggers an order, and the order quantity brings inventory up to a predetermined maximum level (Max).
Safety Lead Time
An element of time added to standard replenishment lead time to ensure goods arrive earlier than their actual need date, protecting against lead time variability.
Demand During Lead Time (DDLT)
The total amount of inventory expected to be consumed between the moment a replenishment order is placed and when it arrives.
Lot-for-Lot (LFL)
A dynamic lot-sizing technique that plans order quantities exactly equal to the net requirements of each specific period, minimizing holding costs but maximizing orders.
Economic Order Quantity (EOQ)
A fixed order quantity formula that balances holding costs and ordering costs to find the minimum total cost lot size: EOQ=CH2CpDˉ.
Periodic Order Quantity (POQ)
A lot-sizing rule calculating order quantities based on the economic time interval derived from dividing EOQ by average period demand.
Part Period Balancing (PPB)
A dynamic lot-sizing technique that evaluates future period demands using a look-ahead/look-back routine to equate cumulative carrying costs to order costs.
Wagner-Whitin (WW) Algorithm
A dynamic programming algorithm that evaluates all possible combinations of ordering to satisfy net requirements over a planning horizon to yield the lowest theoretical cost.
Level of Service
A customer satisfaction metric measuring the percentage of customer orders or demand filled complete and on time directly from stock.
Mean Absolute Deviation (MAD)
A statistical measure of forecast error calculated as the average absolute difference between actual demand and forecast values, approximately related to standard deviation by: σ≈1.25×MAD.